GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
RAJYA SABHA
UNSTARRED QUESTION NO. 915
ANSWERED ON 06.02.2026
RAIL SAFETY UPGRADES
915 SHRI G.C. CHANDRASHEKHAR:
Will the Minister of RAILWAYS be pleased to state:
(a) accidents or safety incidents reported in Karnataka during 2023–25, the details thereof;
(b) progress of Kavach, track renewal and signalling upgrades; and
(c) funds allocated specifically for safety works in the State?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (c): Safety is accorded the highest priority on Indian Railways. As a consequence of
various safety measures taken over the years, there has been a steep decline in the number of
accidents on Indian Railways including rail network situated in Karnataka.
Number of Consequential Train Accidents has reduced as shown in the table below:-
Year Consequential Accidents
2014-15 135
2025-26 (Till date) 12 (90% lesser)
Another important index showing improvement in safety in train operations is Consequential
Accidents Index, the details of which are as under:-
Consequential Accident Index:-
Year Accident Index
2014-15 0.11
2024-25 0.03 (73% lesser)
This index measures number of consequential accidents as a ratio of total running kilometers of all
trains.
No. of consequential accidents
Accident Index =
No. of trains X million kilometers run234
s
t
n
e
d
i
c
c
A
n 165
i
a
r
T
l 135
a
i
t
n
e
u
q
e
s
n
o 55
C
f
o
.o
31
N
12
2005-06 2009-10 2014-15 2019-20 2024-25 2025-26
(upto Jan 2026)
The various safety measures including track and signalling taken to enhance safety in train
operations are as under:-
1. On Indian Railways, the expenditure on Safety related activities has increased over the years
as under:-
Expenditure/Budget on Safety related activities (Rs. in Cr.)
2013-14 2022-23 2023-24 2024-25 2025-26
39,200 87,336 1,01,662 1,14,022 1,17,693
2. Electrical/Electronic Interlocking Systems with centralized operation of points and signals have
been provided at 6,660 stations up to 31.12.2025 to reduce accidents due to human failure.
3. Interlocking of Level Crossing (LC) Gates has been provided at 10,097 Level Crossing Gates up
to 31.12.2025 for enhancing safety at LC Gates.
4. Complete Track Circuiting of stations to enhance safety by verification of track occupancy by
electrical means has been provided at 6,665 stations up to 31.12.2025.
5. Detailed instructions on issues related with safety of Signalling, e.g. mandatory correspondence
check, alteration work protocol, preparation of completion drawing, etc. have been issued.
6. System of disconnection and reconnection for S&T equipment as per protocol has been re-
emphasized.
7. All locomotives are equipped with Vigilance Control Devices (VCD) to improve alertness of
Loco Pilots.8. Retro-reflective sigma boards are provided on the mast which is located two OHE masts prior to
the signals in electrified territories to alert the crew about the signal ahead when visibility is low
due to foggy weather.
9. A GPS based Fog Safety Device (FSD) is provided to loco pilots in fog affected areas which
enables loco pilots to know the distance of the approaching landmarks like signals, level
crossing gates, etc.
10. Modern track structure consisting of 60kg, 90 Ultimate Tensile Strength (UTS) rails, Prestressed
Concrete Sleeper (PSC) Normal/Wide base sleepers with elastic fastening, fan shaped layout
turnout on PSC sleepers, Steel Channel/H-beam Sleepers on girder bridges is used while
carrying out primary track renewals.
11. Mechanisation of track laying activity through use of track machines like PQRS, TRT, T-28 etc.
to reduce human errors.
12. Maximizing supply of 130m/260m long rail panels for increasing progress of rail renewal and
avoiding welding of joints, thereby improving safety.
13. Ultrasonic Flaw Detection (USFD) testing of rails to detect flaws and timely removal of
defective rails.
14. Laying of longer rails, minimizing the use of Alumino Thermic Welding and adoption of better
welding technology for rails i.e., Flash Butt Welding.
15. Monitoring of track geometry by OMS (Oscillation Monitoring System) and TRC (Track
Recording Cars).
16. Patrolling of railway tracks to look out for weld/rail fractures.
17. The use of Thick Web Switches and Weldable CMS Crossing in turnout renewal works.
18. Inspections at regular intervals are carried out to monitor and educate staff for observance of
safe practices.
19. Web based online monitoring system of track assets viz. Track database and decision support
system has been adopted to decide rationalized maintenance requirement and optimize inputs.
20. Detailed instructions on issues related with safety of Track, e.g. integrated block, corridor block,
worksite safety, monsoon precautions, etc. have been issued.
21. Preventive maintenance of railway assets (Coaches & Wagons) is undertaken to ensure safe train
operations.
22. Replacement of conventional ICF design coaches with LHB design coaches is being done.
23. All unmanned level crossings (UMLCs) on Broad Gauge (BG) route have been eliminated by
January 2019.
24. Safety of Railway Bridges is ensured through regular inspection of Bridges. The requirement of
repair/rehabilitation of Bridges is taken up based upon the conditions assessed during these
inspections.25. Indian Railways has displayed Statutory “Fire Notices” for widespread passenger information in
all coaches. Fire posters are provided in every coach so as to educate and alert passengers
regarding various Do’s and Don’ts to prevent fire. These include messages regarding not
carrying any inflammable material, explosives, prohibition of smoking inside the coaches,
penalties etc.
26. Production Units are providing Fire detection and suppression system in newly manufactured
Power Cars and Pantry Cars, Fire and Smoke detection system in newly manufactured coaches.
Progressive fitment of the same in existing coaches is also underway by Zonal Railways in a
phased manner.
27. Regular counselling and training of staff is undertaken.
28. Concept of Rolling Block introduced in Indian Railways (Open Lines) General Rules vide
Gazette notification dated 30.11.2023, wherein work of integrated maintenance/
repair/replacement of assets is planned up to 52 weeks in advance on rolling basis and executed
as per plan.
The details of the Safety related works related to better maintenance practices, Technological
improvements, better infrastructure and rolling stock etc. undertaken by Railways are tabulated
below:-
2004-05 to 2014-15 to 2014-25 Vs.
S.N. Item
2013-14 2024-25 2004-14
Technological Improvements
1. Use of high-quality rails 57,450 Km 1.43 Lakh Km More than
(60 Kg) (Km) 2 times
2. Longer Rail Panels 9,917 Km 77,522 Km Nearly 8 times
(260m) (Km)
3. Electronic Interlocking 837 Stations 3,691 Stations More than
(Stations) 4 times
4. Fog Pass Safety Devices As on 31.03.14: As on 31.03.25: 288 times
(Nos.) 90 Nos. 25,939 Nos.
5. Thick Web Switches (Nos.) Nil 28,301 Nos.
Better Maintenance Practices
1. Primary Rail Renewal (Track 32,260 Km 49,941 Km 1.5 times
Km)
2. USFD (Ultra Sonic Flaw 79.43 Lakh 2 Crore More than
detection) Testing of Welds 2 times
(Nos.)
3. Weld failures (Nos.) In 2013-14: In 2024-25: 90% reduction
3699 Nos. 370 Nos.
4. Rail fractures (Nos.) In 2013-14: In 2024-25: More than
2548 Nos. 289 Nos. 88% reductionBetter Infrastructure and Rolling Stock
1. New Track KM added (Track 14,985 Km 34,428 Km More than
Km) 2 times
2. Flyovers (RoBs)/Underpasses 4,148 Nos. 13,808 Nos. More than
(RUBs) (Nos.) 3 times
3. Unmanned Level crossings As on 31.03.14: As on 31.03.24:Nil Removed
(Nos.) on BG 8,948 (All eliminated by
31.01.19)
4. Manufacture of LHB 2,337 Nos. 42,677 More than
Coaches (Nos.) 18 times
Implementation of Kavach:
i. Kavach is an indigenously developed Automatic Train Protection (ATP) system. Kavach is a
highly technology intensive system, which requires safety certification of highest order (SIL-
4).
ii. Kavach aids the Loco Pilot in running of trains within specified speed limits by automatic
application of brakes in case Loco Pilot fails to do so and also helps the trains to run safely
during inclement weather.
iii. The first field trials on the passenger trains were started in February 2016. Based on the
experience gained and Independent Safety Assessment of the system by Independent Safety
Assessor (ISA), three firms were approved in 2018-19, for supply of Kavach Ver 3.2.
iv. Kavach was adopted as National ATP system in July, 2020.
v. Implementation of Kavach System involves following Key Activities:
a. Installation of Station Kavach at each and every station, block section.
b. Installation of RFID Tags throughout the track length.
c. Installation of telecom Towers throughout the section.
d. Laying of Optical Fibre Cable along the track.
e. Provision of Loco Kavach on each and every Locomotive running on Indian Railways.
vi. Based on deployment of Kavach version 3.2 on 1465 RKm on South Central Railway and
experience gained, further improvements were made. Finally, Kavach specification version 4.0
was approved by RDSO on 16.07.2024.
vii. Kavach version 4.0 covers all the major features required for the diverse railway network. This
is a significant milestone in safety for Indian Railways. Within a short period, IR has
developed, tested and started deploying Automatic Train Protection System.
viii. Major improvement in Version 4.0 includes increased Location Accuracy, Improved
Information of Signal Aspects in bigger yards, Station to Station Kavach interface on OFC andDirect Interface to existing Electronic Interlocking System. With these improvements, Kavach
Ver.4.0. is planned for large scale deployment over Indian Railways.
ix. After extensive and elaborate trials, Kavach Version 4.0 has been successfully commissioned
on 1297 Route Kilometres, covering the high density Delhi - Mumbai and Delhi – Howrah
routes. On the Delhi – Mumbai route Kavach ver 4.0 has been commissioned on Junction cabin
– Palwal – Mathura – Nagda section (667 Rkm) & Ahmedabad – Vadodara – Virar section
(432 Rkm) and on the Delhi – Howrah route on Gaya – Saramatanr (93 Rkm) and Bardhaman
- Howrah section (105 Rkm).
x. Further, track side Kavach implementation work has been taken up on 23,360 RKM covering
all GQ,GD,HDN and identified sections of Indian Railways.
xi. Progress of key items of Kavach on High density routes including Delhi– Mumbai & Delhi–
Howrah corridors are as under:
S N Item Progress
i Laying of Optical Fibre Cable 8570 Km
ii Installation of Telecom Towers 938 nos
iii Station Data Centre 767 station
iv Installation of Track side equipment 5672 RKm
v Provision of Kavach in Loco 4154
xii. Tender has been finalised for equipping 6,300 Electric Locomotives with Kavach version 4.0
and another tender for equipping 2,679 Diesel Locomotives is under finalisation.
xiii. Specialized training programmes on Kavach are being conducted at centralized training
institutes of Indian Railways to impart training to all concerned officials. By now more than
48,000 technicians, operators and engineers have been trained on Kavach technology. This
includes about 45,000 Loco Pilots & Assistant Loco Pilots. Courses have been designed in
collaboration with IRISET.
xiv. The cost for provision of Track Side including Station equipment of Kavach is approximately
Rs. 50 Lakhs/Km and cost for provision of Kavach equipment on locomotives is approximately
Rs. 80 Lakh/Loco.
xv. The funds utilized on Kavach works so far up to Dec'25 is Rs. 2,573.36 Crores. The allocation
of funds during the year 2025-26 is Rs. 1673.19 Crores. Requisite funds are made available as
per the progress of works.
*****