**Executive Summary**
The Department of Atomic Energy (DAE) has allocated ₹20,000 crore under the Nuclear Energy Mission for the research, design, development, and deployment of Small Modular Reactors (SMRs). Bhabha Atomic Research Centre (BARC) is leading the design and development of three SMR types: BSMR-200, SMR-55, and a high-temperature gas-cooled reactor for hydrogen generation. Lead units are slated for establishment at DAE sites for technology demonstration.
**Key Points / Main Content**
* **Budgetary Allocation and Scope:**
* A total budgetary provision of ₹20,000 crore has been made under the Nuclear Energy Mission for fiscal year 2025-26.
* This funding is designated for the research, design, development, and deployment of Small Modular Reactors (SMRs).
* **SMR Development by BARC:**
* Bhabha Atomic Research Centre (BARC), a unit of the Department of Atomic Energy (DAE), is undertaking the design and development of SMRs.
* The SMRs under development include:
* 220 MWe Bharat Small Modular Reactor (BSMR-200).
* 55 MWe Small Modular Reactor (SMR-55).
* Up to 5 MWth High temperature gas cooled reactor (HTGCR) for hydrogen generation.
* Lead units of these SMRs will be established at DAE sites for technology demonstration.
* **Estimated Fund Utilization by BARC:**
* Development and Construction of BSMR-200: ₹5960 crore.
* Development and Construction of SMR-55 (2 units): ₹7000 crore.
* Design and construction of High Temperature Gas Cooled Reactor (HTGCR): ₹320 crore.
* Design, engineering & development works for new reactors: ₹800 crore.
* Civil and General Infrastructure Development for reactors complex: ₹452 crore.
* **Progress of SMRs:**
* **BSMR-200:** In-principle approval received from the Atomic Energy Commission (AEC). Proposal for administrative and financial sanction cleared by AEC for submission to the Cabinet Committee.
* **SMR-55:** In-principle approval received for the project.
* **HTGCR:** In-principle approval received. Detailed Project Report (DPR) prepared. Siting consent received, and Terms of Reference (ToR) for environmental clearances obtained from the Ministry of Environment, Forest and Climate Change (MoEF&CC).
* **Indigenous Development and Collaboration:**
* "Advanced Purified Reactor Vessel Alloy (ApuRVA)" and technology for forgings for reactor pressure vessels of BSMR-200 and SMR-55 have been developed indigenously in collaboration with Indian Industries.
* The control rod drive mechanism has been developed in-house.
* Necessary technology for reactor deployment is available domestically.
* Majority of equipment will be manufactured by Indian Industries with technological support from BARC.
* **Joint Development and Construction Timeline:**
* Bharat Small Modular Reactor (BSMR) is jointly designed and developed by BARC and Nuclear Power Corporation of India Limited (NPCIL).
* Estimated construction time for BSMR is 60 to 72 months from the receipt of administrative and financial approval.
* **Source of Information:**
* This information was provided by the Union Minister of State (Independent Charge) for Science & Technology and Earth Sciences, and Minister of State in the Prime Minister's Office, Personnel, Public Grievances and Pensions, Atomic Energy and Space, Dr. Jitendra Singh, in a written reply in the Lok Sabha.
**Impact Analysis**
* **Bhabha Atomic Research Centre (BARC)**
* **Impact:** BARC is leading the design and development of multiple SMR types and will be involved in the technological handholding of Indian industries for manufacturing equipment. They will also oversee the establishment of lead units for technology demonstration.
* **Action Required:** Continue with design and development works, secure necessary approvals, and collaborate with Indian industries for manufacturing.
* **Indian Industries**
* **Impact:** Indian industries will be engaged in the manufacturing of equipment for the SMRs, leveraging domestically developed technology and alloys.
* **Action Required:** Collaborate with BARC and NPCIL for manufacturing of SMR components and equipment.
* **Nuclear Power Corporation of India Limited (NPCIL)**
* **Impact:** NPCIL is jointly designing and developing the Bharat Small Modular Reactor (BSMR) with BARC.
* **Action Required:** Continue joint design and development efforts for BSMR.
* **Ministry of Environment, Forest and Climate Change (MoEF&CC)**
* **Impact:** The Ministry has provided the Terms of Reference (ToR) for obtaining environmental clearances for the High Temperature Gas Cooled Reactor (HTGCR).
* **Action Required:** Process environmental clearance applications as per the established ToR for the HTGCR project.
* **Cabinet Committee**
* **Impact:** The Cabinet Committee will review the administrative and financial sanction proposal for the BSMR-200 project.
* **Action Required:** Review and approve the administrative and financial sanction proposal for BSMR-200.
Key Entities Referenced
Nuclear Energy Mission: A program announced in the Union Budget, focusing on the research, design, development, and deployment of Small Modular Reactors (SMRs).
Bhabha Atomic Research Centre (BARC): A constituent unit of the Department of Atomic Energy (DAE) undertaking design and development works on SMRs.
Atomic Energy Commission (AEC): The body providing in-principle approval and clearing proposals for projects like BSMR-200.
Ministry of Environment, Forest and Climate Change (MoEF&CC): The ministry from which environmental clearances are being obtained for the HTGCR project.
Bharat Small Modular Reactor (BSMR): A type of Small Modular Reactor (SMR) jointly designed and developed by BARC and NPCIL.
Department of Atomic Energy
PARLIAMENT QUESTION: NUCLEAR ENERGY
MISSION
Posted On: 11 MAR 2026 4:54PM by PIB Delhi
Under the Nuclear Energy Mission announced in the Union Budget 2025–26, a total budgetary provision
of ₹20,000 crore has been made for the research, design, development, and deployment of Small Modular
Reactors (SMRs). Bhabha Atomic Research Centre (BARC), a constituent unit of Department of Atomic
Energy (DAE) has undertaken design and development works on SMRs namely,
i. 220 MWe Bharat Small Modular Reactor (BSMR-200),
ii. 55 MWe Small Modular Reactor (SMR-55), and
iii. Up to 5 MWth High temperature gas cooled reactor meant for hydrogen generation.
The lead units of these SMRs will be established at DAE sites for technology demonstration.
The estimated utilisation of the allocated funds by BARC toward setting up SMRs is mentioned below:
Reactor Cost Outlay (Rs Cr.)
Development and Construction of BSMR-200 5960
Development and Construction of SMR-55 (2 units) 7000
Design and construction of High Temperature Gas Cooled Reactor 320
(HTGCR)
Design, engineering & development works for new reactors 800
Civil and General Infrastructure Development for reactors complex 452
The progress of these SMRs is as follows;
i. BSMR-200: AEC in-principle approval has been received for the project. Proposal for
administrative & financial sanction is cleared by Atomic Energy Commission (AEC) for
submission of the proposal to the Cabinet Committee.
ii. SMR-55: In-principle approval has been received for the project.
iii. HTGCR: In-principle approval has been received for the project. Detailed Project Report
(DPR) has been prepared. Siting consent has been received and Terms of Reference (ToR) for
obtaining environmental clearances has been received from Ministry of Environment, Forest
and Climate Change (MoEF&CC).The special material called “Advanced Purified Reactor Vessel Alloy (ApuRVA) and technology for
forgings for reactor pressure vessels of BSMR-200 and SMR-55 has been developed indigenously in
collaboration with Indian Industries. The control rod drive mechanism has also been developed in-house.
Necessary technology for deployment of these reactors is available in the country. Majority of equipment
are within manufacturing capability of Indian Industries with technological handholding by BARC.
Therefore, Indian industries will be engaged in manufacturing of equipment.
Bharat Small Modular Reactor (BSMR) is being jointly designed and developed by BARC and Nuclear
Power Corporation of India Limited (NPCIL), a Govt. of India enterprise under DAE. Estimated time for
construction of BSMR is 60 to 72 months from receipt of administrative & financial approval.
This information was given by Union Minister of State (Independent Charge) for Science & Technology
and Earth Sciences, and Minister of State in the Prime Minister’s Office, Personnel, Public Grievances and
Pensions, Atomic Energy and Space, Dr. Jitendra Singh, in a written reply in the Lok Sabha on
Wednesday.
*****
NKR/AK