As of August 6, 2025, India's installed nuclear power capacity is 8780 MW, comprising 24 reactors, excluding the long-term shutdown RAPS1 (100 MW). Four reactors are currently undergoing refurbishment and upgrade projects: Tarapur Atomic Power Station Units 1&2 (2 x 160 MW), Madras Atomic Power Station Unit 1 (1 x 220 MW), and Kaiga Atomic Power Station Unit 1 (1 x 220 MW). The remaining 20 reactors are operational.
Several projects are under construction, including RAPP8 (1 x 700 MW) in Rajasthan, KKNPP3&4 (2 x 1000 MW) and KKNPP5&6 (2 x 1000 MW) in Kudankulam, Tamil Nadu, PFBR (1 x 500 MW) in Kalpakkam, and GHAVP1&2 (2 x 700 MW) in Gorakhpur, Haryana. Pre-project activities are underway for Kaiga 5&6 (2 x 700 MW) in Karnataka, GHAVP 3&4 (2 x 700 MW) in Gorakhpur, Haryana, Chutka 1&2 (2 x 700 MW) in Madhya Pradesh, and Mahi Banswara 1&2 and 3&4 (4 x 700 MW) in both Rajasthan and Madhya Pradesh.
The Nuclear Power Corporation of India Limited (NPCIL) implements these projects, and BHAVINI is assigned to Anushakti Vidyut Nigam Limited (ASHVINI). Upon completion of these projects, the installed nuclear power capacity is projected to reach 22,380 MW by 2032.
Specifically, at Tarapur, Maharashtra, Units 3&4 (2 x 540 MW) are currently operating, while Units 1&2 (2 x 160 MW) are being refurbished and upgraded. These units will be restarted upon regulatory clearance. The Mahi Banswara Nuclear Power Project (2800 MW total) has acquired land and obtained statutory environmental clearance from the MoEFCC and siting consent from AERB; pre-project activities are in progress.
This information was provided by Dr. Jitendra Singh, Union Minister of State (Independent Charge) for Science and Technology, Earth Sciences, MoS PMO, MoS Personnel, Public Grievances Pensions, Department of Atomic Energy, and Department of Space, in a written reply in the Lok Sabha.
Key Entities Referenced
Kaiga Atomic Power Station: A nuclear power station in Kaiga, Karnataka.
Department of Atomic Energy: The Indian government department responsible for nuclear energy.
Tarapur Atomic Power Station: A nuclear power station in Tarapur, Maharashtra.
Madras Atomic Power Station: A nuclear power station in Kalpakkam, Tamil Nadu.
Rajasthan Atomic Power Project: A nuclear power plant located in Rawatbhata, Rajasthan.
Kudankulam Nuclear Power Project: A nuclear power plant located in Kudankulam, Tamil Nadu.
Bhavini: Bharatiya Nabhikiya Vidyut Nigam Limited, an Indian nuclear power company.
Dr. Jitendra Singh: Union Minister of State Independent Charge for Science and Technology, Earth Sciences, MoS PMO, MoS Personnel, Public Grievances Pensions, Department of Atomic Energy and Department of Space
Department of Atomic Energy
PARLIAMENT QUESTION: OPERATIONAL
NUCLEAR POWER PLANTS
Posted On: 06 AUG 2025 4:38PM by PIB Delhi
Presently, the installed nuclear power capacity in the country comprises of 24 reactors with a total capacity of
8780 MW, excluding RAPS-1 (100 MW), which is under long term shut down. Among these 24 reactors, 4
nos. of reactors i.e., Tarapur Atomic Power Station Units-1&2 (2 x 160 MW), Madras Atomic Power Station
Unit-1 (1x220 MW) and Kaiga Atomic Power Station Unit-1 (1x220 MW) are presently in project mode for
carrying out refurbishment & upgradation activities and remaining 20 reactors are operational.
The details are given below:
State Location Project Capacity (MW)
Projects Under Construction
Rajasthan Rawatbhata RAPP-8 1X 700
KKNPP-3&4 2 X 1000
Kudankulam
Tamil Nadu KKNPP-5&6 2 X 1000
Kalpakkam PFBR& 1 X 500
Haryana Gorakhpur GHAVP-1&2 2 X 700
Projects Under Pre-Project Activities
Karnataka Kaiga Kaiga-5&6 2 X 700
Haryana Gorakhpur GHAVP– 3&4 2 X 700
Madhya Pradesh Chutka Chutka-1&2 2 X 700
Mahi Mahi Banswara-1&2* 2 X 700
Rajasthan
Banswara Mahi Banswara-3&4* 2 X 700
& Implemented by BHAVINI
*Assigned to Anushakti Vidyut Nigam Limited (ASHVINI)
With progressive completion of the projects under implementation, the installed nuclear power capacity is
expected to reach 22,380 MW by 2032.
There are four reactors Units-1&2 (2 x 160 MW) and Units-3&4 (2 x 540 MW) at Tarapur, Maharashtra.
Presently, Units- 3&4 are operating while Units-1 & 2 (2 x 160 MW) are undergoing refurbishment and
upgradation. On completion of these activities Units-1&2, will be restarted in line with regulatory clearance.
The Mahi Banswara Nuclear Power Project with a total capacity of 2800 MW comprises Units 1&2 (2x700
MW) and Units 3&4 (2x700 MW). Land has been acquired, statutory environment clearance from MoEFCC
and siting consent from AERB have been obtained. Presently, pre-project activities are in progress at the site.
This information was given by Dr. Jitendra Singh, Union Minister of State (Independent Charge) for Scienceand Technology, Earth Sciences, MoS PMO, MoS Personnel, Public Grievances & Pensions, Department of
Atomic Energy and Department of Space, in a written reply in the Lok Sabha today.
***