Executive Summary:
This document presents the Ministry of Railways' response to questions regarding railway accidents, safety measures, and infrastructure development, particularly in Kerala. It highlights a significant reduction in train accidents due to enhanced safety measures. The document also details ongoing projects in Kerala, including track doubling, level crossing elimination, and station redevelopment, while noting delays due to land acquisition and other factors.
Key Points / Main Content:
Railway Accident Statistics and Safety Measures:
* Consequential Train Accidents have decreased from 135 in 2014-15 to 31 in 2024-25 and further to 3 in 2025-26 (up to June 2025).
* Accidents Per Million Train Kilometer (APMTKM) improved by approximately 73%, decreasing from 0.11 in 2014-15 to 0.03 in 2024-25.
* The primary causes of accidents include track defects, loco/coach defects, equipment failures, and human errors.
* Total cost of damages to railway properties in consequential train accidents during the last five years has been about Rs 432.91 Cr.
Safety Enhancement Initiatives:
* Increased expenditure on safety-related activities, rising from Rs 39,463 Cr in 2013-14 to Rs 1,16,470 Cr in 2025-26 (Budget Estimate).
* Electrical/Electronic Interlocking Systems implemented at 6,635 stations up to 30.06.2025.
* Interlocking of Level Crossing (LC) Gates provided at 11,096 level crossings up to 30.06.2025.
* Complete Track Circuiting implemented at 6,640 stations up to 30.06.2025.
* Kavach, an Automatic Train Protection (ATP) system, adopted as a national standard in July 2020 and deployed on 1548 RKm.
* Other measures include equipping locomotives with Vigilance Control Devices (VCD), using modern track structures, and implementing Ultrasonic Flaw Detection (USFD) testing of rails.
Infrastructure Development in Kerala:
* As of 01.04.2025, 6 projects (2 New Lines and 4 Doubling) totaling 266 km, costing ₹9,415 crore, are sanctioned, with 26 km commissioned and ₹3,250 crore spent up to March 2025.
* Budget allocation for infrastructure projects and safety works in Kerala is ₹3,042 crore for 2025-26.
Project Delays and Challenges:
* Execution of projects is delayed due to land acquisition issues, with 403 Ha of land still to be acquired as of 01.04.2025.
* Other factors influencing project completion include forest clearance, shifting of utilities, statutory clearances, geological conditions, and law and order.
Station Redevelopment:
* 35 stations in Kerala identified for development under the Amrit Bharat Station Scheme.
* Phase I works completed at Chirayinkeezh and Vadakara stations.
* Fund allocation to Southern Railway for development and maintenance of stations is ₹1,122 crore in 2025-26 (Budget Estimate).
Level Crossings, ROBs, and RUBs:
* All Unmanned Level Crossings (UMLCs) on Broad Gauge (BG) routes have been eliminated by January 2019.
* As on 01.04.2025, 4,402 ROBs/RUBs are sanctioned at the cost of Rs. 1,00,860 Cr. on Indian Railways including 140 Nos. Road Over Bridges Road Under Bridges at the cost of Rs. 4,837 crore in the State of Kerala
Impact Analysis:
Government of Kerala:
* Impact: Success of railway projects in Kerala depends on the State Government's support, particularly in land acquisition.
* Action Required: Expedite land acquisition for ongoing railway projects and provide necessary support for infrastructure development.
Railway Passengers:
* Impact: Enhanced safety measures and infrastructure improvements aim to reduce accidents and improve travel experience.
* Action Required: Be aware of safety guidelines and cooperate with railway authorities during travel.
Railway Personnel:
* Impact: Implementation of new technologies and safety protocols requires training and adherence to updated procedures.
* Action Required: Undergo necessary training programs, particularly on Kavach technology, and implement safety protocols diligently.
Indian Railways:
* Impact: The need to continue investing in safety measures, infrastructure upgrades, and technological advancements to further reduce accidents and improve efficiency.
* Action Required: Continue to upgrade and modernize the signalling system.
Key Entities Referenced
Indian Railways: The primary railway operator in India, overseen by the Ministry of Railways. The document discusses safety measures, infrastructure projects, and modernization efforts undertaken by Indian Railways.
Kavach: An indigenously developed Automatic Train Protection (ATP) system designed to enhance railway safety by automatically applying brakes if the loco pilot fails to do so and helping trains run safely during inclement weather.
Kerala: A state in India where several railway infrastructure projects are underway, including track doubling, station redevelopment, and the implementation of safety technologies. The document highlights challenges related to land acquisition in Kerala.
Amrit Bharat Station Scheme: A scheme launched by the Ministry of Railways for the development and upgradation of railway stations across India. 35 stations in Kerala are identified for development under this scheme.
SHRI ASHWINI VAISHNAW: The Minister of Railways, Information Broadcasting and Electronics Information Technology, responsible for answering questions related to railway accidents and safety measures.
LHB design coaches: Modern railway coaches that are being used to replace conventional ICF design coaches to enhance safety in train operations.
South Central Railway: A zone of Indian Railways where Kavach has already been deployed on 1548 RKm.
Automatic Train Protection ATP system: Advance technology system Kavach as an Automatic Train Protection ATP system.
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 629
TO BE ANSWERED ON 23.07.2025
NUMBER OF MAJOR RAILWAY ACCIDENTS
629. SHRI K RADHAKRISHNAN:
Will the Minister of RAILWAYS be pleased to state:
(a) the number of major railway accidents reported across the country
during the last five years;
(b) the primary causes identified for these accidents;
(c) the total number of casualties and the estimated loss of properties in
each case;
(d) the amount sanctioned by the Government to the State of Kerala during
the last five years for infrastructure development projects;
(e) the detail of key projects undertaken in Kerala with the sanctioned
funds, including those related to track doubling, level crossing
elimination, overbridges, station redevelopment and implementation of
safety technologies like Kavach;
(f) the present status of each of these projects and their expected date of
completion;
(g) the measurable impact of these initiatives on improving railway safety
and reducing accidents in the country; and
(h) whether the Government has any further proposals under consideration
for enhancing railway safety in India, and if so, the details thereof?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (h): Safety is accorded the highest priority on Indian Railways. As a
consequence of various safety measures taken over the years, there hasbeen a steep decline in the number of accidents. Consequential Train
Accidents have reduced from 135 in 2014-15 to 31 in 2024-25 as shown in the
graph below. The causes of these accidents broadly include track defects,
loco/coach defects, equipment failures, human errors etc.
It may be noted that the Consequential Train Accidents during the
period 2004-14 was 1711 (average 171 per annum), which has declined to 31
in 2024-25 and further to 3 in 2025-26 (upto June, 2025).
Another important index showing improved safety in train operations is
Accidents Per Million Train Kilometer (APMTKM) which has reduced from
0.11 in 2014-15 to 0.03 in 2024-25, indicating an improvement of approx. 73%
during the said period.
The number of consequential train accidents during the last five years
are depicted in the Graph below.
234
s
t
n
e
d
ic
c
A 165
n
ia
r T 135
la
it
n
e
u
q
e
s
n
o
C
f o
55
48
.o
N 35
40
31
22
3
2005- 2009- 2014- 2019- 2020- 2021- 2022- 2023- 2024- 2025-26
06 10 15 20 21 22 23 24 25 (up to
Covid year Covid year Jun'25)Consequential Train Accidents on Indian Railways and casualties
(including railway passengers and railway personnel) therein are as follows:-
Period No. of Consequential No. of Deaths No. of Injuries
Train Accidents
2004-05 to 2013-14 1,711 904 3,155
2014-15 to 2023-24 678 748 2,087
Total cost of damages to railway properties in consequential train
accidents during the last five years has been about Rs 432.91 Cr.
The various safety measures taken to enhance safety in train
operations are as under:-
1. On Indian Railways, the expenditure on Safety related activities has
increased over the years as under:-
Expenditure on Safety related activities (Rs. in Cr.)
2013-14 2022-23 2023-24 RE 2024-25 BE 2025-26
(Act.) (Act.) (Act.)
Maintenance of 9,172 18,115 20,322 21,800 23,316
Permanent Way &
Works
Maintenance of 14,796 27,086 30,864 31,540 30,666
Motive Power and
Rolling Stock
Maintenance of 5,406 9,828 10,772 12,112 12,880
Machines
Road Safety LCs 1,986 5,347 6,662 8,184 7,706
and ROBs/ RUBs
Track Renewals 4,985 16,326 17,850 22,669 22,800
Bridge Works 390 1,050 1,907 2,130 2,169
Signal & Telecom 905 2,456 3,751 6,006 6,800
Works
Workshops Incl. 1,823 7,119 9,523 9,581 10,134
PUs and Misc.
expenditure on
Safety
Total 39,463 87,327 1,01,651 1,14,022 1,16,4702. Electrical/Electronic Interlocking Systems with centralized operation of
points and signals have been provided at 6,635 stations up to
30.06.2025 to reduce accident due to human failure.
3. Interlocking of Level Crossing (LC) Gates has been provided at 11,096
level Crossing Gates up to 30.06.2025 for enhancing safety at LC gates.
4. Complete Track Circuiting of stations to enhance safety by verification
of track occupancy by electrical means has been provided at 6,640
stations up to 30.06.2025.
5. Kavach is a highly technology intensive system, which requires safety
certification of highest order. Kavach was adopted as a National ATP
system in July 2020. Kavach is provided progressively in phased
manner. Kavach has already been deployed on 1548 RKm on South
Central Railway and North Central Railway. Presently, the work is in
progress on Delhi-Mumbai and Delhi-Howrah corridors (approximately
3000 RKm). Track side works on these routes have been completed on
about 2200 RKm as on 30.06.2025. Regular trials are being done on
these sections.
6. Detailed instructions on issues related with safety of Signalling, e.g.
mandatory correspondence check, alteration work protocol,
preparation of completion drawing, etc. have been issued.
7. System of disconnection and reconnection for S&T equipment as per
protocol has been re-emphasized.
8. All locomotives are equipped with Vigilance Control Devices (VCD) to
improve alertness of Loco Pilots.
9. Retro-reflective sigma boards are provided on the mast which is
located two OHE masts prior to the signals in electrified territories to
alert the crew about the signal ahead when visibility is low due to
foggy weather.10. A GPS based Fog Safety Device (FSD) is provided to loco pilots in fog
affected areas which enables loco pilots to know the distance of the
approaching landmarks like signals, level crossing gates, etc.
11. Modern track structure consisting of 60kg, 90 Ultimate Tensile
Strength (UTS) rails, Prestressed Concrete Sleeper (PSC) Normal/Wide
base sleepers with elastic fastening, fan shaped layout turnout on PSC
sleepers, Steel Channel/H-beam Sleepers on girder bridges is used
while carrying out primary track renewals.
12. Mechanisation of track laying activity through use of track machines
like PQRS, TRT, T-28 etc. to reduce human errors.
13. Maximizing supply of 130m/260m long rail panels for increasing
progress of rail renewal and avoiding welding of joints, thereby
improving safety.
14. Ultrasonic Flaw Detection (USFD) testing of rails to detect flaws and
timely removal of defective rails.
15. Laying of longer rails, minimizing the use of Alumino Thermic Welding
and adoption of better welding technology for rails i.e., Flash Butt
Welding.
16. Monitoring of track geometry by OMS (Oscillation Monitoring System)
and TRC (Track Recording Cars).
17. Patrolling of railway tracks to look out for weld/rail fractures.
18. The use of Thick Web Switches and Weldable CMS Crossing in turnout
renewal works.
19. Inspections at regular intervals are carried out to monitor and educate
staff for observance of safe practices.
20. Web based online monitoring system of track assets viz. Track
database and decision support system has been adopted to decide
rationalized maintenance requirement and optimize inputs.21. Detailed instructions on issues related with safety of Track, e.g.
integrated block, corridor block, worksite safety, monsoon precautions,
etc. have been issued.
22. Preventive maintenance of railway assets (Coaches & Wagons) is
undertaken to ensure safe train operations.
23. Replacement of conventional ICF design coaches with LHB design
coaches is being done.
24. All unmanned level crossings (UMLCs) on Broad Gauge (BG) route have
been eliminated by January 2019.
25. Safety of Railway Bridges is ensured through regular inspection of
Bridges. The requirement of repair/rehabilitation of Bridges is taken up
based upon the conditions assessed during these inspections.
26. Indian Railways has displayed Statutory “Fire Notices” for widespread
passenger information in all coaches. Fire posters are provided in every
coach so as to educate and alert passengers regarding various Do‟s
and Don‟ts to prevent fire. These include messages regarding not
carrying any inflammable material, explosives, prohibition of smoking
inside the coaches, penalties etc.
27. Production Units are providing Fire detection and suppression system
in newly manufactured Power Cars and Pantry Cars, Fire and Smoke
detection system in newly manufactured coaches. Progressive fitment
of the same in existing coaches is also underway by Zonal Railways in
a phased manner.
28. Regular counselling and training of staff is undertaken.
29. Concept of Rolling Block introduced in Indian Railways (Open Lines)
General Rules vide Gazette notification dated 30.11.2023, wherein
work of integrated maintenance/ repair/replacement of assets is
planned up to 52 weeks in advance on rolling basis and executed as
per plan.The details of the Safety related works related to better maintenance
practices, technological improvements, better infrastructure and rolling
stock etc. undertaken by Railways are tabulated below:-
2014-15 to
2004-05 to 2014-25 Vs.
S.N. Item 2024-25
2013-14 2004-14
(till March 25)
Technological improvements
1. Use of high-quality rails (60 57,450 Km 1.43 Lakh Km More than 2
Kg) (Km) times
2. Longer Rail Panels (260m) 9,917 Km 77,522 Km Nearly 8
(Km) times
3. Electronic Interlocking 837 3,691 Stations More than 4
(Stations) Stations times
4. Fog Pass Safety Devices As on As on 31.03.25: 288 times
(Nos.) 31.03.14: 25,939
90 Nos.
5. Thick Web Switches (Nos.) Nil 28,301 Nos.
Better maintenance practices
1. Primary Rail Renewal 32,260 Km 49,941 Km 1.5 times
(Track Km)
2. USFD (Ultra Sonic Flaw 79.43 Lakh 2 Crore More than 2
detection) Testing of Welds times
(Nos.)
3. Weld failures (Nos.) In 2013-14: In 2024-25: 90 %
3699 Nos. 370 Nos. reduction
4. Rail fractures (Nos.) In 2013-14: In 2024-25: More than
2548 Nos. 289 Nos. 88%
reduction
Better infrastructure and Rolling stock
1. New Track KM added 14,985 Nos. 34,428 Km More than 2
(Track km) times
2. Flyovers (RoBs)/ 4,148 Nos. 13,808 Nos. More than 3
times
Underpasses (RUBs) (Nos.)
3. Unmanned Level crossings As on As on 31.03.24: Removed
(nos.) on BG 31.03.14: Nil
8948 (All eliminated
by 31.01.19)
4. Manufacture of LHB 2,337 Nos. 42,677 More than 18
Coaches (Nos.) timesIndian Railways continuously upgrades and modernises its signalling
system to enhance safety. In this regards some of the steps taken are as
follows:-
1. Electrical/Electronic Interlocking Systems with centralized operation of
points and signals in place of old mechanical signalling have been
provided at 6635 stations as on 30.06.2025.
2. Complete Track Circuiting of stations to enhance safety for verification of
track occupancy by electrical means has been provided at 6640 stations
upto 30.06.2025.
3. Interlocking of Level Crossing Gates (LC) has been provided at 11096
Level Crossing Gates upto 30.06.2025 for enhancing safety at LC Gate.
4. Axle counters for automatic clearance of Block Section, BPAC (Block
Proving Axle Counter) are provided to ensure complete arrival of train
without manual intervention before granting line clear to receive next
train and to reduce human element. These systems have been provided on
6147 Block Sections up to 30.06.2025.
5. Indian Railways has also gone for implementation of advance technology
system “Kavach” as an Automatic Train Protection (ATP) system.
i. Kavach is an indigenously developed Automatic Train Protection (ATP)
system. Kavach is a highly technology intensive system, which requires
safety certification of highest order (SIL-4).
ii. Kavach aids the Loco Pilot in running of trains within specified speed
limits by automatic application of brakes in case Loco Pilot fails to do so
and also helps the trains to run safely during inclement weather.
iii. The first field trials on the passenger trains were started in February
2016. Based on the experience gained and Independent Safety
Assessment of the system by Independent Safety Assessor (ISA), three
firms were approved in 2018-19, for supply of Kavach Ver 3.2.iv. Kavach was adopted as National ATP system in July 2020.
v. Implementation of Kavach System involves following Key Activities:
a. Installation of Station Kavach at each and every station, block section.
b. Installation of RFID Tags throughout the track length.
c. Installation of telecom Towers throughout the section.
d. Laying of Optical Fibre Cable along the track.
e. Provision of Loco Kavach on each and every Locomotive running on
Indian Railways.
vi. Based on deployment of Kavach version 3.2 on1465 RKm on south central
Railway, a lot of experience was gained. Using that further improvements
were made. Finally, Kavach specification version 4.0 was approved by
RDSO on 16.07.2024.
vii. Kavach version 4.0 covers all the major features required for the diverse
railway network. This is a significant milestone in safety for Indian
Railways. Within a short period, IR has developed, tested and started
deploying Automatic Train Protection System.
viii. Major improvement in Version 4.0 includes increased Location Accuracy,
Improved Information of Signal Aspects in bigger yards, Station to Station
Kavach interface on OFC and Direct Interface to existing Electronic
Interlocking System. With these improvements, Kavach Ver.4.0. is
planned for large scale deployment over Indian Railways.
ix. Progress of Key items comprising Kavach system on Indian Railways upto
14.07.25 is as under:-
S. No. Items Progress
i. Laying of Optical Fibre Cable 5856 Km
ii. Installation of Telecom Towers 619 Nos.
iii. Provision of Kavach at Stations 708 Nos.iv. Provision of Kavach in Loco 1107 Locos
v. Installation of Track side equipment 4001 Rkm
x. Next phase of Kavach implementation is planned as under:-
a. Project for equipping 10,000 Locomotives has been finalized. 69
number of loco sheds have been prepared for equipping with
Kavach.
xi. Bids for track side Works of Kavach for approximately 15,000 RKm have
been invited covering all GQ, GD, HDN and identified sections of Indian
Railways, out of which works of 14847 RKm have been awarded.
xii. The sections mentioned above also pass through the railway routes in
state of Kerala.
xiii. Specialized training programmes on Kavach are being conducted at
centralized training institutes of Indian Railways to impart training to all
concerned officials. By now more than 30,000 technicians, operators and
engineers have been trained on Kavach technology. Courses have been
designed in collaboration with IRISET.
Infrastructure Projects:-
Railway projects are surveyed/ sanctioned/executed Zonal Railway
wise. Zonal Railway wise details of Railway projects are made available in
public domain on Indian Railway‟s website.
As on 01.04.2025, 06 projects (02 New Lines and 04 Doubling), of a
total length of 266 km, costing 9,415 crore, falling fully/partly in Kerala, are
sanctioned, out of which 26 km length has been commissioned and an
expenditure of `3,250 crore has been incurred upto March‟ 2025. The
summary is as under:-Length
No of Total Length Total Exp
Commissioned
Category sanctioned NL/DL upto Mar'25
till Mar'25
Projects (in Km) (` in Cr)
(in Km)
New Lines 2 146 0 3,864
Doubling /
4 120 26 5,551
Multitracking
Total 6 266 26 9,415
Budget allocation for infrastructure projects and safety works, falling
fully/partly in the State of Kerala is as under:-
Period Outlay
2009-14 ₹372 crore/year
2025-26 ₹3,042 crore (more than 8 times)
Execution of important infrastructure projects falling fully/partly in the
State of Kerala are held up due to delay in land acquisition. Status of land
acquisition in the State of Kerala is as under:-
Total Land required for Projects in Kerala 476 Ha
Land Acquired 73 Ha (15%)
Balance Land to be acquired 403 Ha (85%)
Government of India is geared up to execute projects, however
success depends upon the support of Government of Kerala. Railway had
deposited ₹2,111.83 crore for land acquisition to Government of Kerala.
Support of the Government of Kerala is needed to expedite the land
acquisition. For instance, details of some major projects which are delayed
due to land acquisition are as under:-
S. Name of the project Total land Land Balance Land to
No. required acquired be acquired
(in Ha) (in Ha) (in Ha)
1. Angamali - Sabarimala new line 416 24.4 391.6
(111 Km)
2. Ernakulam – Kumbalam Patch 4.2 3.55 0.65
Doubling (8 Km)3. Kumbalam - Turavur Patch 10.3 9.63 0.67
Doubling (16 Km)
4. Trivandrum – Kanyakumari 41 35.67 5.33
Doubling (87 Km)
5. Shoranur – Vallathol Doubling 4.77 0 4.77
(10 Km)
Other factors influencing the completion of the projects include forest
clearance, shifting of infringing utilities, statutory clearances from various
authorities, geological and topographical conditions of area, law and order
situation in the area of project/s site, number of working months in a year for
particular project site etc. All these factors affect the completion time and
cost of the project/s.
Station Redevelopment:-
Ministry of Railways has launched Amrit Bharat Station Scheme for
development/upgradation of stations over Indian Railways. So far, 1337
stations have been identified for development under Amrit Bharat Station
Scheme, out of which 35 stations are located in the state of Kerala. The
names of stations identified for development under Amrit Bharat Station
Scheme in the state of Kerala are as following:-
No. of Amrit
State Names of Amrit Stations
Stations
Alappuzha, Angadippuram, Angamali For Kaladi,
Chalakudi, Changanassery, Chengannur, Chirayinikil,
Ernakulam, Ernakulam Town, Ettumanur, Ferok,
Guruvayur, Kannur, Kasargod, Kayankulam Jn, Kollam
Kerala 35
Jn (Quilon), Kozhikode Main (Calicut), Kuttippuram,
Mavelikara, Neyyattinkara, Nilambur Road,
Ottappalam, Parappanangadi, Payyanur, Punalur,
Shoranur Jn., Thalassery, Thiruvananthapuram
Central, Thrisur, Tirur, Tiruvalla, Tripunithura,Vadakara, Varkala Shivagiri, Wadakancheri
Development works at railway stations under Amrit Bharat Station
Scheme in the state of Kerala have been taken up at a good pace. Till now
Phase – I works of Chirayinkeezh and Vadakara stations in the state of
Kerala have been completed under this scheme.
Amrit Bharat Station Scheme envisages improving amenities at the
stations like improvement of station access, circulating areas, waiting halls,
toilets, lift/escalators as necessary, platform surfacing and cover over
platform, cleanliness, free Wi-Fi, kiosks for local products through schemes
like „One Station One Product‟, better passenger information systems,
executive lounges, nominated spaces for business meetings, landscaping,
etc. keeping in view the necessity at each station.
The scheme also envisages improvement of building, integrating the
station with both sides of the city, multimodal integration, amenities for
Divyangjans, sustainable and environment friendly solutions, provision of
ballastless tracks, etc. as per necessity, phasing and feasibility and creation
of city centre at the station in the long term.
Development / Redevelopment / Upgradation / Modernisation of stations
on Indian Railways is a continuous and ongoing process and works in this
regard are undertaken as per requirement, subject to inter-se priority of the
statons and availability of funds.
Kerala is covered under Southern Railway. The fund allocation to
Southern Railway for development and maintenance of stations under Plan
Head-53 „Customer Amenities‟, for the last 5 years including the current year
is as follows:-(fig. in Cr. of Rupees)
2021-22 2022-23 2023-24 2024-25
Year 2025-26 (BE)
(RE) (RE) (RE) (RE)
Allocation 218 431 563 1,098 1,122
Development / Redevelopment / Upgradation / Modernisation of railway
stations is complex in nature involving safety of passengers & trains and
requires various statutory clearances such as fire clearance, heritage, tree
cutting, air-port clearance etc. The progress also gets affected due to
brownfield related challenges such as shifting of utilities (involving
water/sewage lines, optical fibre cables, gas pipe lines, power/signal cables,
etc.), infringements, operation of trains without hindering passenger
movement, speed restrictions due to works carried out in close proximity of
tracks and high voltage power lines, etc. and these factors affect the
completion time. Therefore, no time frame can be indicated at this stage.
Level Crossings/Road Over Bridges (ROB) and Road Under Bridges (RUB):-
All Unmanned level crossings (UMLCs) on running lines of Broad Gauge
(BG) network of Indian Railway including in Kerala have been eliminated by
31.01.2019. As on 01.04.2024, there are total 378 Nos. Manned Level
Crossings (MLCs) in the State of Kerala.
Sanctioning and execution of works of Road Over Bridges/ Road Under
Bridges (ROBs/RUBs) in lieu of LCs is a continuous and ongoing process on
Indian Railways. Such works are prioritized and taken up on the basis of its
impact on safety and mobility in train operations and impact on road users.
No. of ROBs/RUBs constructed on Indian Railways during the period
2004-14 vis-a-vis 2014-25 is as under:-Period ROBs/RUBs constructed
2004-14 4,148
2014-26 (upto June‟25) 13,426 (including 118 Nos. in the state of
Kerala)
As on 01.04.2025, 4,402 Nos. ROBs/ RUBs are sanctioned at the cost
of Rs. 1,00,860 Cr. on Indian Railways including 140 Nos. Road Over Bridges /
Road Under Bridges at the cost of Rs. 4,837 crore in the State of Kerala,
which are at various stages of planning and execution. Out of 140 Nos.
ROBs/RUBs in the state of Kerala, 132 Nos. ROBs/RUBs are sanctioned in lieu
of LCs.
Completion and commissioning of ROB/RUB works depend on various
factors like cooperation of State Governments in giving consent for closure
of LCs, fixing of approach alignment, approval of General Arrangement
Drawing (GAD), land acquisition, removal of encroachments, shifting of
infringing utilities, statutory clearances from various authorities, law and
order situation in the area of project/work sites, duration of working season
in a year for the particular project/area due to climatic conditions etc. All
these factors determine the completion time of the projects / works.
*****