GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 2984
TO BE ANSWERED ON 05.08.2026
RAILWAY CONNECTIVITY IN TRIBAL/ASPIRATIONAL DISTRICTS OF
MAHARASHTRA
2984. SHRI BHASKAR MURLIDHAR BHAGARE:
Will the Minister of RAILWAYS be pleased to state:
(a) whether the Government has undertaken any assessment of railway
connectivity in the tribal and aspirational districts of Maharashtra and if
so, the details thereof;
(b) the names of tribal and remote districts identified as lacking adequate
railway connectivity and the criteria adopted for such assessment;
(c) whether any new railway lines, doubling, electrification, gauge
conversion or station development projects have been sanctioned or are
under consideration for these districts and if so, the details thereof;
(d) the present status of railway proposals received from Maharashtra for
improving connectivity in tribal and backward regions;
(e) the status of ongoing railway projects in tribal areas of Maharashtra,
including physical and financial progress, district-wise; and
(f) the details of the timeline fixed for completion of these projects and the
measures taken to address delays in land acquisition, funding and
execution?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (f):
Budget allocation in recent years has increased significantly. Budget
allocation for infrastructure projects and safety works, falling fully/partly in
the State of Maharashtra including tribal and aspirational districts, is as
under:
§ Page 1 of 22Period Outlay
2009-14 ₹1,171 crore/year
2026-27 ₹23,926 crore (More than 20 times)
Track Construction:
The details of constructing new track falling fully/partly in the State of
Maharashtra including tribal and aspirational districts during 2009-14 and
2014-26 are as under:
Period New track
Average commissioning of new tracks
Commissioned
2009-14 292 Km 58.4 Km/year
2014-26 2,585 Km 215.4 Km/year (Nearly 4 times)
Projects sanctioned:
As on 01.04.2026, 52 projects (13 New Lines, 02 Gauge Conversion and 37
Doubling), of a total length of 5,956 km, costing ₹1,42,635 crore, falling
fully/partly in Maharashtra including tribal and aspirational districts, are
sanctioned. The summary is as under:-
Category No. of Total Length Exp.
sanctioned Length Commissioned upto Mar'26
Projects (in Km) Upto Mar'26 (₹ in Cr.)
(in Km)
New Line 13 1,399 266 13,065
Gauge Conversion 02 609 334 5,013
Doubling/ 37 3,948 998 16,704
Multitracking
Total 52 5,956 1,598 34,782
Page 2 of 22Recently completed projects:
Details of some of the recently completed projects falling fully/partly in
Maharashtra including tribal and aspirational districts, are as under:
S.No. Project Cost
(₹ in crore)
1 Pune - Miraj - Londa Doubling (467 Km) 6,463
2 Hotgi - Kudgi - Gadag Doubling (284 Km) 2,459
3 Manmad - Jalgaon 3rd Line (160 Km) 1,677
4 Jabalpur - Gondia Gauge Conversion (300 Km) 2,005
5 Chhindwara - Nagpur Gauge Conversion (150 Km) 1,512
6 Panvel - Pen Doubling (35 Km) 263
7 Pen - Roha Doubling (40 Km) 330
8 Udhna - Jalgaon Doubling (307 Km) 2,448
9 Mudkhed - Parbhani Doubling (81 Km) 673
10 Bhusawal - Jalgaon 3rd Line (24 Km) 325
11 Jalgaon - Bhusawal 4th Line (24 Km) 261
12 Daund - Gulbarga Doubling (225 Km) 3,182
13 Daund - Manmad Doubling (236 Km) 3,426
Ongoing Projects:
To further improve the Railway Infrastructure in the state of Maharashtra
including tribal and aspirational districts, following works have been taken
up:-
S.No. Name of the project Cost
(₹ In crore)
1 Ahilyanagar - Parli Vaijnath New Line (261 Km) 5,800
2 Baramati - Lonand New Line (64 Km) 1,844
3 Wardha - Nanded New Line (284 Km) 5,248
Page 3 of 224 Indore - Manmad New Line (360 Km) 18,529
5 Wadsa - Gadchiroli New Line (52 Km) 1,886
6 Jalna - Jalgaon New Line (174 Km) 5,804
7 Wardha - Nagpur 3rd Line (76 Km) 917
8 Wardha - Ballarshah 3rd Line (132 Km) 1,755
9 Itarsi - Nagpur 3rd Line (280 Km) 2,607
10 Rajnandgaon - Nagpur 3rd Line (228 Km) 3,545
11 Wardha - Nagpur 4th Line (79 Km) 1,215
12 Jalgaon - Manmad 4th Line (160 Km) 2,574
13 Bhusawal - Khandwa 3rd & 4th Line (131 Km) 3,285
14 Solapur – Tuljapur - Osmanabad New Line (84 Km) 3,296
15 Panvel - Chowk Double Line (17 Km) 491
16 Wardha - Balharshah 4th Line (135 Km) 2,226
17 Itarsi - Nagpur 4th Line (297 Km) 5,010
18 Wardha - Bhusawal 3rd & 4th Line (314 Km) 9,197
19 Gondia - Dongargarh 4th Line (84 Km) 2,223
20 Gondia - Balharshah Doubling (240 Km) 4,819
21 Kalyan - Kasara 3rd Line (68 Km) 1,433
22 Naigaon - Juichendra Double Chord Line (5 Km) 176
23 Nilje - Kopar Double Chord Line (5 Km) 338
24 Badlapur - Karjat 3rd & 4th Line (32 Km) 1,324
25 Asangaon - Kasara 4th Line (35 Km) 794
26 Kasara - Manmad 3rd & 4th Line (131 Km) 10,154
27 Gondia - Jabalpur Doubling (231 Km) 5,236
28 Chalisgaon Rail Over Rail Flyover (11 Km) 264
29 Chord line between Chikhli and Somtane (4 Km) 172
30 Puntamba - Sainagar Shirdi Doubling (17 Km) 227
Page 4 of 22Further, during the last three years i.e. 2023-24, 2024-25, 2025-26 and the
current financial year 2026-27, 60 surveys (21 New Line and 39 Doubling) of
total length 6,872 Km falling fully/ partly in the State of Maharashtra
including tribal and aspirational districts, have been sanctioned. Some of
the important surveys are as follows:-
S.No. Name of the Survey Status
1. Jalna - Khamgaon New Line (162 Detailed Project Report (DPR)
Km) has been prepared.
2. Nashik - Dahanu Road New Line DPR has been prepared.
(100 Km)
3. Pune - Ahilyanagar New Line (134 DPR has been prepared.
Km)
4. Pune - Wadi 3rd & 4th Line (393 DPR has been prepared.
Km)
5. Nashik - Dahanu Road New Line Final Location Survey (FLS)
(100 Km) has been sanctioned for the
preparation of DPR.
6. Karzat - Lonawala - Pune 3rd & 4th FLS has been sanctioned for
Line (91 Km) the preparation of DPR.
After preparation of Detailed Project Report (DPR), sanctioning of project
requires consultation with various stake-holders including State
Governments and necessary approvals viz. appraisal of NITI Aayog,
Ministry of Finance etc. As sanctioning of projects is a continuous and
dynamic process, exact timelines depend upon appraisals and approvals by
various stakeholders.
Sanction of any railway project depends upon many parameters/factors
which include the following:
Page 5 of 22 Anticipated traffic projections and Remunerativeness of the proposed
route
First and last mile connectivity provided by the project
Connection of missing links and providing additional route
Augmentation of congested/saturated lines
Demands raised by State Governments/Central Ministries/Public
representatives,
Railway’s own operational requirements
Socio-economic considerations
Overall availability of funds
Completion of Railway project/s depends on various factors which include
the following:
Land acquisition by State Government
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
Various steps taken by the Government for effective and speedy
implementation of rail projects include:
Substantial increase in allocation of funds.
Delegation of powers at field level.
Close monitoring of progress of project at various levels.
Page 6 of 22 Regular follow up with State Governments and concerned authorities
for expeditious land acquisition, forestry and Wildlife clearances and
for resolving other issues pertaining to projects.
Benefits of Railway projects in the respective regions include:
Faster movement of the essential goods and agriculture products
Increase in employment opportunities for the people of this region
Socio-economic development of the area, development of tourism
industry
Increase in industrial activities in the region.
Capacity Augmentation works for Mumbai Suburban area
Presently, about 120 Mail/Express trains and 3200 sub urban trains are
handled daily in Mumbai area.
To increase train handling capacity at various stations in Mumbai area,
following works have been completed/taken up/planned at various stations:
S.No. Location Details
1 Bandra Terminus 3 Pit Lines have been completed
2 Mumbai Central Platform extension for 24 LHB coaches
3 Jogeshwari 5 additional Platforms, 2 pit lines
4 Dadar 1 additional platform
5 Panvel - Kalamboli 5 platforms, 4 pit lines and 2 sick lines
6 Kalyan 6 platforms and 4 pit lines
7 LTT 4 platforms and 2 pit lines
8 Parel 6 platforms, 5 pit lines, 6 stabling lines
9 Vasai - Virar Area Vasai road: 6 Platforms, 3 pit lines and 5
stabling lines
Naigaon - 30 stabling Lines
Virar - 2 stabling Lines
10 Dahanu Area Dahanu: 5 stabling Lines
New Vangaon: 30 stabling Lines
Page 7 of 22In addition to above, Platform extension work at 34 stations to
accommodate 15 car EMUs have been taken up.
New projects for increasing capacity:
To improve the connectivity and capacity of rail network in Mumbai
suburban areas, Mumbai Urban Transport Project (MUTP)-I costing ₹4,502
Cr., MUTP-II costing ₹8,087 Cr., MUTP-III costing ₹10,947 Cr. & MUTP-IIIA
costing ₹33,690 Cr have been sanctioned. The progress of works is as
below:
Cost
Name of the
SN (₹ in Status of work
project
crore)
1 Virar - Dahanu 3,578 Entire 39 Ha. Land acquired.
Road 3rd & 4th line
Entire 3 lac cum. earthwork
(64 km)
completed.
13 out of 16 major bridges completed.
53 out of 68 minor bridges completed.
All 4 RUBs completed.
60 out of 181 Station/Service
buildings completed.
31 km out of 128 km track laying
completed.
2 Borivali - Virar 5th 2,184 16 Ha. out of 17 Ha. landacquired.
& 6th line (26 km)
Forest clearance obtained from
MoEFCC.
Permission for Mangroves felling
obtained from Hon’ble High Court.
3.3 lac cum. earthwork out of 6.7 lac
cum. completed.
5 out of 23 FOB Extn. completed.
Page 8 of 22 2 out of 12 minor Bridges completed.
Work in progress in 3 major bridges.
Work in progress in Station buildings
and other items.
3 Naigaon - 176 Land acquisition has been taken up.
Juichandra
double chord line
(6 km)
4 Extension of 826 Land acquisition has been taken up.
Harbour line from
Goregaon -
Borivali (7 km)
5 Mumbai Central - 919 Phase-I (Borivali - Khar Road, 17 km):
Borivali 6th line Commissioned.
(30 km) Phase-II (Khar Road - Mumbai
Central): Land acquisition has been
taken up.
6 4th line Asangaon- 794 Design & drawings have been taken
Kasara (34.97 up.
km)
7 Kalyan - 1,759 8 out of 92 minor bridges completed.
Asangaon 4th line Land Acquisition of 17 Ha out of 28
(32 km) Ha completed.
Work in progress in 7 major bridges.
8 Kalyan - Kasara 1,433 Land acquisition of 48 Ha. out of 54
3rd Line (68 km) Ha. completed.
4 out of 9 major bridges completed.
All 5 Station buildings completed.
23 km out of 68 km track laying
completed.
9 Kalyan - Badlapur 1,510 1 out of 2 major bridges completed.
3rd & 4th line (14 2 out of 4 ROBs completed.
km) 30 out of 40 minor bridges completed.
10 3rd and 4th line 1,324 Design & drawings have been taken
Badlapur - Karjat up.
(32.46 km)
11 Panvel - Karjat 2,782 All 3 tunnels (3 km) completed.
Suburban 5 ROBs, 16 RUBs completed.
Corridor(29.6 km) 9 major bridges, 35 minor bridges
Page 9 of 22completed.
67 km out of 70 km track laying
completed.
12 Airoli - Kalwa 476 Phase-I (Halt station at Digha):
(elevated) Commissioned.
Suburban Phase-II (Airoli - Kalwa elevated
Corridor link (3.3 track, 3.3 km): Land acquisition and
km) R&R has been taken up.
13 Nilje - Kopar 338 Land acquisition has been taken up.
double chord line 6 out of 15 minor bridges completed.
(5 km)
0.85 lac cum. earthwork out of 1 lac
cum. completed
14 CSMT - Kurla 5th 891 Phase-I (Kurla - Parel, 10.1 km):
& 6th line 1 out of 12 minor bridges completed.
(17.5 km) 2 out of 4 station buildings
completed.
Rebuilding of Sion ROB is in progress.
Phase-II (Parel - CSMT, 7.4 km):
Land acquisition has been taken up.
New generation trains:
To enhance passenger carrying capacity, 238 rakes of 12 cars each with
doors have been sanctioned under MUTP-III & IIIA at a cost of ₹19,293
crore. The process for procurement of these rakes has been taken up.
Bullet Train project:
Presently, the Mumbai-Ahmedabad High Speed Rail (MAHSR) Project (508
km) is under execution. The Project is passing through the States of
Gujarat, Maharashtra and Union Territory of Dadra & Nagar Haveli with 12
stations planned at Mumbai, Thane, Virar, Boisar, Vapi, Billimora, Surat,
Bharuch, Vadodara, Anand, Ahmedabad and Sabarmati.
Entire land (1389.5 Ha.) for the MAHSR project has been acquired. All
Statutory Clearances have been obtained. All 1651 utilities have been
Page 10 of 22shifted. The delay in land acquisition in the State of Maharashtra has
impacted the project till 2021. The land acquisition picked up in 2022 in
Maharashtra.
The progress of various major items so far is as under:
Item Progress
Piers 452 kms.
Girder 356 kms.
Track Bed 209 kms.
OHE Masts 190 kms.
The progress of stations is given below:-
S. No. Station Status
Foundation works completed, Platform slab &
1 Sabarmati roof structural works and finishing works are in
progress
2 Ahmedabad Structural works completed and finishing works
3 Anand/Nadiad have been taken up.
Foundation work completed, structural works and
4 Vadodara
finishing works have been taken up.
5 Bharuch
6 Surat Structural works completed and finishing works
7 Bilimora have been taken up.
8 Vapi
9 Boisar Foundation works have been taken up and in an
10 Virar advanced stage. Structural works have been
11 Thane taken up.
12 BKC (Mumbai) This is an underground station. Foundation works
Page 11 of 22almost completed and Base Slab has been taken
up.
The progress on the River Bridges is as under:-
S. No. River Name Status
Sabarmati River Sub-Structure work completed,
1
(480m) Superstructure work has been taken up.
2 Meshwa River (120m)
3 Vatrak River (280m)
Bridge construction completed.
Mohar (Shedhi) River
4
(160m)
11 out of 12 wells completed; 5 spans
5 Mahi River (720m)
launched
Vishwamitri River
6
(80m) Bridge construction completed.
7 Dhadhar River (120m)
Narmada River 21 out of 25 wells completed; 4 spans
8
(1366m) launched
9 Kim River (120m) Bridge construction completed.
Foundation work has been taken up, 10
10 Tapi River (720m)
out of 12 wells completed
Mindhola River
11
(240m)
12 Purna River (360m)
13 Ambika River (200m)
Bridge construction completed.
Venganiya River
14
(200m)
15 Kaveri River (120m)
16 Kharera River (120m)
Page 12 of 2217 Auranga River (320m)
18 Par River (320m)
19 Kolak River (160m)
Daman Ganga River
20
(360m)
21 Darotha River (80m)
22 Jagani River (360m) Foundation works have been completed
Vaitarna River 12 Pile Cap and 11 Pier (out of 58)
23
(2320m) completed.
Ulhas River Branch Temporary Access Bridge (TAB)
24
(120m) completed to start the foundation work.
Geo-technical Investigation (GTI) has
Desai Khadi River
25 been completed and Design work has
Bridge (400m)
been taken up.
The work of the under-sea tunnel (approximately 21 km) has commenced,
out of which 4.8 km of tunnel between Ghansoli and Shilphata in
Maharashtra has been completed.
On the Surat - Vapi section (97 km) entire civil works including river bridge
construction, have been completed and 87% of the track bed has been
laid.
However, Bullet train project is a very complex and technology intensive
project. Exact timelines for the completion of the entire project can be
reasonably ascertained after the completion of all associated works of
Civil Structures, Track, Electrical, Signaling & Telecommunication and
supply of Trainsets.
Further, to strengthen national transport infrastructure, provide a fillip to
regional connectivity, economic growth, tourism, investment and
Page 13 of 22employment generation, and encourage modal shift from road and air
transport to rail, the Government has announced the development of the
following seven new High-Speed Rail (HSR) corridors in the Union Budget
2026-27:-
(i) Mumbai - Pune
(ii) Pune - Hyderabad
(iii) Hyderabad–Bengaluru
(iv) Hyderabad - Chennai
(v) Chennai - Bengaluru
(vi) Delhi - Varanasi
(vii) Varanasi - Siliguri
Being highly capital intensive, the decision to sanction any HSR
Corridor/Project depends on many factors such as outcome of DPR, techno-
economic feasibility studies and availability of resources such as financing
options etc.
Dedicated freight corridor:
Ministry of Railways has taken construction of two Dedicated Freight
Corridors (DFC) viz. Eastern Dedicated Freight Corridor (EDFC) from
Ludhiana to Sonnagar (1337 Km) and the Western Dedicated Freight
Corridor (WDFC) from Jawaharlal Nehru Port Terminal (JNPT) to Dadri
(1506 Km).
The work on EDFC & WDFC has been completed and commissioned.On an
average more than 443 trains are operated per day on DFCs. The fully
commissioned sections of the Eastern and Western Dedicated Freight
Corridors (EDFC & WDFC) have demonstrated robust operational
performance. Freight volumes have steadily increased, with higher average
speeds, faster turnarounds, and enhanced reliability. The corridors are
witnessing consistent growth in container, coal, and bulk cargo movement,
Page 14 of 22contributing significantly to capacity augmentation in freight
transportation.
DFC has contributed to creating additional paths on the conventional
network by diverting freight traffic to EDFC and WDFC. As a result,
Railways have been able to run additional goods and coaching services
over its network. The DFCs have enabled faster transit times, higher
throughput, and double-stack container operations (especially on the
Western DFC). These improvements have contributed to lowering overall
logistics costs, improving supply chain efficiency, and enhancing
competitiveness of Indian industries.
A new Dedicated Freight Corridor connecting Dankuni in East to Surat in
West, has been announced in the Union Budget 2026. The work of
preparation/ updation of Detailed Project Report (DPR) for this corridor has
been taken up.
Railway Electrification
Electrification of railway network on Indian Railways has been taken up in
mission mode. So far, about 99.6% of Broad Gauge (BG) network has been
electrified. The electrification in remaining network has been taken up.
Electrification carried out during 2014-26 and before 2014 is as under:-
Period Route Kilometer
Before 2014 (about 60 years) 21,801
2014-26 48,072
In Maharashtra, entire existing BG network has been electrified. Further,
all new line/ Multitracking projects are being sanctioned and constructed
with electrification.
Page 15 of 22Station Redevelopment
Ministry of Railways has launched Amrit Bharat Station Scheme for
redevelopment of stations with a long-term approach.
The scheme involves preparation of master plans and their implementation
in phases to improve the stations of Indian Railways. The master planning,
keeping in view the necessity of each station, includes:
Improvement of access to station and circulating areas
Integration of station with both sides of city
Improvement of station building
Improvement of waiting halls, toilets, sitting arrangement, water
booths
Provision of wider foot over bridge/subway to commensurate with
passenger traffic
Provision of lifts/escalators/ramps
Improvement of platform surface/ provision of platform shelter
Provision of kiosks for local products through schemes like ‘One
Station One Product’
Parking development
Amenities for Divyangjans
Better passenger information systems
Provision of air concourse, executive lounges, Multimodal integration,
landscaping, etc.
The scheme also envisages sustainable and environment friendly solutions
etc. as per necessity, phasing and feasibility and creation of city centre at
the station in the long term.
Page 16 of 22So far, 1,340 stations have been identified for development under this
scheme, out of which 132 stations, including 4 stations of Aspirational
districts, are located in Maharashtra.
The names of stations identified for development under Amrit Bharat
Station Scheme from Aspirational districts of Maharashtra are as following:
State Aspirational District Name of Station
Gadchiroli Wadsa
Nandurbar Nandurbar
Maharashtra
Osmanabad Dharashiv
Washim Washim
The names of stations identified for development under Amrit Bharat
Station Scheme in Maharashtra are as following:
State No. of Names of Stations
Stations
Maharashtra 132 Ahmednagar, Ajni (Nagpur), Akalkot Road,
Akola, Akurdi, Amalner, Amgaon, Amravati,
Andheri, Badnera, Balharshah, Bandra
Terminus, Baramati, Belapur, Bhandara Road,
Bhokar, Bhusawal, Borivali, Byculla,
Chalisgaon, Chanda Fort, Chandrapur, Charni
Road, Chhatrapati Sambhaji nagar,
Chhatrapati Shivaji Maharaj Terminus,
Chinchpokli, Chinchwad, Dadar (CR), Dadar
(WR), Dahisar, Daund, Dehu Road, Devlali,
Dhamangaon, Dharangaon, Dharashiv,
Dharmabad, Dhule, Diva, Dudhani,
Gangakher, Godhani, Gondia, Grant Road,
Page 17 of 22State No. of Names of Stations
Stations
Hadapsar, Hatkanangale, Hazur Sahib
Nanded, Himayatnagar, Hinganghat, Hingoli
Deccan, Igatpuri, Jalgaon, Jalna, Jeur,
Jogeshwari, Kalyan Jn, Kamptee, Kandivali,
KanjurMarg, Karad, Katol, Kedgaon, Kinwat,
Kopargaon, Kurduwadi Jn, Kurla Jn,
Lasalgaon, Latur, Lokmanya Tilak Terminus,
Lonand Jn, Lonavla, Lower Parel, Malad,
Malkapur, Manmad Jn, Manwath Road,
Marine Lines, Matunga, Miraj Jn, Mudkhed
Jn, Mumbai Central, Mumbra, Murtizapur Jn,
Nagarsol, Nagpur Jn, Nandgaon, Nandura,
Nandurbar, Narkher Jn, Nashik Road, Netaji
Subhash Chandra Bose Itwari Junction,
Pachora Jn, Palghar, Pandharpur, Panvel Jn,
Parbhani Jn, Parel, Parli Vaijnath, Partur,
Phaltan, Prabhadevi, Pulgaon Jn, Pune Jn,
Purna Jn, Raver, Rotegaon, SainagarShirdi,
Sandhurst Road, Sangli, Satara, Savda, Selu,
Sewagram, Shahad, Shegaon, Shivaji Nagar
Pune, Shri Chhatrapati Shahu Maharaj
Terminus Kolhapur, Solapur, Talegaon,
Thakurli, Thane, Titvala, Tumsar Road, Umri,
Uruli, Vadala Road, Vidyavihar, Vikhroli,
Wadsa, Wardha, Washim, Wathar
Page 18 of 22Completed stations in Maharashtra:
Development works at railway stations under Amrit Bharat Station Scheme
in Maharashtra have been taken up at a good pace. Details of stations
completed in Maharashtra are as under:
State No. of Names of Stations
Stations
Maharashtra 20 Amgaon, Baramati, Byculla, Chanda Fort,
Chinchpokli, Devlali, Dhule, Himayatnagar,
Kedgaon, Lasalgaon, Lonand Junction,
Malkapur, Matunga, Murtizapur Junction,
Nandura, Netaji Subhash Chandra Bose Itwari
Junction, Parel, Savda, Shahad, Vadala Road
The activities for development at other stations have also been taken up at
good pace and progress of some of the stations is as given below:
Stations of Aspirational districts in Maharashtra:
Wadsa station: The works of improvement of station building, waiting
hall, booking counter, toilet, improvement of platform surface,
improvement of circulating area, approach road, landscaping, 12 m wide
foot over bridge, entry/ exit gates, art work, installation of Train
Indication Board and Coach Indication Board, signages and high mast
light have been completed. The work of lifts has been taken up.
Nandurbar station: The works of new station building, improvement of
existing station building, improvement of platform surface, new platform
shelter, new toilet block, improvement of existing toilet, new entry/exit
gate, improvement of circulating area and parking have been taken up.
Page 19 of 22 Dharashiv station: The works of improvement of station building,
improvement of circulating area, parking, improvement of platform
surface and platform shelter have been completed. The works of 6 m
wide foot over bridge and toilet block have been taken up.
Washim station: The works of improvement of station building at main
entry, platform shelter, improvement of platform surface, waiting hall,
toilet, improvement of circulating area at main entry, 12 m wide foot
over bridge and lift have been taken up.
Other stations of Maharashtra:
Nagpur Junction station: The works of relocation of passenger
reservation system building and booking offices, and improvement of
parking on the main entry side have been completed. The works of
construction of new admin building, departure building and basement
parking on main entry side, construction of departure building and
unified basement on second entry side, new air concourse, improvement
to platform surfacing on platform 8, and new platform shelters have
been taken up.
Chhatrapati Sambhajinagar station: The works of new post office
building and parcel office, new Railway Protection Force and
Government Railway Police building at North side have been completed.
The works of new arrival and departure building at South side, new
waiting hall, toilet, air concourse, 6 m wide foot over bridge, through
roof, new underground tanks at North and South sides, new sewage
treatment plant at North and South side and new electrical sub-station
building have been taken up.
Page 20 of 22 Solapur station: The works of new ramp for existing foot over bridge,
new toilet block, new booking office at second entry, improvement of
station building, toilet, improvement of circulating area, parking at main
and second entry, and boundary wall have been completed. The work of
6 m wide foot over bridge has been taken up.
Tumsar Road station: The works of improvement of station building,
waiting hall, toilet, entrance porch, improvement of circulating area,
approach road, landscaping, improvement of platform surface,
installation of Train Indication Board and Coach Indication Board,
signages and CCTV have been completed. The work of lifts has been
taken up.
Gondia station: The works of improvement of station building, waiting
hall, booking counter, toilet, improvement of circulating area, approach
road, installation of Train Indication Board and Coach Indication Board,
signages and CCTV have been completed. The works of 12 m wide foot
over bridge and lifts have been taken up.
Further, development / redevelopment / upgradation / modernisation of
stations on Indian Railways is a continuous and ongoing process and works
in this regard are undertaken as per requirement, subject to inter-se
priority and availability of funds. Development / redevelopment /
upgradation / modernisation of a station is carried out based on category
of station/condition/traffic handled etc.
Development / Upgradation of railway stations is a complex in nature
involving safety of passengers & trains and requires various statutory
clearances such as tree cutting, heritage, fire clearance, airport clearance
etc. These stations are in operation since long, so brownfield work
challenges are being faced, such as shifting of utilities (involving
Page 21 of 22water/sewage lines, optical fibre cables, gas pipelines, power/signal
cables, etc.), infringements, operation of trains without hindering
passenger movement, speed restrictions due to works carried out in close
proximity of the tracks and near to high voltage power lines, etc. and these
factors affect the progress of work and completion time.
Development / upgradation / modernisation of stations including under
Amrit Bharat Station Scheme is generally funded under Plan Head-53
‘Customer Amenities’. The details of allocation and expenditure under Plan
Head-53 are maintained Zonal Railway - wise and not station-wise or state-
wise. Maharashtra is covered under the jurisdiction of four railway zones,
namely, Central Railway, Southern Central Railway, South East Central
Railway and Western Railway. For these zones, an allocation of ₹3,543
crore has been made for the financial year 2026-27, out of which an
expenditure (up to June, 2026) of ₹1,671 crore has been incurred so far.
*****