**Executive Summary**
The document is the response of the Minister of Railways to questions raised in Lok Sabha regarding rail facilities in the Banda-Chitrakoot region, to be answered on December 10, 2025. It outlines the current rail connectivity, ongoing projects for doubling and electrification, and station redevelopment plans under the Amrit Bharat Station Scheme. No specific timeframes for project completion are provided due to various factors affecting project progress.
**Key Points / Main Content**
* **Current Connectivity:**
* Banda/Chitrakoot stations are connected to Delhi and Prayagraj by 2 and 10 pairs of trains, respectively, including the Banaras-Khajuraho Vande Bharat Express.
* Manikpur station is served by 45 pairs of trains, providing connectivity to major cities like Delhi, Lucknow, Prayagraj, Varanasi, Mumbai, Kolkata, Kanniyakumari, and Chennai.
* Introduction of new train services/stoppages is an ongoing process dependent on factors like capacity, path availability, rolling stock, infrastructure, and maintenance.
* **Doubling and Electrification:**
* The Jhansi-Banda-Chitrakoot-Manikpur rail line is electrified.
* Doubling of the rail line along with electrification has been sanctioned.
* The Jhansi-Khairar-Manikpur and Khairar-Bhimsen (431 km) doubling project costs Rs. 4,330 crore.
* Approximately 67 Ha of land has been acquired (of a total of 97 Ha) for the project through the State Government in Nov 2022.
* Expenditure up to March 2025 is Rs. 1,830 crore, with an outlay of Rs. 1,416 crore for the financial year 2025-26; 81 km of length has been commissioned so far.
* **Surveys:**
* In the last three years (2022-23 to 2025-26), 119 surveys (33 New Line, 84 Doubling, and 02 Gauge Conversion) covering 6,414 km have been sanctioned in Uttar Pradesh, including the Bundelkhand region.
* 61 surveys (18 New Line & 43 Doubling) covering 5,901 Km have been sanctioned in Madhya Pradesh, including Bundelkhand region.
* DPRs have been prepared for the following projects:
* Bypass RUR Virangna-Lakshmibai-Jhansi-Mustara (07 KM)
* Manikpur-Katni-Jabalpur-Itarsi-3rd line (518 KM)
* Dholpur-Jhansi-Bina 4th line (333KM)
* **Project Completion Factors:**
* Completion depends on land acquisition, forest clearance, shifting of utilities, statutory clearances, geological conditions, law and order, and available working months.
* **Amrit Bharat Station Scheme:**
* The Ministry of Railways launched the Amrit Bharat Station Scheme for station redevelopment.
* The scheme includes master planning and phased implementation to improve stations, focusing on access, integration, and passenger amenities.
* 1,337 stations are identified for development under the scheme, with 157 in Uttar Pradesh, including Manikpur Junction station.
* List of stations identified for development in the state of Uttar Pradesh is provided.
* Works at 22 stations in Uttar Pradesh under Amrit Bharat Station Scheme are completed. (List of stations included)
* Completed and ongoing projects include Manikpur Junction, Banda station and Chitrakut Dham Karwi station.
* **Funding and Challenges:**
* The scheme is generally funded under Plan Head-53 'Customer Amenities.'
* For the five railway zones covering Uttar Pradesh, an allocation of ₹ 4,358 crore has been made for FY 2025-26, with an expenditure of ₹ 2,288 crore incurred up to October 2025.
* Development/upgradation of railway stations is complex, involving safety, statutory clearances, utility shifting, and operation of trains.
**Impact Analysis**
**Passengers**
* **Impact:** Improved rail connectivity to major cities, enhanced station facilities (waiting halls, toilets, accessibility, information systems), and potential new train services.
* **Action Required:** Utilize the improved facilities and services. Provide feedback on improvements, and report any issues or concerns to the railway authorities.
**Residents of Banda-Chitrakoot Region**
* **Impact:** Better connectivity, potential economic development, and improved access to other parts of India.
* **Action Required:** Participate in the planning process for station redevelopment and provide input on local needs and preferences.
**Ministry of Railways/ Railway Authorities**
* **Impact:** Implementation of ongoing projects, managing the Amrit Bharat Station Scheme, and addressing connectivity and infrastructure needs.
* **Action Required:** Ensure timely execution of projects, allocate funds appropriately, address challenges affecting project completion, and monitor progress.
**State Government of Uttar Pradesh**
* **Impact:** Coordination with railway authorities, land acquisition for projects, and facilitating necessary clearances.
* **Action Required:** Provide support for land acquisition, ensure timely clearances, and coordinate with railway authorities to ensure effective project implementation.
Key Entities Referenced
Vande Bharat: A semi-high-speed, intercity electric multiple unit train operated by the Indian Railways.
Banda-Chitrakoot: A region in Uttar Pradesh, India, the focus of the railway facility improvements discussed in the document.
Amrit Bharat Station Scheme: A scheme launched by the Ministry of Railways for the redevelopment of stations with a long-term approach.
Ministry of Railways: The Union Government ministry responsible for the planning, development, and maintenance of rail transport in India.
Uttar Pradesh: A state in India where significant railway development and station redevelopment are taking place under the Amrit Bharat Station Scheme.
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 1834
TO BE ANSWERED ON 10.12.2025
RAIL FACILITIES IN BANDA-CHITRAKOOT REGION
†1834. SMT. KRISHNA DEVI SHIVSHANKAR PATEL:
Will the Minister of RAILWAYS be pleased to state:
(a) whether the Government proposes to connect Banda-Chitrakoot
section directly to Delhi and Prayagraj by introducing Vande Bharat,
Unknown/Intercity ог any new superfast trains and if so, the present
status of the proposal thereof;
(b) the present progress made on the doubling of the Jhansi-Banda-
Chitrakoot route including the Banda-Karwi-Manikpur section and the
estimated timeframe for completion of said work;
(c) whether the Government proposes to develop Manikpur Junction as a
major interchange station enhancing facilities such as platform
expansion, electrification upgradation and stoppage to additional trains
and if so, the details thereof; and
(d) whether the Union Government is working on a special "Bundelkhand
Rail Connectivity Package" to connect the rail network of the
Bundelkhand region with major rail-lines in Purvanchal and North India
and if so, the details thereof?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (d) Presently, Banda/Chitrakoot stations are connected to Delhi and
Praygraj by 02 pairs and 10 pairs of train services respectively. This
……contd/2/2/
includes 26505/06 Banaras-Khajuraho Vande Bharat Express catering to
the needs of Banda-Chitrakoot-Prayagraj sector.
Manikpur station is presently served by 45 pairs of trains providing
connectivity inter alia to Delhi, Lucknow, Prayagraj, Varanasi, Mumbai,
Kolkata, Kanniyakumari, Chennai etc. Besides, introduction of new train
services/stoppage of trains, which is an on-going process, depends on
various factors which include-
• Capacity of that section
• Availability of path
• Availability of required rolling stock
• Availability of matching infrastructure for rolling stock
• Maintenance requirement of railway tracks and other assets.
Doubling and electrification:
Jhansi-Banda-Chitrakoot-Manikpur rail line is electrified. Doubling of this
rail line alongwith electrification has been sanctioned. The details are as
under:
The work on Jhansi-Khairar-Manikpur and Khairar-Bhimsen (431 km)
doubling project has been taken up at a cost of Rs. 4,330 crore. The
project has been notified as “Special Railway Project” for acquisition of
land through State Government in Nov, 2022. Approx 67 Ha of land has
been acquired out of a total 97 Ha. An expenditure of Rs. 1,830 crore has
been incurred up to March 2025 and an outlay of Rs. 1,416 crore has been
provided for for the project the financial year 2025-26. So, far 81 Km
length has been commissioned.
In last three years 2022-23, 2023-24, 2024-25 and current financial year
2025-26, 119 surveys (33 New Line, 84 Doubling and 02 Gauge Conversion)
covering a total length of 6,414 Km have been sanctioned falling
fully/partly in the State of Uttar Pradesh including Bundelkhand region.
……contd/3/3/
In last three years i.e. 2022-23, 2023-24, 2024-25 and current financial
year 2025-26, 61 surveys (18 New Line & 43 Doubling) covering a total
length of 5,901 Km have been sanctioned falling fully/partly in the State of
Madhya Pradesh including Bundelkhand region. Some of the major survey
are:
SL Projects Sanctioned
1 Bypass RUR Virangna-Lakshmibai- Jhansi-Mustara DPR prepared
(07 KM)
2 Manikpur-Katni-Jabalpur-Itarsi-3rd line (518 KM) DPR prepared
3 Dholpur-Jhansi-Bina 4th line (333KM) DPR prepared
Completion of Railway project/s depends on various factors which include
the following:
● Land acquisition
● Forest clearance
● Shifting of infringing utilities
● Statutory clearances from various authorities
● Geological and topographical conditions of area
● Law and order situation in the area of project site
● Number of working months in a year for particular project site etc
Amrit Bharat Station Scheme:
Ministry of Railways has launched Amrit Bharat Station Scheme for
redevelopment of stations with a long-term approach.
The scheme involves preparation of master plans and their
implementation in phases to improve the stations. The master planning
includes:
● Improvement of access to station and circulating areas
● Integration of station with both sides of city
……contd/4/4/
● Improvement of station building
● Improvement of waiting halls, toilets, sitting arrangement, water
booths
● Provision of wider foot over bridge/air concourse commensurate
with passenger traffic
● Provision of lift/escalators/ramp
● Improvement /Provision of platform surface and cover over
platforms
● Provision of kiosks for local products through schemes like ‘One
Station One Product’
● Parking areas, Multimodal integration
● Amenities for Divyangjans
● Better passenger information systems
● Provision of executive lounges, nominated spaces for business
meetings, landscaping, etc. keeping in view the necessity at each
station.
The scheme also envisages sustainable and environment friendly
solutions, provision of ballastless tracks etc. as per necessity, phasing
and feasibility and creation of city centre at the station in the long term.
So far, 1337 stations have been identified for development under Amrit
Bharat Station Scheme, out of which 157 stations including Manikpur
Junction station, are located in the state of Uttar Pradesh. The name of
stations identified for development under Amrit Bharat Station Scheme in
the state of Uttar Pradesh are as following:
……contd/5/5/
State No. of Name of Stations
Stations
Uttar 157 Achnera, Agra Cantt., Agra Fort, Aishbagh Jn, Akbarpur Jn,
Pradesh Aligarh, Amethi, Amroha, Anand Nagar Jn., Aonla, Ayodhya
Dham Junction, Azamgarh, Babatpur, Bachhrawan, Badaun,
Badshahnagar, Badshahpur, Baheri, Bahraich, Balamau Jn.,
Ballia, Balrampur, Banaras, Banda, Barabanki Jn, Bareilly,
Bareilly City, Barhni, Basti, Belthara Road, Bhadohi,
Bharatkund, Bhatni, Bhuteshwar, Bijnor, Bulandsahar,
Chandauli Majhwar, Chandausi, Chilbila, Chitrakut Dham
Karwi, Chopan, Chunar Jn., Daliganj, Darshannagar, Deoria
Sadar, Dhampur, Dildarnagar, Etawah Jn., Farrukhabad,
Fatehabad, Fatehpur, Fatehpur Sikri, Firozabad, Gajraula,
Garhmuktesar, Gauriganj, Ghatampur, Ghaziabad, Ghazipur
City, Gola Gokarnath, Gomtinagar, Gonda, Gorakhpur,
Govardhan, Govindpuri, Gursahaiganj, Haidergarh, Hapur,
Hardoi, Hathras City, Idgah Agra Jn, Izzatnagar, Janghai Jn,
Jaunpur City, Jaunpur Jn, Kannauj, Kanpur Anwarganj,
Kanpur Bridge Left Bank, Kanpur Central, Kaptanganj Jn,
Kasganj Jn, Kashi, Khalilabad, Khorason road, Khurja Jn.,
Kosi Kalan, Kunda Harnamganj, Lakhimpur, Lalganj, Lalitpur
Jn, Lambhua, Lohta, Lucknow (Charbagh) NR, Lucknow city,
Lucknow Jn. (NER), Maa Belha Devi Pratapgarh Junction,
Maghar, Maharaja Bijli Pasi, Mahoba Jn, Mailani Jn, Mainpuri
Jn, Malhaur, Manak Nagar, Manikpur Jn, Mariahu, Mathura
Jn, Mau Jn, Meerut City Jn, Mirzapur, Modinagar,
Mohanlalganj, Moradabad Jn, Muzaffarnagar, Nagina,
Najibabad Jn, Orai, Panki Dham, Phaphamau Jn, Phulpur,
Pilibhit Jn, Pokhrayan, Prayag Jn, Prayagraj Jn, Pt. Deen
Dayal Upadhyay Jn , Rae Bareli Jn, Raja Ki Mandi, Ramghat
Halt, Rampur Jn, Renukoot, Saharanpur Jn., Salempur,
Seohara, Shahganj Jn, Shahjahanpur, Shamli, Shikohabad Jn.,
Shivpur, Siddharth nagar, Sitapur Jn., Sonbhadra, Sri Krishna
Nagar, Sultanpur Jn, Suraimanpur, Swaminarayan Chappia,
Takia, Tulsipur, Tundla Jn., Ujhani, Unchahar, Unnao Jn,
Utraitia Jn, Varanasi Cantt., Varanasi City, Vindhyachal,
Virangana Lakshmibai Jhansi, Vyasnagar, Zafarabad
……contd/6/6/
Development works at railway stations under Amrit Bharat Station Scheme
in the state of Uttar Pradesh have been taken up at a good pace. Till now,
works of 22 stations (Ayodhya Dham, Balrampur, Bareilly City, Bijnor,
Fatehabad, Fatehpur, Gola Gokarnath, Gomtinagar, Govardhan, Govindpuri,
Hathras City, Idgah Agra Jn, Izzatnagar, Mailani, Panki Dham, Pokhrayan,
Ramghat Halt, Saharanpur Jn., Siddharth Nagar, Suraimanpur,
Swaminarayan Chappia, Ujhani) in the state of Uttar Pradesh have been
completed under this scheme.
The works at other stations have also been taken up at good pace and
progress of some of above stations is as given below:
Manikpur Junction station: The work of construction of new G+1 service
building including new waiting room and Government Railway Police (GRP)
office, approach road, parking and Public Address Systems have been
completed. The work of improvement of station building, construction of
second entry building, circulating area, Divyangjan facilities, lighting,
sewage treatment plant and 12 m Foot Over Bridge have been taken up.
Banda station: The works of platform surfacing, drain in circulating area and
boundary wall in parking area have been completed. The work of entrance
gate have been taken up.
Chitrakut Dham Karwi station: The works of improvement of station building,
toilet, platform surfacing, main entrance gate, circulating area and
landscaping have been completed.
Further development / redevelopment / upgradation / modernisation of
stations including provision of passenger amenities at stations on Indian
Railways is a continuous and ongoing process and works in this regard are
undertaken as per requirement, subject to inter-se priority and availability of
funds. The priority for development / redevelopment /
upgradation / modernisation of stations is accorded to higher category of
……contd/7/7/
station over lower category of station while sanctioning and executing
the works.
Development / upgradation / modernisation of stations including under
Amrit Bharat Station Scheme is generally funded under Plan Head-53
‘Customer Amenities’. The details of allocation and expenditure under
Plan Head-53 are maintained Zonal Railway-wise and not work-wise, or
station wise or state-wise. The state of Uttar Pradesh is covered under
the jurisdiction of five railway zones, namely East Central Railway, North
Central Railway, Northern Railway, North Eastern Railway and West
Central Railway. For these zones, an allocation of ₹ 4,358 crore has been
made for the financial year 2025-26, out of which an expenditure (up to
October, 2025) of ₹ 2,288 crore has been incurred so far.
Development / Upgradation of railway stations is complex in nature
involving safety of passengers & trains and requires various statutory
clearances such as fire clearance, heritage, tree cutting, airport
clearance etc. The progress also gets affected due to brownfield related
challenges such as shifting of utilities (involving water/sewage lines,
optical fibre cables, gas pipe lines, power/signal cables, etc.),
infringements, operation of trains without hindering passenger
movement, speed restrictions due to works carried out in close proximity
of tracks and high voltage power lines, etc. and these factors affect the
completion time. Therefore, no time frame can be indicated at this stage.
*****