GOVERNMENT OF INDIA
MINISTRY OF PETROLEUM AND NATURAL GAS
RAJYA SABHA
UNSTARRED QUESTION NO - 3493
ANSWERED ON - 23/03/2026
OPERATIONALIZATION OF PNG AND CNG IN ODISHA
3493 SHRI SUBHASISH KHUNTIA:
Will the Minister of PETROLEUM AND NATURAL GAS be pleased to state:
(a) whether domestic PNG connections have been released in Cuttack, Bhubaneswar and Puri since
commissioning of the pipeline and if so, the number thereof;
(b) whether CNG stations are operational in these cities and if so, the number thereof;
(c) whether targets were fixed for PNG connections and the achievement against such targets; and
(d) whether any delay has occurred in consumer-level rollout despite pipeline commissioning and the
reasons therefor?
ANSWER
THE MINISTER OF STATE IN THE MINISTRY OF PETROLEUM AND NATURAL GAS
(SHRI SURESH GOPI)
(a) to (d) Providing Piped Natural Gas (PNG) connections, establishment of Compressed Natural Gas
(CNG) stations and laying of pipeline infrastructure is part of the development of City Gas
Distribution (CGD) Network, which is carried out by the entities authorized by Petroleum and
Natural Gas Regulatory Board (PNGRB) as per their Minimum Work Programme (MWP) in their
respective Geographical Areas (GAs).
Cuttack, Bhubaneswar and Puri fall under Cuttack District GA, Khordha District GA and Ganjam,
Nayagarh & Puri Districts GA respectively. These GAs have been authorized by PNGRB to GAIL
Gas Limited for development of CGD network. The GA-wise details of MWP targets and
achievements in respect of PNG (D) connections, CNG stations and pipeline infrastructure as on
31.01.2026 are at Annexure.
******Annexure
ANNEXURE REFERRED TO IN REPLY TO PART (a) to (d) OF RAJYA SABHA
UNSTARRED QUESTION NO. 3493 TO BE ANSWERED ON 23.03.2026 REGARDING
OPERATIONALIZATION OF PNG AND CNG IN ODISHA.
GA wise details of MWP targets and achievements in respect of PNG (D) connections, CNG
stations and pipeline infrastructure as on 31.01.2026
Geographical Authorized Date of Date of PNG (D) connections CNG stations Pipeline Infrastructure-
Area/ CGD Authorization Target Inch KM
CGD Entity Completion
Networks
MWP Achievements MWP Achievements MWP Achievements
Target Target Target
Ganjam, GAIL Gas 06-09-2018 31-Mar-30 51000 8078 15 11 650 1149
Nayagarh & Limited (New start
Puri Districts date
01.01.2022)
Khordha GAIL 07-03-2018 31-Mar-27 26900 76911 NA 24 1513 1577
District (India) (New start
Limited date
01.07.2020)
Cuttack GAIL 07-03-2018 31-Mar-27 28959 37931 NA 14 1416 873
District (India) (New start
Limited date
01.07.2020)
(Sourc: PNGRB)
****