Executive Summary:
This document provides details on railway projects related to new lines, gauge conversions, doubling, and electrification for the Northern, North Central, and North Eastern Railway Zones as of April 1, 2025. It also covers projects under Rashtriya Rail Sanraksha Kosh (RRSK), the provision of Electronic Interlocking Systems in Uttar Pradesh, fund allocation, and instances of project delays and cost overruns. The information was provided in response to questions raised in Lok Sabha.
Key Points / Main Content:
Railway Project Sanctioning:
Projects are sanctioned based on remunerativeness, traffic projections, connectivity, state government demands, operational requirements and socio-economic factors.
Zonal railway-wise project details are available on the Indian Railways website.
Electrification Status:
Entire Broad Gauge Railway lines of Northern Railway, North Central Railway and North Eastern Railway have been electrified.
North Eastern Railway Projects (as of 01.04.2025):
17 sanctioned projects (8 New Line, 1 Gauge Conversion, 8 Doubling) totaling 1252 km and costing approximately ₹20,466 crore.
354 km commissioned, with approximately ₹10,485 crore spent up to March 2025.
North Central Railway Projects (as of 01.04.2025):
18 sanctioned projects (3 Gauge Conversion, 15 Doubling) totaling 1874 km and costing approximately ₹25,829 crore.
565 km commissioned, with approximately ₹14,057 crore spent up to March 2025.
Northern Railway Projects (as of 01.04.2025):
29 sanctioned projects (8 New Line, 21 Doubling) totaling 1169 km and costing approximately ₹69,731 crore.
344 km commissioned, with approximately ₹31,625 crore spent up to March 2025.
Safety Measures:
Accidents have decreased significantly, with Consequential Train Accidents reducing from 135 in 2014-15 to 31 in 2024-25.
Accidents Per Million Train Kilometer (APMTKM) improved by approximately 73% during the same period.
Increased expenditure on safety-related activities, with a budget of ₹1,16,470 crore for 2025-26.
Safety Enhancements:
Electronic Interlocking Systems provided at 6,635 stations (up to 30.06.2025).
Interlocking of Level Crossing Gates provided at 11,096 locations (up to 30.06.2025).
Complete Track Circuiting provided at 6,640 stations (up to 30.06.2025).
Kavach deployed on 1548 RKm on South Central Railway and North Central Railway, with ongoing work on Delhi-Mumbai and Delhi-Howrah corridors.
Uttar Pradesh Railway Projects:
535 stations in Uttar Pradesh have Electronic Interlocking System.
49 sanctioned projects (10 New Line, 2 Gauge Conversion, 37 Doubling) totaling 3,808 Km and costing ₹62,360 crore.
1,323 Km commissioned, with ₹30,611 crore spent up to March 2025.
Budget allocation for 2025-26 is ₹19,858 crore, nearly 18 times the 2009-14 outlay.
Project Completion Factors:
Completion depends on land acquisition, forest clearances, utility shifting, statutory clearances, geological conditions, and law and order.
Government Steps for Speedy Implementation:
Gati Shakti units, project prioritization, increased funding, delegation of powers, close monitoring, and regular follow-up with state governments.
Impact Analysis:
Ministry of Railways:
Impact: Responsible for planning, sanctioning, executing, and monitoring railway projects across various zones. Requires efficient allocation and utilization of funds, adherence to safety standards, and coordination with state governments for project implementation.
Action Required: Continue monitoring project progress, address delays and cost overruns, ensure safety measures are implemented effectively, and maintain transparency through the Indian Railways website.
Zonal Railways (Northern, North Central, North Eastern):
Impact: Responsible for executing sanctioned projects within their respective zones. Requires effective project management, adherence to timelines, and coordination with various departments and stakeholders.
Action Required: Expedite project execution, ensure quality and safety, address local challenges, and provide regular updates to the Ministry of Railways.
State Governments (Uttar Pradesh, Madhya Pradesh, Rajasthan, Haryana, Punjab, Himachal Pradesh, Uttarakhand, Delhi, Chandigarh, Jammu Kashmir, Ladakh, Bihar):
Impact: Play a crucial role in land acquisition, forest clearances, and resolving local issues related to project implementation.
Action Required: Facilitate land acquisition, expedite clearances, and provide necessary support for smooth project execution.
General Public:
Impact: Benefits from improved railway infrastructure, increased connectivity, enhanced safety, and reduced travel time.
Action Required: Utilize the improved infrastructure responsibly and provide feedback to the railway authorities for further improvements.
Key Entities Referenced
Rashtriya Rail Sanraksha Kosh RRSK: A fund for railway safety projects.
Northern Railway: One of the 18 zones of Indian Railways.
North Central Railway: One of the 18 zones of Indian Railways.
North Eastern Railway: One of the 18 zones of Indian Railways.
Uttar Pradesh: A state in India where many railway projects are underway.
Electronic Interlocking System: A railway signalling system to prevent accidents, installed at stations.
Kavach: A National Automatic Train Protection (ATP) system adopted in July 2020 to enhance railway safety.
LHB design coaches: Modern passenger coaches being introduced to replace conventional ICF design coaches to improve safety.
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 1690
TO BE ANSWERED ON 30.07.2025
PROJECTS UNDER RASHTRIYA RAIL SANRAKSHA KOSH
1690. MS IQRA CHOUDHARY:
SHRI PUSHPENDRA SAROJ:
Will the Minister of RAILWAYS be pleased to state:
(a) the details of the status of all the railway projects related to
new railway lines, gauge conversions, doubling and
electrification of existing railway lines for the Northern, North
Central & North Eastern Railway Zones;
(b) the details of the status of all the projects under Rashtriya Rail
Sanraksha Kosh (RRSK) in the above mentioned three zones;
(c) the details of the number of stations in Uttar Pradesh that have
been provided Electronic Interlocking System, district-wise;
(d) the details of funds allocated, sanctioned and spent for the
projects, year-wise; and
(e) whether any delays and cost-overruns have been witnessed in
the above projects, if so, the details thereof along with the
estimated increase in costs and timeline for completion?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (e): Railway projects are sanctioned on the basis of
remunerativeness, traffic projections, last mile connectivity,
missing links and alternate routes, augmentation of
congested/saturated lines, demands raised by State Governments,
..P/2-:2:-
Central Ministries, Members of Parliament, other public
representatives, Railway’s own operational requirement, socio-
economic considerations etc. depending upon throwforward of
ongoing projects and overall availability of funds.
Zonal Railway wise details of projects are made available in public
domain on Indian Railways website.
Entire Broad Gauge Railway lines of Northern Railway, North Central
Railway and North Eastern Railway have been electrified.
Details of sanctioned Railway infrastructure projects (New Line,
Gauge Conversion and Doubling) being executed in North Eastern
Railway, North Central Railway and Northern Railway are given
below:
North Eastern Railway
North Eastern Railway zone span across the States of Uttar
Pradesh, Bihar and Uttarakhand.
As on 01.04.2025, across North Eastern Railway, 17 Railway
infrastructure projects (08 New Line, 01 Gauge Conversion and 08
Doubling) of total length 1252 Km, costing approx. 20,466 crore are
sanctioned, out of which, 354 Km length has been commissioned
and an expenditure of approx. 10,485 lakh crore has been incurred
upto March, 2025. The summary is as under:-
..P/3-:3:-
Total Length
Total Exp
No of Length Commissioned
Category upto Mar'25
Projects NL/GC/DL till Mar'25
( in crore)
(km) (Km)
New Lines 8 656 48 4042
Gauge 1 56 0 260
Conversion
Doubling / 8 541 306 6184
Multitracking
Total 17 1252 354 10485
North Central Railway
North Central Railway zone span across the States of Uttar Pradesh,
Madhya Pradesh, Rajasthan and Haryana.
As on 01.04.2025, across North Central Railway, 18 Railway
infrastructure projects (03 Gauge Conversion and 15 Doubling) of
total length 1874 Km, costing approx. 25,829 crore are sanctioned,
out of which, 565 Km length has been commissioned and an
expenditure of approx. 14,057 lakh crore has been incurred upto
March, 2025. The summary is as under:-
Total Length
Total Exp
No of Length Commissioned
Category upto Mar'25
Projects NL/GC/DL till Mar'25
( in crore)
(km) (Km)
Gauge 3 440 97 2903
Conversion
Doubling / 15 1433 468 11155
Multitracking
Total 18 1874 565 14057
..P4-:4:-
Northern Railway
Northern Railway zone span across the States of Punjab, Haryana,
Himachal Pradesh, Uttarakhand, Uttar Pradesh, Delhi, Chandigarh,
Jammu & Kashmir and Ladakh.
As on 01.04.2025, across Northern Railway, 29 Railway
infrastructure projects (08 New Line and 21 Doubling) of total length
1169 Km, costing approx. 69,731 crore are sanctioned, out of
which, 344 Km length has been commissioned and an expenditure
of approx. 31,625 lakh crore has been incurred upto March, 2025.
The summary is as under:-
Total Length
Total Exp
No of Length Commissioned
Category upto Mar'25
Projects NL/GC/DL till Mar'25
( in crore)
(km) (Km)
New Lines 8 499 80 28288
Doubling / 21
670 264 3337
Multitracking
Total 29 1169 344 31625
Safety is accorded the highest priority on Indian Railways. As a
consequence of various safety measures taken over the years, there
has been a steep decline in the number of accidents. Consequential
Train Accidents have reduced from 135 in 2014-15 to 31 in 2024-25 as
shown in the graph below.
It may be noted that the Consequential Train Accidents during the
period 2004-14 was 1711 (average 171 per annum), which has
declined to 31 in 2024-25 and further to 3 in 2025-26 (upto June).
..P/5-:5:-
Another important index showing improved safety in train operations
is Accidents Per Million Train Kilometer (APMTKM) which has reduced
from 0.11 in 2014-15 to 0.03 in 2024-25, indicating an improvement of
approx. 73% during the said period.
234
165
135
55 48
40
35 31
22
3
2005- 2009- 2014- 2019- 2020- 2021- 2022- 2023- 2024- 2025-26
06 10 15 20 21 22 23 24 25 (up to
Covid Covid Jun'25)
year year
The various safety measures taken to enhance safety in train
operations are as under:-
1. On Indian Railways, the expenditure on Safety related activities
has increased over the years as under:-
Expenditure on Safety related activities ( in Cr.)
2013-14 2022-23 2023-24
RE 2024-25 BE 2025-26
(Act.) (Act.) (Act.)
Maintenance of
Permanent Way 9,172 18,115 20,322 21,800 23,316
& Works
Maintenance of
Motive Power
14,796 27,086 30,864 31,540 30,666
and Rolling
Stock
..P/6
stnediccA
niarT
laitneuqesnoC
fo
.oN-:6:-
Maintenance of
5,406 9,828 10,772 12,112 12,880
Machines
Road Safety
LCs and ROBs/ 1,986 5,347 6,662 8,184 7,706
RUBs
Track
4,985 16,326 17,850 22,669 22,800
Renewals
Bridge Works 390 1,050 1,907 2,130 2,169
Signal &
905 2,456 3,751 6,006 6,800
Telecom Works
Workshops
Incl. PUs and
Misc. 1,823 7,119 9,523 9,581 10,134
expenditure on
Safety
Total 39,463 87,327 1,01,651 1,14,022 1,16,470
2. Electrical/Electronic Interlocking Systems with centralized
operation of points and signals have been provided at 6,635
stations up to 30.06.2025 to reduce accident due to human
failure.
3. Interlocking of Level Crossing (LC) Gates has been provided at
11,096 level Crossing Gates up to 30.06.2025 for enhancing
safety at LC gates.
4. Complete Track Circuiting of stations to enhance safety by
verification of track occupancy by electrical means has been
provided at 6,640 stations up to 30.06.2025.
5. Kavach is a highly technology intensive system, which requires
safety certification of highest order. Kavach was adopted as a
National ATP system in July 2020. Kavach is provided
..P/7-:7:-
progressively in phased manner. Kavach has already been
deployed on 1548 RKm on South Central Railway and North
Central Railway. Presently, the work is in progress on Delhi-
Mumbai and Delhi-Howrah corridors (approximately 3000 RKm).
Track side works on these routes have been completed on
about 2200 RKm as on 30.06.2025. Regular trials are being done
on these sections.
6. Detailed instructions on issues related with safety of Signalling,
e.g. mandatory correspondence check, alteration work protocol,
preparation of completion drawing, etc. have been issued.
7. System of disconnection and reconnection for S&T equipment
as per protocol has been re-emphasized.
8. All locomotives are equipped with Vigilance Control Devices
(VCD) to improve alertness of Loco Pilots.
9. Retro-reflective sigma boards are provided on the mast which is
located two OHE masts prior to the signals in electrified
territories to alert the crew about the signal ahead when
visibility is low due to foggy weather.
10. A GPS based Fog Safety Device (FSD) is provided to loco pilots
in fog affected areas which enables loco pilots to know the
distance of the approaching landmarks like signals, level
crossing gates, etc.
..P/8-:8:-
11. Modern track structure consisting of 60kg, 90 Ultimate Tensile
Strength (UTS) rails, Prestressed Concrete Sleeper (PSC)
Normal/Wide base sleepers with elastic fastening, fan shaped
layout turnout on PSC sleepers, Steel Channel/H-beam Sleepers
on girder bridges is used while carrying out primary track
renewals.
12. Mechanisation of track laying activity through use of track
machines like PQRS, TRT, T-28 etc. to reduce human errors.
13. Maximizing supply of 130m/260m long rail panels for increasing
progress of rail renewal and avoiding welding of joints, thereby
improving safety.
14. Ultrasonic Flaw Detection (USFD) testing of rails to detect flaws
and timely removal of defective rails.
15. Laying of longer rails, minimizing the use of Alumino Thermic
Welding and adoption of better welding technology for rails i.e.,
Flash Butt Welding.
16. Monitoring of track geometry by OMS (Oscillation Monitoring
System) and TRC (Track Recording Cars).
17. Patrolling of railway tracks to look out for weld/rail fractures.
18. The use of Thick Web Switches and Weldable CMS Crossing in
turnout renewal works.
..P/9-:9:-
19. Inspections at regular intervals are carried out to monitor and
educate staff for observance of safe practices.
20. Web based online monitoring system of track assets viz. Track
database and decision support system has been adopted to
decide rationalized maintenance requirement and optimize
inputs.
21. Detailed instructions on issues related with safety of Track, e.g.
integrated block, corridor block, worksite safety, monsoon
precautions, etc. have been issued.
22. Preventive maintenance of railway assets (Coaches & Wagons)
is undertaken to ensure safe train operations.
23. Replacement of conventional ICF design coaches with LHB
design coaches is being done.
24. All unmanned level crossings (UMLCs) on Broad Gauge (BG)
route have been eliminated by January 2019.
25. Safety of Railway Bridges is ensured through regular inspection
of Bridges. The requirement of repair/rehabilitation of Bridges is
taken up based upon the conditions assessed during these
inspections.
26. Indian Railways has displayed Statutory “Fire Notices” for
widespread passenger information in all coaches. Fire posters
..P/10-:10:-
are provided in every coach so as to educate and alert
passengers regarding various Do’s and Don’ts to prevent fire.
These include messages regarding not carrying any inflammable
material, explosives, prohibition of smoking inside the coaches,
penalties etc.
27. Production Units are providing Fire detection and suppression
system in newly manufactured Power Cars and Pantry Cars, Fire
and Smoke detection system in newly manufactured coaches.
Progressive fitment of the same in existing coaches is also
underway by Zonal Railways in a phased manner.
28. Regular counseling and training of staff is undertaken.
29. Concept of Rolling Block introduced in Indian Railways (Open
Lines) General Rules vide Gazette notification dated
30.11.2023, wherein work of integrated maintenance/
repair/replacement of assets is planned up to 52 weeks in
advance on rolling basis and executed as per plan.
The details of the Safety related works related to better
maintenance practices, Technological improvements, better
infrastructure and rolling stock etc. undertaken by Railways are
tabulated below:-
..P/11-:11:-
2004-05 to 2014-15 to 2014-25 Vs.
SN Item
2013-14 2024-25 2004-14
Technological improvements
Use of high-quality More than 2
1. 57,450 Km 1.43 Lakh Km
rails (60 Kg) (Km) times
Longer Rail Panels Nearly 8
2. 9,917 Km 77,522 Km
(260m) (Km) times
Electronic
More than 4
3. Interlocking 837 Stations 3,691 Stations
times
(Stations)
Fog Pass Safety As on 31.03.14: As on 31.03.25:
4. 288 times
Devices (Nos.) 90 Nos. 25,939
Thick Web
5. Nil 28,301 Nos.
Switches (Nos.)
Better maintenance practices
Primary Rail
1. Renewal (Track 32,260 Km 49,941 Km 1.5 times
Km)
USFD (Ultra Sonic
Flaw detection) More than 2
2. 79.43 Lakh 2 Crore
Testing of Welds times
(Nos.)
In 2013-14: In 2024-25: 90 %
3. Weld failures (Nos.)
3699 Nos. 370 Nos. reduction
More than
Rail fractures In 2013-14: In 2024-25:
4. 88%
(Nos.) 2548 Nos. 289 Nos.
reduction
Better infrastructure and Rolling stock
New Track KM More than 2
1. 14,985 Nos. 34,428 Km
added (Track km) times
Flyovers (RoBs)/
More than 3
2. Underpasses 4,148 Nos. 13,808 Nos.
times
(RUBs) (Nos.)
As on 31.03.24:
Unmanned Level
As on 31.03.14: Nil
3. crossings Removed
8948 (All eliminated
(nos.) on BG
by 31.01.19)
Manufacture of
More than
4. LHB Coaches 2,337 Nos. 42,677
18 times
(Nos.)
..P/12-:12:-
535 stations in Uttar Pradesh have been provided with Electronic
Interlocking System.
Uttar Pradesh
Railway infrastructure projects falling fully/partly in the State of
Uttar Pradesh are covered under Northern Railway, North Central
Railway, North Eastern Railway, East Central Railway and West
Central Railway zones of Indian Railways. Zonal Railway wise
details of Railway projects are made available in public domain on
Indian Railway’s website.
As on 01.04.2025, 49 Railway projects (10 New Line, 02 Gauge
Conversion and 37 Doubling), of total length of 3,808 Km costing
₹62,360 crore falling fully/partly in the State of Uttar Pradesh are
sanctioned, out of which 1,323 Km length has been commissioned
and an expenditure of ₹30,611 crore has been incurred upto March
2025.
The status of work is summarized as under:-
Total Length Expenditure upto
No. of
Plan Head Length Commissioned March 2025
projects
(in Km) (in Km) (₹in Cr)
New Lines 10 1227 340 10517
Gauge
2 67 0 281
Conversion
Doubling /
37 2513 983 19813
Multitracking
Total 49 3808 1323 30611
..P/13-:13:-
Budget allocation for Infrastructure projects and safety works,
falling fully/ partly in Uttar Pradesh is as under:
Period Outlay
2009-14 1,109 crore/year
2025-26 19,858 Crore (nearly 18 times)
The details of commissioning / laying of new track falling
fully/partly in the State of Uttar Pradesh during 2009-14 and 2014-25
is as under :-
New Track Average Commissioning of new
Period
Commissioned tracks
2009-14 996 Km 199.2 Km/year
479.3 km per year (More than 2
2014-25 5272 Km
times)
Details of some of the recently completed projects falling fully/partly
in Uttar Pradesh are as under:
Estimated
S.No. Project Cost
(₹ in Crores)
1 Agra-Etawah New Line(110 km) 427
Guna-Gwalior-Bhind-Etawah New Line (348
2 683
km)
Lalitpur Khajuraho/Tikamgarh(Mawai)-
3 800
Khajuraho sectionNew Line (165 km)
4 Etawah-Mainpuri New Line (58 km) 313
5 Ghazipur city-Tarighat New Line (17 km) 1766
Gonda-Gorakhpur Loop Gauge
6 863
Conversion(260 km)
..P/14-:14:-
Kanpur-Kasganj-Mathura &Kasgan-Bareilly
7 1790
Gauge Conversion (545 km)
Kaptanganj-Thawe-Chhapra Gauge
8 819
Conversion (234 km)
Bareilly-Pilibhit-Tanakpur Gauge Conversion
9 313
(102 km)
10 Gonda-Bahraich Gauge Conversion (60 km) 318
Pilibhit-Shahjahanpur Gauge Conversion (83
11 589
km)
12 Indara-Dohrighat Gauge Conversion (34 km) 213
13 Lucknow-Pilibhit Gauge Conversion (263 km) 1634
14 Utretia-Zafrabad – Doubling(148 km) 890
15 Bhadoi-Janghai Doubling(31 km) 168
16 Banupur-Panki Doubling (11 km) 55
17 Lahota-Bhadoi Doubling (39 km) 184
18 Aurnihar-Manduadih Doubling (39 km) 200
19 Meerut-Muzaffarnagar Doubling (55 km) 430
20 Ghazipur-Aunrihar Doubling (40 km) 371
21 Phaphamau-PrayagrajDoubling (14 km) 212
22 Muzaffarnagar – Tapri Doubling (52 km) 525
23 Mathura-Palwal Doubling (80 km) 669
24 Utretia-Raibareilly Doubling (66 km) 662
25 Raibareilly-Amethi Doubling (60 km) 668
26 Alamnagar-Utretia Doubling (20 km) 358
27 Bhimsen—Jhansi Doubling (206 km) 2620
97
28 Bhaupur-Panki Doubling (11 km)
29 Ballia-Gazipur city Doubling (65 km) 650
30 Aunrihar-Jaunpur Doubling (60 km) 405
31 Malhaur-Daliganj Doubling (13 km) 183
32 Ruma Chakeri- Chandari Doubling (13 km) 177
33 ChipiyanaBuzurg - Dadri Doubling (12 km) 129
34 Barabanki-Akbarpur Doubling (161 km) 1700
..P/15-:15:-
Rosa-Sitapur Cantt-Burhwal Doubling (181
35 2094
km)
Eastern Dedicated Freight Corridor (1756
36 51219
km)
37 Jaunpur- Akbarpur (Tanda) Doubling (77 km) 676
38 Dailwara-BiraiDoubling (7.55 km) 77
39 Ramna-Singrauli Doubling (160 km) 2436
40 Janghai- PhaphamauDoubling (47 km) 414
Varanasi-Madhosingh-PrayagrajDoubling
41 2018
(120 km)
42 Karaila Road- Shaktinagar Doubling (32 km) 763
43 Deoband -Roorkee New Line ( 29 km) 1289
Some of the projects falling fully/partly in Uttar Pradesh which have
been taken up are as under:
Estimated
S.No. Project Cost
(₹ in Crores)
1 Chhitauni-Tumkuhi Road New Line( 59 km) 1731
2 Anandnagar-Ghugli New Line ( 53 km) 958
3 Sahjanwa-Dohrighat New Line ( 81 km) 1320
4 Bahraich- Khalilabad New Line ( 240 km) 4940
5 Etah-Kasganj New Line ( 29 km) 389
6 Unchhar-Amethi New Line ( 66 km) 1229
Lalitpur-Satna, Rewa-Singrauli & Mahoba-
7 8914
Khajuraho New Line ( 541 km)
Bahraich-Nanpara-Nepal Ganj Gauge
8 342
Conversion( 56 km)
Pandit Deen Dayal Upadhyay -Prayagraj 3rd
9 2649
Line( 150 km)
10 Jhansi-Bina 3rd Line( 153 km) 2002
11 Mathura-Jhansi 3rd Line ( 274 km) 5924
Jhansi-Khairar-Manikpur & Khirar-Bhimsen
12 Doubling 4330
( 431 km)
..P/16-:16:-
13 Aligarh Flyover ( 22 km) 1179
14 Agra Fort -Bandikui Doubling ( 150 km) 988
15 Aligarh - Daud Khan 3rd Line ( 18 km) 452
16 Billi- Chunar Doubling( 102 km) 1424
17 Chhapra-Ballia Patch Doubling (65 km) 1046
Domingarh-Gorakhpur-Gorakhpur Cantt.-
18 508
Kusumhi – 3rd Line (21 km)
19 Burhwal Gonda 3rd Line( 62 km) 1118
Phephna-Indara, Mau-Shahganj Doubling (
20 1778
150 km)
21 Bhatni-Aurnihar Doubling (117 Km) 2529
22 Gorakhpur- Valmikinagar Doubling ( 96 km) 1120
23 Utretia-Zafrabad Doubling( 263 km) 1582
Janghai-Pratapgarh- Amethi Doubling ( 87
24 1197
km)
25 Barabanki-Malhaur 3rd and 4th Line (33 km) 407
26 Phaphamau-Unchahahar Doubling (72 km) 971
27 Barabanki-Burhwal 3rd Line (27 Km) 426
Prayagraj (Iradatganj)-Manikpur 3rd Line (84
28 1508
km)
Completion of Railway project/s depends on various factors like
quick land acquisition by State Government, forest clearance by
officials of forest department, shifting of infringing utilities,
statutory clearances from various authorities, geological and
topographical conditions of area, law and order situation in the area
of project/s site, number of working months in a year for particular
project site etc. All these factors affect the completion time and
cost of the project/s.
..P/17-:17:-
Various steps taken by the Government for speedy approval and
implementation of Railway projects include (i) setting up of Gati
Shakti units (ii) prioritisation of projects (iii) substantial increase in
allocation of funds on priority projects (iv) delegation of powers at
field level (v) close monitoring of progress of project at various
levels, and (vi) regular follow up with State Governments and
concerned authorities for expeditious land acquisition, forestry and
Wildlife clearances and for resolving other issues pertaining to
projects. This has led to substantial increase in rate of
commissioning since 2014.
*******