GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 3042
TO BE ANSWERED ON 11.03.2026
PROGRESS OF KOLKATA METRO YELLOW LINE
3042. DR. KAKOLI GHOSH DASTIDAR:
Will the Minister of RAILWAYS be pleased to state:
(a) the detailed project/progress report of the metro line connecting
Noapara-Jai Hind Airport- Barasat;
(b) whether any feasibility study has been done on the same and if so, the
details thereof; and
(c) the details of the projected timeline for the completion of the said
project?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (c): Metro project in Kolkata started in 1972. The details of the Metro
commissioned since then are as under:
Period Metro Commissioned
1972 to 2014 (42 years) 28 km
2014 to 2025 (11 years) 45 km
The details of Metro Corridors commissioned are as under:
S.No. Metro Corridor Section Commissioned
Kavi Subash – Noapara (28 Km) This Corridor commissioned
1 (Blue Line) before year 2014 (This required
about 42 years to complete)
§Noapara – Dakshineswar (4.14 This Corridor commissioned in
2
Km) (Extension of Blue Line) 2020-21
Noapara – Jaihind Airport - Noapara – Jaihind Airport section
3
Barasat (18 Km) (Yellow Line) (6.77 Km) Commissioned in 2025-26
Joka – Majerhat - Esplanade (14 Joka – Majerhat section (7.74 Km)
4 KM) (Purple Line) Commissioned in stages from
2022 to 2024
New Garia - Belaghata - New Garia – Belaghata (9.8 Km)
5 Dumdum Airport (32 Km) Commissioned in stages between
(Orange Line) 2023-26
Howrah Maidan – Salt Lake Sec. This Corridor commissioned in
6
V (16.55 Km) (Green Line) stages from 2019 to 2025
Further, work pertaining to 4 Metro corridors at total length of about 52 km
is under progress, out of which 20 km of work is held up due to land
acquisition and utility shifting issues pertaining to State Government. In
the rest of the Metro stretch, though the work is in progress yet facing
difficulties due to one or other reasons at the end of State Government.
Details are as below:
(i) Noapara – Jaihind Airport - Barasat (18 km): Noapara - Jai Hind
Airport (6.77 km) has been commissioned and work from Jai Hind
Airport to Michael Nagar is in progress. However, work from New
Barrackpore to Barasat (7.5 km) is held up due to land acquisition and
encroachment issues by State authorities.
SN Location Issues
1. New Land acquisition (23,000 sq. m) and removal
Barrackpore to of heavy encroachments (1277 hutments,
Barasat 764 shops) are involved in this section. The matter is not yet resolved by
Government of West Bengal (GoWB).
(ii) Joka –Majerhat - Esplanade (14 km):- Joka - Majerhat (7.74 km) has
been commissioned and balance work from Majerhat to Esplanade
(6.26 km) has been taken up. However, progress of the work is
affected due to the following issues:
SN Location Issues
1. Khidderpur For utility shifting and road traffic diversion, 837
Metro sqm permanent and 1,702 sqm temporary land
Station of State Government (Kolkata Armed Police) is
required. The proposal of this land was sent to
State Government on 24.08.2020.
Several meetings were held with officials of
Government of West Bengal (GoWB) for transfer
of above land.
After lot of persuasion, State Government finally
accorded approval in July 2025 only after almost
5 years.
2. Dr. B.C. Roy For construction of Esplanade Metro Station,
Market temporary shifting of unauthorised 528 Shops at
B.C. Roy Market on Defence land is required.
The proposal for NOC of temporary/permanent
shifting of these shops was submitted to State
Government in February 2022. Shops for
temporary shifting of these unauthorized shops
have also been constructed by Railway.SN Location Issues
The State Government has been requested to
facilitate shifting. Regular follow up with State
PWD is also being done.
Issue is pending for more than 3.5 years.
(iii) New Garia –Belaghata - Dum Dum Airport (32 km): New Garia -
Belaghata (9.8 km) has been commissioned and balance work from
Belaghata to Dum Dum Airport (22.2 km) has been taken up. However,
progress of the work is affected due to the following issues:
SN Location Issues
1. Chingrighata Temporary traffic diversion at Chingrighata
Crossing crossing for launching of viaduct segments is
(Between required for 3 nights each on either side of the
Beleghata – road (8 hours on every night).
Gour Kishore The proposal was submitted to Government of
Ghosh stations) West Bengal (GoWB) in December 2024.
The diversion road as desired by Kolkata
traffic police has already been constructed in
February 2025.
Since then, several meetings have been held
with various State Government and Kolkata
police officials for NOC.
The NOC is still awaited even after about 12
months.
(iv) Baranagar - Barrackpore - Dakshineshwar (14.5 km): Baranagar -
Dakshineshwar (2 km) has been commissioned and balance work fromBaranagar to Barrackpore (12.5 km) is held up due to pending utility
shifting in the alignment by state government authorities. The details
are as below:
SN Location Issues
1. Baranagar The original alignment along the B.T road was
to agreed in 2011 as per MoU among Metro
Barrackpore Railway, RVNL and Kolkata Municipal
Corporation.
As per MoU, existing pipeline was to be replaced
by new 64-inch diameter pipeline by the State
Government.
Shifting of this pipeline was completed in 2012.
However, NOC is still awaited from Government
of West Bengal.
Completion of Railway project/s depends on various factors which include
the following:
Land acquisition by State Government
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time of the project/s.
*****