Parliament Question: Obstacles in the Implementation of Bharatmala Pariyojana

Issued by Ministry of Road Transport and Highways · Not Applicable

Research with AI Agent Chat with Document Generate Summary Translate Helpful Share Add to Project Create Task

Executive Summary & Key Takeaways

**Executive Summary:** This document is the response of the Minister of Road Transport and Highways to questions raised in Lok Sabha regarding obstacles in the implementation of the Bharatmala Pariyojana. It outlines steps taken to address these obstacles, the initiative's promotion of indigenous manufacturing and infrastructure development, and the details of approved, awarded, and completed projects under the program until June 2025. The Bharatmala Pariyojana Phase-I was approved in 2017. **Key Points / Main Content:** * **Addressing Implementation Obstacles:** * Identified obstacles include land acquisition, pre-construction delays, contractor financial difficulties, force majeure events, and material scarcity. * Solutions involve streamlining land acquisition via the Bhoomi Rashi portal and faster clearances using the revamped Parivesh Portal. * Online approval of General Arrangement Drawings (GAD) for Road over Bridges (ROB) and Road under Bridges (RUB) from the Railways is enabled. * Review meetings are conducted with stakeholders, including State Governments. * **Promoting Indigenous Manufacturing and Infrastructure Development:** * Initiatives support local construction materials, new technologies research, and local manufacturing of machinery/equipment. * This reinforces "Make in India" and "Atmanirbhar Bharat" concepts. * Connectivity to industrial corridors and ports is improved, aligning with PM GatiShakti principles. * Logistics costs are reduced, and freight efficiency is improved. * **Project Status (as of June 2025):** * Bharatmala Pariyojana Phase-I, approved in 2017, covers 34,800 km. * Projects awarded cover 26,425 km, with 20,770 km already constructed. * State-wise details of awarded and constructed lengths are provided in the annexure. **Impact Analysis** **Central Government (Ministry of Road Transport and Highways):** * *Impact:* Accountable for overseeing and expediting the Bharatmala Pariyojana. * *Action Required:* Continue implementing initiatives to address obstacles, promote indigenous manufacturing, and monitor project progress. **State Governments:** * *Impact:* Responsible for facilitating land acquisition and coordinating with central authorities. * *Action Required:* Collaborate with the Ministry of Road Transport and Highways to resolve bottlenecks and ensure timely project completion within their respective states. **Contractors:** * *Impact:* Affected by financial difficulties and material scarcity. * *Action Required:* Adhere to project timelines and quality standards, and seek support from the government to address financial and resource-related challenges. **Construction Material Suppliers:** * *Impact:* Benefit from initiatives promoting the use of local construction materials. * *Action Required:* Ensure the availability of quality materials and comply with government regulations and standards. **Transportation and Logistics Sector:** * *Impact:* Benefits from improved connectivity, reduced logistics costs, and enhanced freight efficiency. * *Action Required:* Adapt to the improved infrastructure and leverage the opportunities for growth and efficiency gains. **General Public:** * *Impact:* Benefits from improved road infrastructure, reduced travel time, and better connectivity. * *Action Required:* Utilize the improved infrastructure responsibly and adhere to traffic regulations.

Key Entities Referenced

Bharatmala Pariyojana: A centrally-sponsored and funded road and highways project in India. Ministry of Road Transport and Highways: The Indian government ministry responsible for the development and maintenance of the national highways network. Nitin Jairam Gadkari: The Minister of Road Transport and Highways. Bhoomi Rashi portal: A portal used for streamlining and expediting the land acquisition process for highway projects. Parivesh Portal: A portal used to facilitate faster forest and environmental clearances. PM GatiShakti: A national master plan for multimodal connectivity, aiming to reduce logistics costs and improve infrastructure. Andhra Pradesh: A state in India where road construction is taking place under the Bharatmala Pariyojana. Make in India: An initiative to encourage local manufacturing and production within India.
Official Source Record View Original Source →
See Full Document Text
GOVERNMENT OF INDIA MINISTRY OF ROAD TRANSPORT AND HIGHWAYS LOK SABHA UNSTARRED QUESTION NO. 3124 ANSWERED ON 7TH AUGUST, 2025 OBSTACLES IN THE IMPLEMENTATION OF BHARATMALA PARIYOJANA 3124. SHRI JASHUBHAI BHILUBHAI RATHVA: SHRI ANANTA NAYAK: SHRI RAHUL SINGH LODHI: SMT. BIJULI KALITA MEDHI: SHRI ANURAG SINGH THAKUR: Will the Minister of ROAD TRANSPORT AND HIGHWAYS सड़क परिवहन औि िाजमार्ग मंत्री be pleased to state: (a) whether any steps have been taken to address the major obstacles hindering the implementation of the Bharatmala Pariyojana and if so, the details thereof; (b) whether the said initiative promotes indigenous manufacturing and infrastructure development and support self-reliant transportation and logistics sector and if so, the details thereof; and (c) the details of the total projects approved, awarded, completed and roads constructed therein (in kilometers) till June 2025, State and year-wise? ANSWER THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS (SHRI NITIN JAIRAM GADKARI) (a) Project implementation of National Highways often faces several challenges that affect the timely completion of projects, such as bottlenecks relating to land acquisition, delays in pre-construction activities, financial difficulties faced by contractors, force majeure events, and scarcity of construction materials etc.To overcome these challenges and expedite project execution, various initiatives have been undertaken. These include streamlining and expediting the land acquisition process through Bhoomi Rashi portal, revamping the Parivesh Portal to facilitate faster forest and environmental clearances, enabling online approval of General Arrangement Drawings (GAD) for Road over Bridges (ROB) and Road under Bridges (RUB) from the Railways, and conducting review meetings at various levels with all stakeholders, including State Governments. The Government is taking all necessary steps for timely completion of these projects. (b) Various initiatives have been undertaken to facilitate use of local construction materials, research on new construction technologies and local manufacturing of construction machinery & equipment, thereby strengthening the local manufacturing system, reinforcing the idea of Make in India and Atmanirbhar Bharat. It improves connectivity to industrial corridors and ports in line with PM GatiShakti principles leading to reduced logistics costs, and improved freight efficiency, thereby strengthening India’s logistics ecosystem. (c) Bharatmala Pariyojana Phase-I was approved by the Government in 2017 covering a length of 34,800 km across the country. Under the program, projects covering a total length of 26,425 km were awarded and out of this, 20,770 km has already been constructed. The State-wise length of awarded and constructed projects under Bharatmala Pariyojana upto June 2025 is Annexed.ANNEXURE REFERRED TO IN REPLY TO PART (c) OF LOK SABHA UNSTARRED QUESTION NO. 3124 ANSWERED ON 7TH AUGUST, 2025 ASKED BY SHRI JASHUBHAI BHILUBHAI RATHVA, SHRI ANANTA NAYAK, SHRI RAHUL SINGH LODHI, SMT. BIJULI KALITA MEDHI AND SHRI ANURAG SINGH THAKUR REGARDING ‘OBSTACLES IN THE IMPLEMENTATION OF BHARATMALA PARIYOJANA’. Total Length Awarded Length Constructed till State Length (km) June 2025 (km) (km) Andhra Pradesh 2,525 1,936 1,234 Assam 433 431 349 Bihar 1,572 1,159 698 Chhattisgarh 571 471 344 Delhi 203 203 187 Goa 26 26 26 Gujarat 1,577 1,194 1,023 Haryana 1,058 1,058 977 Himachal Pradesh 167 167 115 Jammu & Kashmir 433 251 145 Jharkhand 1,000 801 508 Karnataka 2,059 1,603 1,156 Kerala 1,126 708 506 Madhya Pradesh 3,063 2,017 1,674 Maharashtra 3,029 2,174 1,944 Manipur 635 635 443 Meghalaya 170 170 118 Mizoram 593 593 493 Nagaland 208 208 153 Odisha 1,586 967 928 Punjab 1,764 1,553 714 Rajasthan 2,503 2,360 2,257 Tamil Nadu 2,414 1,476 1,265 Telangana 1,719 1,026 874 Tripura 94 94 64 Uttar Pradesh 3,126 2,495 2,061 Uttarakhand 273 264 174 West Bengal 874 385 339 Total 34,800 26,425 20,770 *****