**Executive Summary**
This document is an answer given by the Minister of Railways, Information & Broadcasting and Electronics & Information Technology to the Lok Sabha Unstarred Question No. 1737 on 10.12.2025 regarding the number of railway zones in Karnataka. It provides the number of operational railway zones in the country, the status of railway projects, and details of railway development in Karnataka.
**Key Points / Main Content**
* **Railway Zones in India:**
* There are 17 operational railway zones in the country, including Metro Railway, Kolkata.
* The foundation stone for the new South Coast Railway (SCoR) zone has been laid recently. The SCoR zone is in the process of being set up.
* Details of zonal railway route kilometers as of March 31, 2025 are provided.
* **Railway Infrastructure:**
* Railway network depends on population density, terrain, and geographical features, varying from region to region.
* Rail infrastructure augmentation focuses on network capacity enhancement, bottleneck removal, increased freight train speeds, and reduced cargo transit time and cost.
* **Railway Projects:**
* 431 Railway infrastructure projects (154 New Line, 33 Gauge Conversion and 244 Doubling) of total length 35,966 Km, costing approx. ₹6.75 lakh crore are sanctioned across Indian Railways as on 01.04.2025.
* Railway projects are surveyed/sanctioned/executed Zonal Railway wise and not State-wise/District wise.
* Zone-wise/year-wise details of all Railway projects are made available in public domain on Indian Railway's website.
* Average commissioning of new tracks increased from 4.2 Km/day (2009-14) to 8.57 Km/day (2014-25).
* **Karnataka Railway Development:**
* Budget allocation for infrastructure projects and safety works in Karnataka has increased significantly.
* 25 projects (15 new lines, 10 doubling) of 3,264 km length, costing ₹42,517 crore falling fully/partly in Karnataka are sanctioned as on 01.04.2025.
* Details of recently completed and ongoing railway projects in Karnataka are listed, including project costs.
* 65 surveys (25 new line and 40 doubling) covering a total length of 7,239 km have been sanctioned falling fully/partly in the State of Karnataka in the last three years.
* Details of major projects delayed due to land acquisition in Karnataka are provided, including land required, acquired, and balance to be acquired.
* Completion of projects is affected by factors like land acquisition, forest clearance, statutory clearances, geological conditions, and law & order.
* Railway project depends upon anticipated traffic projections, first and last mile connectivity, connection of missing links, augmentation of congested/saturated lines and demands raised by State Governments/Central Ministries/Public representatives.
**Impact Analysis**
**Stakeholder:** The Minister of Railways, Information & Broadcasting and Electronics & Information Technology
* **Impact:** Required to provide information on railway zones and development activities.
* **Action Required:** To note the railway zones across the country.
**Stakeholder:** Shri G Kumar Naik
* **Impact:** Received information on railway zones in the country and the railway density in each zone, State/UT-wise and, in particular, Karnataka.
* **Action Required:** None explicitly stated.
**Stakeholder:** Government of India
* **Impact:** Responsible for the execution of railway projects.
* **Action Required:** Need to expedite project completion and address land acquisition issues with support from the Government of Karnataka.
**Stakeholder:** Government of Karnataka
* **Impact:** Railway development within the state.
* **Action Required:** Provide support in land acquisition for timely project completion.
**Stakeholder:** Indian Railways
* **Impact:** Tasked with implementing railway infrastructure projects.
* **Action Required:** Continue focusing on network capacity enhancement, bottleneck removal, and improving freight train speeds.
Key Entities Referenced
Ministry of Railways: The central ministry responsible for the railway sector in India.
Railway Zones: Divisions of the Indian Railways that manage railway operations in specific geographical areas. The document discusses the number and density of these zones.
Karnataka: A state in India that is the primary location of focus in the unstarred question regarding railway density and infrastructure projects.
South Coast Railway (SCoR): A new railway zone that is in the process of being set up.
Indian Railways: The national railway system of India, encompassing all railway zones and infrastructure projects.
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 1737
TO BE ANSWERED ON 10.12.2025
NUMBER OF RAILWAY ZONES IN KARNATAKA
1737. SHRI G KUMAR NAIK:
Will the Minister of RAILWAYS be pleased to state:
(a) the total number of railway zones in the country and the
railway density in each zone, State/UT-wise;
(b) the railway density in Karnataka, district-wise;
(c) whether the Government has a policy that defines the
minimum railway density required to adequately meet
public transportation needs and support economic growth
and if so, the details thereof;
(d) whether the existing railway density is sufficient to meet
the needs of the people and if so, the details thereof; and
(e) the details of any schemes/initiatives proposed by the
Government to enhance railway density in Karnataka?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (e) : There are 17 Railway Zones operational (including Metro
Railway, Kolkata) in the country. Further, foundation stone of new
South Coast Railway (SCoR) zone has been laid recently.
Page 1 of 7The details of Zonal Railway wise route km is given below: -
Route Km.
S.No. Railway
(as on 31.03.2025)
1 Central 4353
2 Eastern 2855
3 East Central 4400
4 East Coast 3162
5 Northern 7477
6 North Central 3518
7 North Eastern 3494
8 Northeast Frontier 4412
9 North Western 5613
10 Southern 5104
11 South Central 6637
12 South Eastern 2749
13 South East Central 2448
14 South Western 3711
15 Western 6284
16 West Central 3177
17 Metro, Kolkata 45
Total 69,439
The new SCoR zone is in the process of setting up.
Railway network in any area depends upon the population density of
that area, terrain, geographical features, etc. Therefore, Railway
density varies from region to region.
The rail infrastructure augmentation plan inter-alia focuses on the
network capacity enhancement, removal of bottlenecks, increasing
average speed of freight trains, reduction in cargo transit time and
cost. Further, to improve capacity of existing network, several
capacity enhancement/augmentation survey/works have been
sanctioned by railways. These works include multi tracking, rail
flyovers, by pass lines, yard remodelling works etc.
Page 2 of 7Railway projects are surveyed/sanctioned/executed Zonal Railway
wise and not State-wise/District wise as the Railway projects may
span across State boundaries. Railway projects are sanctioned on
the basis of remunerativeness, traffic projections, last mile
connectivity, missing links and alternate routes, augmentation of
congested/saturated lines, demands raised by State Governments,
Central Ministries, Members of Parliament, other public
representatives, Railway’s own operational requirement, socio-
economic considerations etc. depending upon throw forward of
ongoing projects and overall availability of funds.
As on 01.04.2025, across Indian Railways, 431 Railway
infrastructure projects (154 New Line, 33 Gauge Conversion and 244
Doubling) of total length 35,966 Km, costing approx. ₹6.75 lakh
crore are sanctioned. The summary is as under: -
Total Length
Total Exp
No of Length Commissioned upto
Category
Projects NL/GC/DL till Mar'25 Mar'25
(km) (km) (₹ in Cr)
New Lines 154 16,142 3,036 1,45,318
Gauge
33 4,180 2,997 22,753
Conversion
Doubling /
244 15,644 6,736 1,22,858
Multitracking
Total 431 35,966 12,769 2,90,929
Zone-wise/year-wise details of all Railway projects are made
available in public domain on Indian Railway’s website.
The details of commissioning / laying of new track across Indian
Railways is given below: -
New track
Period Average commissioning of new tracks
Commissioned
2009-14 7,599 Km 4.2 Km/day
2014-25 34,428 Km 8.57 Km/day (more than 2 times)
Page 3 of 7Karnataka: -
Budget allocation in the recent years has increased significantly.
Budget allocation for infrastructure projects and safety works,
falling fully/partly in the State of Karnataka is as under:
Period Outlay
2009-14 ₹835 crore/year
2025-26 ₹7,564 crore (more than 9 times)
As on 01.04.2025, 25 projects (15 new lines, 10 doubling) of 3,264
km length, costing ₹42,517 crore falling fully/partly in Karnataka are
sanctioned. The summary is as under: -
Length
No of Total Exp upto
Commissioned
Category sanctioned Length Mar'25
Upto Mar'25
Projects (in km) (₹ in cr.)
(km)
New Line 15 2,034 421 8,794
Doubling/
10 1,230 973 12,516
Multitracking
Total 25 3,264 1,394 21,310
Details of some of the recently completed projects falling fully/partly
in Karnataka are as under: -
Cost
S.No Project
(₹in Crores)
1 Kottur-Harihar new line (65 km) 468
2 Hassan-Bangalore new line (167 km) 1,290
3 Bidar-Gulbarga new line (110 km) 1,543
4 Shivani-Hosadurga Road doubling (10 km) 50
5 Shivani-Birur doubling (29 km) 143
6 Hosadurga-Chikjajur doubling (29 km) 260
7 Ramanagram-Mysore patch doubling (94 km) 998
8 Yelahanka – Chennasadra doubling (13 km) 108
9 Yeshwantpur-Yelahanka doubling (12 km) 95
10 Netrawati-Mangalore Central doubling (2 km) 28
Page 4 of 711 Kankanadi-Panambur doubling (19 km) 350
12 Arsikere-Tumkur doubling (96 km) 758
13 Yelahanka-Penukonda doubling (123 km) 1,104
14 Daund-Gulbarga doubling (225 km) 3,182
15 Hubli-Chikjajur doubling (190 km) 1,850
Some of the projects falling fully/partly in Karnataka which have
been taken up are as under: -
Cost
S No. Project (₹in
Crores)
Hospet-Hubli-Londa-Vasco-de-Gama doubling
1 4,153
(312 km)
2 Hotgi-Gadag doubling (284 km) 2,459
3 Ginigera - Raichur new line (165 km) 3,401
4 Gadag - Wadi new line (257 km) 2,842
5 Bagalkot – Kudachi new line (142 km) 1,649
6 Tumkur – Rayadurga new line (207 km) 2,496
7 Tumkur – Davangere new line (182 km) 2,142
8 Kadur – Chikmagalur – Belur new line (68 km) 825
9 Baiyyapanahalli – Hosur doubling (48 km) 336
10 Yeshwanthpur – Channasandra doubling (22 km) 314
In last three years i.e. 2022-23, 2023-24, 2024-25 and current
financial year 2025-26, 65 surveys (25 new line and 40 doubling)
covering a total length of 7,239 km has been sanctioned falling
fully/partly in the State of Karnataka.
Page 5 of 7Details of some major projects which are delayed due to land
acquisition are as under: -
Balance
Total
Land Land
Land
S No. Project acquired to be
required
(in Ha) acquired
(in Ha)
(in Ha)
Shimoga –Rannebennur
1 559 226 333
new line (96 km)
Belgaum – Dharwad new
2 581 0 581
line (73 km)
Shimoga – Harihar new
3 488 0 488
line (79 km)
Whitefield-Kolar new line
4 337 0 337
(53 km)
Hassan-Belur new line
5 206 0 206
(32 km)
Summary of the status of land acquisition in Karnataka is as under:-
Total Land required for Projects in 9,020 Ha
Karnataka
Land Acquired 5,679 Ha (63%)
Balance Land to be acquired 3,341 Ha (37%)
Government of India is geared up to execute projects, however
success depends upon the support of Government of Karnataka.
Sanction of any railway project depend upon many
parameters/factors which include the following:
Anticipated traffic projections and remunerativeness of the
proposed route
First and last mile connectivity provided by the project
Connection of missing links and providing additional route
Augmentation of congested/saturated lines
Demands raised by State Governments/Central
Ministries/Public representatives,
Page 6 of 7 Railway’s own operational requirements
Socio-economic considerations
Overall availability of funds
Completion of Railway project/s depends on various factors which
include the following:
Land acquisition by State Government
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site
etc.
All these factors affect the completion time and cost of the
project/s.
*****