**Executive Summary**
This document presents the Ministry of Railways' response to Lok Sabha Starred Question No. 45, concerning the Pune-Nashik Semi-High-Speed Railway Project, to be answered on 03.12.2025. It outlines the progress of various projects aimed at improving connectivity between Pune and Nashik, focusing on budgetary allocations, project timelines, and measures to ensure the project benefits both industries and the public. The document also highlights the factors influencing project timelines and costs.
**Key Points / Main Content**
* **Pune-Nashik Connectivity Projects:**
* Several surveys and works are underway to improve connectivity between Pune and Nashik.
* Nashik – Sainagar Shirdi New Double Line (95 km): DPR prepared.
* Sainagar Shirdi - Puntamba-Doubling (16 km): Project recently sanctioned.
* Puntamba –Nimblak Doubling (80 km): Recently Commissioned.
* Nimblak – Ahilyanagar Doubling (6 km): Work in progress.
* Ahilyanagar- Pune New Double Line (133 km): DPR prepared, passing through Shirur constituency area.
* Another DPR was prepared by Maharashtra Rail Infrastructure Development Corporation Ltd. (MRIDC) to provide connectivity between Pune and Nashik via Sangamner (near Akole). However, the proposed alignment was found unacceptable due to its adverse impact on the Giant Metrewave Radio Telescope (GMRT) Observatory.
* **Budgetary Allocation (Maharashtra):**
* The budget allocation for infrastructure projects and safety works in Maharashtra has significantly increased.
* 2009-14: ₹ 1,171 crore/year.
* 2025-26: ₹ 23,778 crore.
* **New Track Commissioning (Maharashtra):**
* Details of new track commissioning/laying in Maharashtra are as follows:
* 2009-14: 292 km (58.4 km/year).
* 2014-25: 2,292 km (208.36 km/year).
* **Sanctioned Projects (Maharashtra):**
* As of 01.04.2025, 38 projects (11 New Lines, 2 Gauge Conversions, and 25 Doubling) with a total length of 5,098 km, costing ₹ 89,780 crore, have been sanctioned.
* 2,360 km have been commissioned, and an expenditure of ₹ 39,407 crore has been incurred up to March 2025.
* **Completed/Ongoing Projects in Maharashtra:**
* Includes projects like Pune-Miraj-Londa doubling, Manmad-Jalgaon 3rd line, Jabalpur-Gondia Gauge Conversion, etc.
* Lists projects like Ahilyanagar-Beed-Parli Vaijnath New Line, Baramati-Lonand New Line, Wardha-Nanded New Line, etc.
* **Surveys:**
* In the last three years 2022-23, 2023-24, 2024-25 and the current financial year 2025-26, 98 surveys (29 New Line, 2 Gauge Conversion and 67 Doubling) of total length 8603 Km. falling fully/ partly in the State of Maharashtra have been sanctioned under PM Gati Shakti NMP.
* **Project Sanctioning Factors:**
* Sanction of any railway project depends upon many parameters/factors which include the following: Anticipated traffic projections and Remunerativeness of the proposed route, First and last mile connectivity provided by the project, Connection of missing links and providing additional route, Augmentation of congested/saturated lines, Demands raised by State Governments/Central Ministries/Public representatives, Railway's own operational requirements, Socio-economic considerations and Overall availability of funds.
* **Factors Affecting Project Completion:**
* Completion of railway projects depends on various factors: land acquisition, forest clearance, shifting utilities, statutory clearances, geological conditions, law and order, and available working months.
**Impact Analysis**
**State Government (Maharashtra)**
* **Impact:** The State Government is a key stakeholder as railway projects fall within its geographical boundaries and require its cooperation for land acquisition, statutory clearances, and overall support.
* **Action Required:** The State Government needs to collaborate with the Ministry of Railways to ensure smooth land acquisition, provide necessary clearances, and address any local issues that may affect project progress.
**General Public and Farmers of Shirur Lok Sabha Constituency**
* **Impact:** The projects aim to provide affordable and reliable transportation, benefiting the public and farmers by improving connectivity and accessibility.
* **Action Required:** The general public and farmers should be informed about the progress of the projects and any potential disruptions during construction. They may also need to provide feedback on the proposed infrastructure improvements to ensure they meet their needs.
**Industries**
* **Impact:** Improved railway infrastructure will enhance transportation efficiency, facilitating movement of goods and reducing logistics costs, thereby boosting industrial growth.
* **Action Required:** Industries should assess how the improved railway connectivity can optimize their supply chains and plan their logistics accordingly.
**Ministry of Railways**
* **Impact:** Responsible for planning, execution, and monitoring of the Pune-Nashik Semi-High-Speed Railway Project and other railway infrastructure projects in Maharashtra.
* **Action Required:** The Ministry needs to continue coordinating with various stakeholders, addressing challenges like land acquisition and environmental concerns, and ensuring timely completion of projects.
**GMRT Observatory/Department of Atomic Energy**
* **Impact:** The GMRT Observatory could be adversely impacted by certain railway alignments due to potential interference with its operations.
* **Action Required:** The Ministry of Railways needs to consider the concerns of the Department of Atomic Energy and ensure that any new railway alignments do not adversely impact the operations of the GMRT Observatory.
Key Entities Referenced
Ministry of Railways: The primary government body responsible for the Pune-Nashik semi-high-speed railway project and other railway projects mentioned in the document.
Pune-Nashik Semi-High Speed Railway Project: The central project discussed in the parliamentary question and subsequent statement, detailing its current status, budgetary allocation, and timeline.
Maharashtra: The state where the Pune-Nashik railway project and numerous other railway projects are located, significantly impacted by railway development and budget allocations.
PM Gati Shakti NMP: A national master plan under which railway projects falling partly/fully in Maharashtra have been sanctioned.
NITI Aayog: A body involved in the appraisal of railway projects before sanctioning.
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
STARRED QUESTION NO. 45
TO BE ANSWERED ON 03.12.2025
PUNE – NASHIK SEMI – HIGH SPEED RAILWAY PROJECT
*45. DR. AMOL RAMSING KOLHE:
Will the Minister of RAILWAYS be pleased to state:
(a) the details of the current status/progress of the Pune-Nashik semi-
high-speed railway project including land acquisition
process/challenges being faced;
(b) the details of total budgetary allocation for this project during the last
three Union Budgets and the actual expenditure incurred till date;
(c) the revised timeline for completion of the project along with the steps
being taken to fast-track the work; and
(d) the manner in which the Government ensures that this project will not
only benefit industries but also provide an affordable/reliable mode of
transport for the general public and farmers of the Shirur Lok Sabha
Constituency?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (d): A Statement is laid on the Table of the House.
*****STATEMENT REFERRED TO IN REPLY TO PARTS (a) TO (d) OF LOK SABHA
STARRED QUESTION NO. 45 TO BE ANSWERED ON 03.12.2025.
(a) to (d): To improve connectivity between Pune and Nashik, following
surveys/works have been taken up:-
S.No. Name of the Work Length in Status
km.
1 Nashik – Sainagar Shirdi New 95 DPR prepared
Double Line
2 Sainagar Shirdi - Puntamba- 16 Project recently
Doubling sanctioned
3 Puntamba –Nimblak Doubling 80 Recently
Commissioned
4 Nimblak – Ahilyanagar Doubling 6 Work in progress
5 Ahilyanagar- Pune New Double 133 DPR prepared
Line
The proposed Ahilyanagar- Pune New Double Line (133 Km) for which DPR
has proposed is passing through Shirur constituency area.
After preparation of DPR, sanctioning of project requires consultation with
various stake-holders including State Governments and necessary
approvals viz. appraisal of NITI Aayog, Ministry of Finance etc. As
sanctioning of projects is a continuous and dynamic process, exact
timelines depend upon appraisals and approvals by various stakeholders.
To provide connectivity between Pune and Nashik via Sangamner (near
Akole), another DPR was prepared by Maharashtra Rail InfrastructureDevelopment Corporation Ltd. (MRIDC), a Joint Venture company of
Government of Maharashtra (50%) and Ministry of Railways (50%).
The proposed alignment in the DPR was passing through Narayangaon
where National Centre for Radio Astrophysics (NCRA), Pune has installed
Giant Metrewave Radio Telescope (GMRT) Observatory. GMRT has users
from 31 number of countries (till 28th Cycle) that uses its services for
scientific observations.
Department of Atomic Energy has advised Ministry of Railways that the
alignment is passing near the GMRT Observatory and will have potential
interference and harmful impact on its operations. As such, this alignment
was not found acceptable due to adverse impact on the GMRT Observatory.
Maharashtra
Budget allocation in the recent years has increased significantly. Budget
allocation for infrastructure projects and safety works, falling fully/partly in
the State of Maharashtra is as under:
Period Outlay
2009-14 ₹ 1,171 crore/year
2025-26 ₹ 23,778 crore (More than 20 times)
The details of commissioning/laying of new track falling fully/partly in the
State of Maharashtra during 2009-14 and 2014-25 is as under:
Period New track Average commissioning of new
Commissioned tracks
2009-14 292 Km 58.4 Km/year
2014-25 2,292 Km 208.36 Km/year (more than 3 times)As on 01.04.2025, 38 projects (11 New Lines, 02 Gauge Conversion and 25
Doubling), of a total length of 5,098 km, costing ₹ 89,780 crore, falling
fully/partly in Maharashtra, are sanctioned, out of which 2,360 km length
has been commissioned and an expenditure of ₹39,407 crore has been
incurred upto March’ 2025. The summary is as under:-
Category No of sanctioned Total Length Exp.
Projects Length Commissioned upto
(in Km) Upto Mar'25 Mar'25
(Km) (₹ in Cr.)
New Line 11 1,355 234 10,504
Gauge Conversion 02 609 334 4,286
Doubling/Multitracki 25 3,134 1,792 24,617
ng
Total 38 5,098 2,360 39,407
Details of some of the recently completed projects falling fully/partly in
Maharashtra are as under:
S.No. Project Cost
(₹ in crore)
1 Pune- Miraj- Londa doubling (467 Km) 4,670
2 Manmad- Jalgaon 3rd line (160 Km.) 2,574
3 Jabalpur-Gondia Gauge Conversion (300 Km) 2,005
4 Chhindwara-Nagpur Gauge Conversion (150 Km) 1,512
5 Panvel-Pen Doubling (35 Km) 263
6 Pen-Roha Doubling (40 Km) 330
7 Udhna-Jalgaon Doubling (307 Km) 2,448
8 Mudkhed-Parbhani Doubling (81 Km) 673S.No. Project Cost
(₹ in crore)
9 Bhusawal-Jalgaon 3rd Line (24 Km) 325
10 Jalgaon-Bhusawal 4th line (24 Km) 261
11 Daund-Gulbarga Doubling (225 Km) 3,182
Some of the main projects falling fully/partly in the Maharashtra which
have been taken up are as under:
S.N Name of the project Cost (₹ In
o. crore)
1 Ahilyanagar-Beed-Parli Vaijnath New Line (261 Km.) 4,957
2 Baramati-Lonand New Line (64 Km.) 1,844
3 Wardha-Nanded New Line (284 Km.) 3,445
4 Manmad-Indore New Line (360 Km.) 18,529
5 Wadsa-Gadchiroli New Line (52 Km.) 1,886
6 Jalna -Jalgaon New Line (174 Km.) 5,804
7 Daund-Manmad Doubling (236 Km.) 3,037
8 Kalyan-Kasara 3rd line (68 Km.) 1,433
9 Wardha-Nagpur 3rd line (76 Km.) 698
10 Wardha-Ballarshah 3rd line (132 Km.) 1,385
11 Itarsi-Nagpur 3rd line (280 Km.) 2,450
12 Rajnandgaon-Nagpur 3rd line (228 Km.) 3,545
13 Wardha-Nagpur 4th line (79 Km.) 1,137
14 Jalgaon-Manmad 4th Line (160 Km) 2,574
15 Bhusawal-Khandwa 3rd & 4th Line (131 Km.) 3,285
In the last three years 2022-23, 2023-24, 2024-25 and the current financial
year 2025-26, 98 surveys (29 New Line, 2 Gauge Conversion and 67 Doubling)of total length 8603 Km. falling fully/ partly in the State of Maharashtra have
been sanctioned under PM Gati Shakti NMP.
Sanction of any railway project depends upon many parameters/factors
which include the following:
Anticipated traffic projections and Remunerativeness of the proposed
route
First and last mile connectivity provided by the project
Connection of missing links and providing additional route
Augmentation of congested/saturated lines
Demands raised by State Governments/Central Ministries/Public
representatives,
Railway’s own operational requirements
Socio-economic considerations
Overall availability of funds
Further, Construction works on the flagship High speed bullet train project
have gathered momentum in Maharashtra. Now 100% land acquisition has
been completed. Works of bridges, aqueducts etc. have been taken up.
Western DFC also passes through Maharashtra. About 178 route Km of
western DFC is situated in Maharashtra which is about 12% of overall route
length of western DFC. 76 Km of this project from New Gholvad to New
Vaitarna in Maharashtra has already been commissioned. Balance works
have been taken up. Connectivity of WDFC to JNPT will boost the capacity to
handle cargo and container traffic from port to Delhi NCR.
Completion of Railway project/s depends on various factors which include
the following: Land acquisition
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
*****