Executive Summary & Key Takeaways

**Executive Summary** The document addresses outstanding dues payable by Distribution Companies (DISCOMs) to power generation companies in India, in response to an unstarred question in Lok Sabha. It details the implementation of the Electricity (Late Payment Surcharge and Related Matters) Rules, 2022 (LPS Rules, 2022) as of June 3, 2022. The document outlines the impact of delayed payments, and the government's action plan to mitigate future accumulation of dues, with data current to February 10, 2026. **Key Points / Main Content** * **LPS Rules 2022:** * Implemented on June 3, 2022, to address outstanding dues, including late payment surcharges. * Treated outstanding dues as of June 3, 2022, as legacy arrears and rescheduled them into Equated Monthly Installments (EMIs) for distribution licensees. * Established a framework for time-bound clearance of current dues and regulation of access for persistent payment defaults. * **Impact of Implementation:** * 13 States reported arrears of ₹1,39,947 crore as on June 3, 2022, which were rescheduled under EMI. * 43 EMIs have been paid, reducing outstanding legacy dues to ₹4,109 crore as of February 10, 2026. * DISCOMs are largely paying current dues to avoid action under the rules. * **Consequences of Delayed Payments:** * Leads to cash flow problems for Generation Companies (GENCOs). * Hinders GENCOs' ability to procure fuel, potentially reducing plant output and causing power shortages. * Discourages investment in new generation capacity, including renewable energy projects. * **Government Actions and Schemes:** * LPS Rules help enforce timely payment of GENCOs' dues, ensuring reliable power supply. * Compliance to LPS Rules is a pre-qualifying criterion for DISCOMs seeking financial assistance under the Revamped Distribution Sector Scheme (RDSS). * Additional Prudential Norms introduced, making loans to State DISCOMs/TRANSCOS/GENCOs contingent on compliance with LPS Rules. * **Data on Outstanding Dues:** * State-wise outstanding dues payable by DISCOMs under LPS Rules are enclosed in Annexure-I. * Outstanding dues payable to State power generation companies of major states are enclosed in Annexure-II. **Impact Analysis** **DISCOMS** * **Impact:** Required to adhere to the LPS Rules for payment of dues, including legacy arrears, through EMIs. They risk losing access to financial assistance under RDSS and new loans if they fail to comply. * **Action Required:** Ensure timely payments of EMIs and current dues to avoid penalties and maintain access to financial assistance. **GENCOS** * **Impact:** LPS Rules aim to ensure timely payment of dues, improving cash flow and enabling fuel procurement for consistent power generation. * **Action Required:** Monitor payments from DISCOMs and report any non-compliance with LPS Rules to the Ministry of Power. **State Governments/Utilities** * **Impact:** State-owned utilities, including DISCOMs, TRANSCOs, and GENCOs, must comply with LPS Rules to be eligible for loans. * **Action Required:** Ensure State utilities adhere to LPS Rules and prescribed conditions to secure financial assistance and maintain a reliable power supply.

Key Entities Referenced

Electricity (Late Payment Surcharge and Related Matters) Rules, 2022 (LPS Rules, 2022): Rules notified by the Ministry of Power in June 2022 to address outstanding dues of power generating companies. Revamped Distribution Sector Scheme (RDSS): A scheme launched in 2021 where compliance with LPS Rules is a pre-qualifying criterion for DISCOMs to receive financial assistance. Ministry of Power: The primary regulator and governing body for power sector policies mentioned. Distribution Companies (DISCOMs): Entities responsible for distributing electricity to end consumers, key stakeholders of the policy. States of India: Location, in the context of the applicability of the policy for outstanding power dues.
Official Source Record View Original Source →
See Full Document Text
GOVERNMENT OF INDIA MINISTRY OF POWER LOK SABHA UNSTARRED QUESTION NO.2134 ANSWERED ON 12.02.2026 OUTSTANDING DUES PAYABLE BY DISCOMS †2134. SHRI RAVINDRA SHUKLA ALIAS RAVI KISHAN: SMT. ROOPKUMARI CHOUDHARY: Will the Minister of POWER be pleased to state: (a) the details of total outstanding dues payable by Distribution Companies (DISCOMs) to Union, State and Private Power Generation Companies in the country, State-wise; (b) whether any scheme has been proposed for settlement of the said dues and if so, the details thereof; (c) whether Uttar Pradesh, Maharashtra and Andhra Pradesh are among the States having the highest outstanding dues and if so, the details thereof; (d) the details of the said outstanding dues indicating separately the share pertaining to coal based, gas based, hydro power and renewable energy generating companies, category-wise; (e) whether the total outstanding dues were approximately 1.39 lakh crore in the year 2022 which have been reduced through various schemes and if so, the major reasons for such reduction; (f) the impact of delayed payments on power generation and fuel supply; and (g) the details of the Government's action plan to prevent accumulation of such outstanding dues in future? A N S W E R THE MINISTER OF STATE IN THE MINISTRY OF POWER (SHRI SHRIPAD NAIK) (a) to (g): (i) The Ministry of Power, Government of India notified the Electricity (Late Payment Surcharge and Related Matters) Rules, 2022 (LPS Rules, 2022) on 3rd June 2022. Under these rules, all outstanding dues, including late payment surcharge, of generating companies (Independent Power Producers, Central Public Sector Enterprises and renewable energy developers), inter-State transmission licensees, and trading licensees, outstanding as on 3rd June 2022, were treated as legacy arrears and rescheduled with re-determined due dates for payment by distribution licensees in Equated Monthly Instalments (EMIs). Accordingly, 13 States reported arrears amounting to ₹1,39,947 crore as on 03.06.2022 which were rescheduled under the EMI mechanism. ……….2.- 2 - The LPS Rules also lay down a framework for time-bound clearance of current dues and provide for progressive regulation of access in the event of persistent payment defaults by distribution licensees. (ii) As a result of these measures, 43 EMIs have been paid by the distribution utilities concerned, including pre-payment of legacy dues by some utilities, and the outstanding legacy dues have reduced to Rs. 4,109 crore as on 10.02.2026. DISCOMs are also largely paying their current dues in time to avoid action under the rules. (iii) Delayed payments by Distribution Companies (DISCOMs) to Generation Companies (GENCOs) lead to cash flow problems, hindering GENCOs’ ability to buy enough fuel on time, which may lead to reduced plant output and power shortages. Such delays also discourage investments in new power generation capacity, including renewable energy projects. LPS rules have helped in enforcing timely payment of GENCOs’ dues facilitating reliable supply of power. (iv) Further, under the Revamped Distribution Sector Scheme (RDSS) launched by Government of India in the year 2021, compliance to LPS Rules by DISCOMs has been prescribed as a pre-qualifying criterion under the Result Evaluation Framework for evaluating the DISCOMs for availing financial assistance under the scheme. (v) Also, Ministry of Power has introduced Additional Prudential Norms for sanctioning of loans to State DISCOMs/ TRANSCOs/ GENCOs. These essentially entail that loans to DISCOMs and other State owned utilities would be contingent to their performance against prescribed conditions, which includes compliance to LPS Rules by DISCOMs. (vi) The State-wise outstanding dues payable by DISCOMs under the LPS Rules are enclosed at Annexure-I. Further, the outstanding dues payable to State power generation companies of major states are enclosed at Annexure-II. *********ANNEXURE-I ANNEXURE REFERRED IN REPLY TO PARTS (a) TO (g) OF UNSTARRED QUESTION NO. 2134 ANSWERED IN THE LOK SABHA ON 12.02.2026 ************* Details of State-wise outstanding dues as on 03.06.2022 and balance outstanding dues as on 10.02.2026 to be paid to Suppliers* (In Rs. Cr.) As on As on 10.02.2026 03.06.2022 Balance legacy Sr. Current Total State Discom Legacy d u e s a f t e r No. Overdues Overdues Overdues as payment of as per (Current + per Discoms 43 EMIs as PRAAPTI Legacy) per DISCOMs Andhra Pradesh Power 1 Andhra Pradesh Purchase Coordination 0 1,561 1,561 Committee Andhra Pradesh Southern 2 Andhra Pradesh Power Distribution 0 277 277 Company Limited Andhra Pradesh Eastern 3 Andhra Pradesh Power Distribution 0 76 76 Company Limited Andhra Pradesh Central 4 Andhra Pradesh Power Distribution 18,309 0 69 69 Company Limited Arunachal Arunachal Power 5 - 0 0 0 Pradesh Distribution Department Assam Power Distribution 6 Assam - 0 29 29 Company Limited North Bihar Power 7 Bihar 430 0 71 71 Distribution Company Ltd. South Bihar Power 8 Bihar 662 0 0 0 Distribution Company Ltd. Chandigarh Power 9 Chandigarh - 0 0 0 Distribution Limited Chhattisgarh State Power 10 Chhattisgarh Distribution Company 4,162 0 68 68 Limited The New Delhi Municipal 11 Delhi - 0 91 91 Council BSES Rajdhani Power 12 Delhi - 0 2 2 Limited Delhi Tata Power 13 Delhi - 0 6 6 Distribution Limited BSES Yamuna Power 14 Delhi - 0 0 0 Limited Dadra And Nagar Haveli And Daman And Diu 15 DNH & DD - 0 0 0 Power Distribution Corporation Ltd 16 Goa Goa Power Department - 0 1 1 Gujarat UrjaVikas Nigam 17 Gujarat - 0 6,546 6,546 Limited Haryana Power Purchase 18 Haryana - 0 124 124 Centre Himachal Himachal Pradesh State 19 - 0 36 36 Pradesh Electricity Board LimitedJammu And Kashmir Jammu and 20 State Power Trading 14,164 0 943 943 Kashmir Company Limited Jharkhand Bijli Vitran 21 Jharkhand 6,000 0 809 809 Nigam Limited Bangalore Electricity 22 Karnataka 7,529 763 1,181 1,945 Supply Company Ltd. Hubli Electricity Supply 23 Karnataka 2,528 0 532 532 Company Ltd. Gulbarga Electricity 24 Karnataka 2,129 52 245 296 Supply Company Ltd. Chamundeshwari 25 Karnataka Electricity Supply 1,247 115 67 181 Corporation Limited Mangalore Electricity 26 Karnataka 125 13 1 14 Supply Company Ltd. Kerala State Electricity 27 Kerala - 0 70 70 Board Limited Madhya Madhya Pradesh Power 28 8,500 0 645 645 Pradesh Management Co Ltd Maharashtra State 29 Maharashtra Electricity Distribution 17,320 1,438 1,494 2,932 Co. Ltd Adani Electricity Mumbai 30 Maharashtra - 0 0 0 Limited Tata Power Co Ltd- 31 Maharashtra - 0 48 48 Mumbai Distribution Manipur State Power 32 Manipur Distribution Company 161 0 43 43 Limited Meghalaya Power 33 Meghalaya Distribution Corporation - 0 17 17 Limited Mizoram Power 34 Mizoram - 0 0 0 Department Nagaland Power 35 Nagaland - 0 21 21 Department Grid Corporation of 36 Odisha - 0 241 241 Odisha Puducherry Power 37 Puducherry - 0 0 0 Department Punjab State Power 38 Punjab - 0 498 498 Corporation Limited Jodhpur VidyutVitran 39 Rajasthan 8,874 0 945 945 Nigam Ltd. Jaipur VidyutVitran 40 Rajasthan 9,264 0 443 443 Nigam Ltd. Ajmer VidyutVitran Nigam 41 Rajasthan 4,096 0 270 270 Ltd. Rajasthan Discoms Power 42 Rajasthan - 0 0 0 Procurement Centre 43 Sikkim Sikkim Power Department - 0 0 0 Tamil Nadu Generation & 44 Tamil Nadu Distribution Corporation 17,734 1,729 172 1,901 Limited Southern Power 45 Telangana Distribution Company Of 6,973 0 132 132 Telangana Telangana State Northern 46 Telangana Power Distribution 2,977 0 25 25 CompanyTripura State Electricity 47 Tripura - 0 85 85 Corporation Limited Uttar Pradesh Power 48 Uttar Pradesh 6,762 0 2,938 2,938 Corporation Ltd Noida Power Company 49 Uttar Pradesh - 0 1 1 Limited Uttarakhand Power 50 Uttarakhand - 0 57 57 Corporation Limited West Bengal State 51 West Bengal Electricity Distribution - 0 247 247 Company Ltd. Damodar Valley 52 West Bengal - 0 2 2 Corporation India Power Corporation 53 West Bengal - 0 52 52 Limited Total 1,39,947 4,109 21,178 25,287 *Suppliers include generating, transmission and trading companies. ******************ANNEXURE-II ANNEXURE REFERRED IN REPLY TO PARTS (a) TO (g) OF UNSTARRED QUESTION NO. 2134 ANSWERED IN THE LOK SABHA ON 12.02.2026 ************* Outstanding dues payable to State power generation companies of major states as on 31.03.2025 Receivables for sale of Power Major States (Rs crore) Andhra Pradesh APGENCO 8,538 Assam APGCL 446 Chhattisgarh CSPGCL 2,590 Gujarat GSECL 331 Haryana HPGCL 905 Jharkhand JUUNL 29 Karnataka KPCL 12,398 Madhya Pradesh MPPGCL 6,205 Maharashtra MSPGCL 25,454 Meghalaya MePGCL 552 Odisha OPGCL 521 Rajasthan RRVUNL - Telangana TSGENCO 11,649 Uttar Pradesh UPRVUNL 7,090 Uttarakhand UJVNL 322 West Bengal WBPDCL 10,917 Total 87,948 *************