GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 2819
TO BE ANSWERED ON 05.08.2026
QUANTITY OF MINERALS PROCESSED IN DHULE–NARDANA RAILWAY
PROJECT
2819. DR. BACHHAV SHOBHA DINESH:
Will the Minister of RAILWAYS be pleased to state:
(a) whether the Government has verified the quantity of earth, murum,
stone, sand, ballast and other minor minerals excavated, procured and
utilized in the Dhule (Borvihir)–Nardana New BG Railway Line Project;
(b) whether the contractor/sub-contractors have furnished proof of valid
quarry permits, source approvals, transit passes, royalty, District
Mineral Foundation (DMF) contributions, other statutory compliances
under the MMDR Act, 1957 and the applicable Maharashtra Minor
Mineral Rules;
(c) whether the Government have reconciled such quantities and statutory
payments with the records of the District Mining Officer, Dhule and if
so, the details thereof; and
(d) whether the Government propose to ensure verification of such
statutory compliance before the release of final payments under the
contract?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (d): The quantity of earth, murum, stone, sand, ballast and other
minor minerals excavated, procured and utilized in the Dhule (Borvihir)–
Nardana New Broad Gauge Line Project (51 Km) are measured, duly
accounted for and paid as per the agreement. The valid quarry permits and
other statutory compliances as stipulated in the agreement are furnished
by the respective agency.
§ Page 1 of 3Payment of all statutory charges including Payment of Royalty is the
responsibility of the concerned agency. However, if any discrepancy is
brought to the notice of Railway by concerned State Government officials
before completion of contract agreement then appropriate action including
deduction is taken accordingly.
The Dhule (Borvihir) – Nardana New Line Project (51 Km) has been
sanctioned at a cost of ₹1,251 crore. The details are as under:-
S.No. Name of the Status
Project
1. Dhule (Borvihir) – An expenditure of ₹367 crore has been
Nardana New Line incurred upto March, 2026 and an Outlay of
(51 Km) ₹120 crore has been provided for the year
2026-27.
Land has largely been acquired but there is a
local resistance in work due to demand of
higher compensation by local farmers.
22 out of 40 Minor Bridges have been
completed.
27 out of 46 Road under Bridge (RUB) have
been completed.
Works of Earthwork, Formation, Major Bridges,
ROBs and Station Buildings’ have been taken
up.
Completion of Railway project/s depends on various factors which include
the following:
Page 2 of 3 Land acquisition by State Government
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
Various steps taken by the Government for effective and speedy
implementation of rail projects include:
Substantial increase in allocation of funds.
Delegation of powers at field level.
Close monitoring of progress of project at various levels.
Regular follow up with State Governments and concerned authorities
for expeditious land acquisition, forestry and Wildlife clearances and
for resolving other issues pertaining to projects.
*****