GOVERNMENT OF INDIA
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
RAJYA SABHA
UNSTARRED QUESTION NO - 2992
ANSWERED ON - 18/03/2026
PENDING COMPENSATION REGARDING STRR PROJECT
2992. SHRI JAGGESH:
Will the Minister of ROAD TRANSPORT AND HIGHWAYS be pleased to state:-
(a) whether it is a fact that compensation payable to land losers under the Bengaluru Satellite Town
Ring Road (STRR) project is still pending;
(b) whether the prolonged delay in settlement of compensation has adversely affected the livelihood of
the displaced landowners;
(c) whether Government has fixed any timeline for clearing all outstanding compensation dues under
the project;
(d) whether any special measures are being implemented to ensure early resolution of compensation-
related grievances of the affected persons; and
(e) if so, the details thereof?
ANSWER
THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS
(SHRI NITIN JAIRAM GADKARI)
(a) to (e) The details are annexed.ANNEXURE
ANNEXURE REFERRED TO IN REPLY TO PARTS (a) to (e) OF RAJYA SABHA UNSTARRED
QUESTION NO. 2992 ANSWERED ON 18/03/2026 ASKED BY SHRI JAGGESH REGARDING
‘PENDING COMPENSATION REGARDING STRR PROJECT’.
LA Status of the Project:
Sr. Project name 3A in 3D in 3G 3G Amount Remarks
No. Ha Ha Approved Approved Disbursed
in Ha Amount Rs. in Cr.
Rs. in Cr.
1 Construction of Satellite 517.63 517.63 517.63 1508.16 216.92 The project is under
Town Ring Road (STRR), (before Nov, process of appraisal &
NH948A, Obalapura to 2023) approval. The
Kunagal from Km 0.0 to compensation for land
Km 79.0 Phase -I in being acquired, can be
Karnataka on HAM disbursed after
[Project Length – 79.0 Km] approval of the project.
2 Construction of STRR, 434.28 434.28 434.28 633.03 52.7
NH948A, Kunagal to S. (before
Mudugadapalli from km November
79.0 to km 2023)
144.25/144.0 Phase -II in
Karnataka & Tamil Nadu
on HAM [Project length -
65.250 km]
3 Bangalore Chennai 101.08 101.08 101.08 1082.57 990.40 Provisional Completion
Expressway Package-1 Certificate(PCC) issued
(Length 7.0 Km forms part Progress: 99%
of STRR)
4 4L of Dobbaspet to 141.42 141.42 141.42 493.66 407.75 PCC issued
Doddaballapura Bypass Progress: 99.2%
section of NH-648 from km
0.00 to km
42.00 [Bangalore Ring
Road Pkg 1]
5 4L of Dodaballapur Bypass 188.27 188.27 188.27 864.64 715.38 PCC issued
to Hoskote section of NH- Progress: 99.2 %
648 from Km 42.00 to km
80.00 [Bangalore Ring
Road Pkg 2]
6 4 lane Green field Highway 135.53 135.53 135.53 599.62 542.45 Under construction
from TN/KA Border to Progress: 93.7%
Hoskote from Km 0.00 to
Km 20.90
7 4-Lane of Belagondapalli 221.15 221.15 220.65 222.10 194.49 Under construction
(Tamil Nadu) to Karnataka Progress: 83%
/ Tamil Nadu border
NH948A - from km
144.170 to Km 179.936
*****