See Full Document Text
GOVERNMENT OF INDIA
MINISTRY OF POWER
RAJYA SABHA
UNSTARRED QUESTION NO.2705
ANSWERED ON 16.03.2026
POWER AVAILABILITY ESSENTIAL FOR THE ECONOMIC GROWTH
2705 SHRI P. P. SUNEER:
Will the Minister of POWER be pleased to state:
(a) whether it is a fact that the power sector is the backbone of India’s economy and reliable
power supply is essential for the country’s growth ,particularly for building our own AI capabilities
and infrastructure; and
(b) if so, the details and the steps that are proposed to be taken to increase the power availability
in the country?
A N S W E R
THE MINISTER OF STATE IN THE MINISTRY OF POWER
(SHRI SHRIPAD NAIK)
(a) & (b): Yes. There is adequate availability of power in the country. Present installed
generation capacity of the country is 520.51 GW (as on January, 2026). Government of India has
addressed the critical issue of power deficiency by adding 296.388 GW of fresh generation capacity
since April, 2014 transforming the country from power deficit to power sufficient.
The Government have taken the following steps to increase the power availability in the country:
1. Generation and Storage Planning:
(i) As per National Electricity Plan (NEP), installed generation capacity in 2031-32 is likely to
be 874 GW. With a view to ensure generation capacity remains ahead of projected peak
demand, All the States, in consultation with CEA, have prepared their “Resource Adequacy
Plans (RAPs)”, which are dynamic 10-year rolling plans and include power generation as
well as power procurement planning.
(ii) All the States were advised to initiate process for creating/ contracting generation
capacities; from all generation sources, as per their Resource Adequacy Plans.
(iii) In order to augment the power generation capacity, the Government of India has initiated
following capacity addition programme:
(A) The projected thermal (coal and lignite) capacity requirement by the year 2034–35 is
estimated at approximately 3,07,000 MW as against the 2,11,855 MW installed capacity as
on 31.03.2023. To meet this requirement, Ministry of Power has envisaged to set up an
additional minimum 97,000 MW coal and lignite based thermal capacity.
To meet this requirement, several initiatives have already been undertaken. Thermal
capacities of around 18,160 MW have already been commissioned since April 2023 till
31.01.2026. In addition, 38,745 MW of thermal capacity (including 4,845 MW of stressed
thermal power projects) is currently under construction. The contracts of 22,920 MW have
been awarded and are due for construction. Further, 24,020 MW of coal and lignite-based
candidate capacity has been identified which is at various stages of planning in the country.(B) 12,723.50 MW of Hydro Electric Projects are under construction. Further, 4,274
MW of Hydro Electric Projects are under various stage of planning and targeted to be
completed by 2031-32.
(C) 6,600 MW of Nuclear Capacity is under construction and targeted to be completed
by 2029-30. 7,000 MW of Nuclear Capacity is under various stages of planning and approval.
(D) 1,57,800 MW Renewable Capacity including 67,280 MW of Solar, 6,500 MW of
Wind and 60,040 MW Hybrid power is under construction while 48,720 MW of Renewable
Capacity including 35,440 MW of Solar and 11,480 MW Hybrid Power is at various stages
of planning and targeted to be completed by 2029-30.
(E) In energy storage systems, 11,620 MW/69,720 MWh Pumped Storage Projects
(PSPs) are under construction. Further, a total of 6,580 MW/39,480 MWh capacity of
Pumped Storage Projects (PSPs) are concurred and yet to be taken up for construction.
Currently, 9,653.94 MW/ 26,729.32 MWh Battery Energy Storage System (BESS) capacity
are under construction and 19,797.65 MW/ 61,013.40 MWh BESS capacity are under
tendering stage.
2. Transmission Planning: Inter and Intra-State Transmission System has been planned and
implementation of the same is taken up in matching time frame of generation capacity addition. As
per the National Electricity Plan, about 1,91,474 ckm of transmission lines and 1,274 GVA of
transformation capacity is planned to be added (at 220 kV and above voltage level) during the ten-
year period from 2022-23 to 2031-32.
In addition to the above, the Ministry of Power has issued guidelines dated 14.06.2024,
21.03.2025 and 15.12.2025 regarding the payment of compensation for Right of Way (RoW) for
transmission lines, wherein the land rate has been linked to the prevailing market rate. These
guidelines address the key challenges of RoW arising from landowners demanding higher
compensation than the rates determined by the State Government.
3. Promotion of Renewable Energy Generation:
(i) 100% Inter State Transmission System (ISTS) charges have been waived for inter-state
sale of solar and wind power for projects to be commissioned by 30th June 2025 (with
waiver tapering off 25% annually till June 2028), for co-located BESS projects
commissioned by June 2028, for Hydro PSP projects where construction work awarded
by June 2028, for Green Hydrogen Projects commissioned till December 2030 and for
offshore wind projects commissioned till December 2032.
(ii) Standard Bidding Guidelines for tariff based competitive bidding process for
procurement of Power from Grid Connected Solar, Wind, Wind-Solar Hybrid and Firm
& Dispatchable RE (FDRE) projects have been issued.
(iii) Renewable Energy Implementing Agencies (REIAs) are regularly inviting bids for
procurement of RE power.
(iv) Foreign Direct Investment (FDI) has been permitted up to 100 percent under the automatic
route.
(v) To augment transmission infrastructure needed for steep RE trajectory, transmission plan
has been prepared till 2032.
(vi) Laying of new intrastate transmission lines and creating new sub-station capacity has been
supported under the Green Energy Corridor Scheme for evacuation of renewable power.(vii) Scheme for setting up of Solar Parks and Ultra Mega Solar Power projects is being
implemented to provide land and transmission to RE developers for installation of RE
projects at large scale.
(viii) Schemes such as Pradhan Mantri Kisan Urja Suraksha evam Utthaan Mahabhiyan (PM-
KUSUM), PM Surya Ghar Muft Bijli Yojana, National Programme on High Efficiency
Solar PV Modules, New Solar Power Scheme (for Tribal and PVTG Habitations/Villages)
under Pradhan Mantri Janjati Adivasi Nyaya Maha Abhiyan (PM JANMAN) and Dharti
Aabha Janjatiya Gram Utkarsh Abhiyan (DA JGUA), National Green Hydrogen Mission,
Viability Gap Funding (VGF) Scheme for Offshore Wind Energy Projects have been
launched.
(ix) To encourage RE consumption, Renewable Purchase Obligation (RPO) followed by
Renewable Consumption Obligation (RCO) trajectory has been notified till 2029-30. The
RCO which is applicable to all designated consumers under the Energy Conservation Act,
2001 will attract penalties on non-compliance.
(x) “Strategy for Establishment of Offshore Wind Energy Projects” has been issued.
(xi) Green Term Ahead Market (GTAM) has been launched to facilitate sale of Renewable
Energy Power through exchanges.
(xii) Production Linked Incentive (PLI) scheme has been launched to achieve the objective of
localization of supply chain for solar PV Modules.
*************