GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 2055
TO BE ANSWERED ON 11.02.2026
RAILWAY GRIEVANCES IN HINGOLI LOK SABHA CONSTITUENCY
2055. SHRI AASHTIKAR PATIL NAGESH BAPURAO:
Will the Minister of RAILWAYS be pleased to state:
(a) whether the Government is aware of the acute hardship faced by
passengers in the Hingoli Lok Sabha Constituency, Maharashtra due to
frequent cancellations, short-terminations, irregular running of trains,
the recent reduction in coach capacity/removal of general coaches, non-
availability of reserved tickets, long waiting list and extreme
overcrowding;
(b) if so, the details thereof specifically the impact on daily commuters,
students, women and elderly passengers, farmers, patients, etc., the
reasons for such disruptions and non- augmentation of coaches despite
rising demand;
(c) whether it is a fact that several railway stations in the Hingoli district
currently face serious deficiencies in basic passenger amenities and
safety infrastructure, including non-functional toilets, lack of drinking
water, inadequate lighting, the absence of foot overbridges and unsafe
platforms;
(d) if so, the details thereof and the reasons for the delay in the
upgradation/redevelopment of these stations despite repeated public
representations;
(e) whether the Government has received requests for providing stoppages
for important long- distance trains at Hingoli Road, adjoining stations and
if so, the action taken thereon to prevent passengers from resorting to
costly and unsafe road travel; and
(f) the details of immediate corrective measures and budgetary provisions
proposed to be taken by the Government in the current financial year to
restore punctual train services, improve station infrastructure and
ensure the safety of passengers in this backward and tribal-dominated
constituency?
§ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (f) Indian Railways in its endeavour to provide safer and better travel
experience to the passengers, undertakes infrastructural and maintenance-
related works. To facilitate these works, partial cancellation, cancellation
and diversion of some trains are necessitated. Accordingly, during 2025–26,
a few trips of trains passing through Hingoli Deccan station were cancelled
and trains were diverted. However, these are restored back once the works
are complete.
Hingoli Deccan is served by 38 train services providing connectivity to cities
like Nagpur, Pune, Mumbai, Jaipur, Hazur Sahib Nanded, Tirupati,
Kacheguda, Dr. Ambedkar Nagar (Mhow).
S.N. Train No. & Name
1 11403/04 Nagpur - SCSM (T) Kolhapur Express
2 11405/06 Pune - Amravati Express
3 12071/72 Mumbai CSMT - Hingoli Deccan Jan Shatabdi Express
4 12421/22 Hazur Sahib Nanded - Amritsar Express
5 12439/40 Hazur Sahib Nanded - Shri Ganganagar Express
6 12485/86 Hazur Sahib Nanded - Shri Ganganagar Express
7 12719/20 Jaipur - Hyderabad Express
8 12751/52 Hazur Sahib Nanded - Jammu Tawi Humsafar Express
9 12765/66 Tirupati - Amravati Express
10 17605/06 Kacheguda - Bhagat Ki Kothi Express
11 17639/40 Kacheguda - Akola Express
12 17641/42 Kacheguda - Narkher Express
13 17683/84 Akola -Purna Express
14 19301/02 Dr. Ambedkar Nagar (Mhow) - Yesvantpur Express
15 19713/14 Jaipur - Kurnool City Express
16 22709/10 Hazur Sahib Nanded - Amb Andaura Express
17 22723/24 Hazur Sahib Nanded - Shri Ganganagar Express
18 57655 Parli Vaijnath–Akola Passenger19 57656 Akola-Purna Passenger
20 77613 Purna–Akola DEMU
21 77614 Akola-Parli Vaijnath DEMU
Besides, provision of stoppage of train services, depends on the traffic
justification, operational feasibility including availability of extra time on the
section & availability of matching infrastructure such as Platform length etc.
Amrit Bharat Station Scheme
Further, to provide better amenities at stations, Ministry of Railways has
launched Amrit Bharat Station Scheme for redevelopment of stations with a
long-term approach. The scheme involves preparation of master plans and
their implementation in phases to improve the stations. The master planning
includes:
● Improvement of access to station and circulating areas
● Integration of station with both sides of city
● Improvement of station building
● Improvement of waiting halls, toilets, sitting arrangement, water
booths
● Provision of wider foot over bridge/air concourse commensurate with
passenger traffic
● Provision of lift/escalators/ramp
● Improvement/Provision of platform surface and cover over platforms
● Provision of kiosks for local products through schemes like ‘One
Station One Product’
● Parking areas, Multimodal integration
● Amenities for Divyangjans
● Better passenger information systems
● Provision of executive lounges, nominated spaces for business
meetings, landscaping, etc. keeping in view the necessity at each
stationThe scheme also envisages sustainable and environment friendly solutions,
provision of ballastless tracks etc. as per necessity, phasing and feasibility
and creation of city centre at the station in the long term.
So far, 1337 stations have been identified for development under this
scheme, out of which 132 stations including Himayatnagar, Hingoli Deccan
and Kinwat stations of Hingoli Lok Sabha Constituency, are located in
Maharashtra. The names of stations identified for development under Amrit
Bharat Station Scheme in Maharashtra are as following:
State No. of Name of Stations
Statio
ns
Maharashtra 132 Ahmednagar, Ajni (Nagpur), Akalkot Road, Akola,
Akurdi, Amalner, Amgaon, Amravati, Andheri,
Badnera, Balharshah, Bandra Terminus, Baramati,
Belapur, Bhandara Road, Bhokar, Bhusawal, Borivali,
Byculla, Chalisgaon, Chanda Fort, Chandrapur,
Charni Road, Chhatrapati Sambhajinagar,
Chhatrapati Shivaji Maharaj Terminus, Chinchpokli,
Chinchwad, Dadar (CR), Dadar (WR), Dahisar, Daund,
Dehu Road, Devlali, Dhamangaon, Dharangaon,
Dharashiv, Dharmabad, Dhule, Diva, Dudhani,
Gangakher, Godhani, Gondia, Grant Road, Hadapsar,
Hatkanangale, Hazur Sahib Nanded, Himayatnagar,
Hinganghat, Hingoli Deccan, Igatpuri, Jalgaon, Jalna,
Jeur, Jogeshwari, Kalyan Jn, Kamptee, Kandivali,
Kanjur Marg, Karad, Katol, Kedgaon, Kinwat,
Kopargaon, Kurduwadi Jn, Kurla Jn, Lasalgaon,
Latur, Lokmanya Tilak Terminus, Lonand Jn, Lonavla,Lower Parel, Malad, Malkapur, Manmad Jn, Manwath
Road, Marine Lines, Matunga, Miraj Jn, Mudkhed Jn,
Mumbai Central, Mumbra, Murtizapur Jn, Nagarsol,
Nagpur Jn, Nandgaon, Nandura, Nandurbar, Narkher
Jn, Nashik Road, Netaji Subhash Chandra Bose
Itwari Junction, Pachora Jn, Palghar, Pandharpur,
Panvel Jn, Parbhani Jn, Parel, Parli Vaijnath, Partur,
Phaltan, Prabhadevi, Pulgaon Jn, Pune Jn, Purna Jn,
Raver, Rotegaon, Sainagar Shirdi, Sandhurst Road,
Sangli, Satara, Savda, Selu, Sewagram, Shahad,
Shegaon, Shivaji Nagar Pune, Shri Chhatrapati Shahu
Maharaj Terminus Kolhapur, Solapur, Talegaon,
Thakurli, Thane, Titvala, Tumsar Road, Umri, Uruli,
Vadala Road, Vidyavihar, Vikhroli, Wadsa, Wardha,
Washim, Wathar
Development works at railway stations under Amrit Bharat Station Scheme in
Maharashtra have been taken up at a good pace. Till now, works of 17
stations (Amgaon, Baramati, Chanda Fort, Chinchpokli, Devlali, Dhule,
Kedgaon, Lasalgaon, Lonand Jn, Matunga, Murtizapur Jn, Nandura, Netaji
Subhash Chandra Bose Itwari Junction, Parel, Savda, Shahad, Vadala Road)
in Maharashtra have been completed under this scheme. The works at other
stations have also been taken up at good pace and progress of some of above
stations is as given below:
● Himayatnagar station: The works of improvement of station building,
porch, platform shelter, improvement of platform surface, waiting hall,
toilet, circulating area and lift have been taken up.
● Hingoli Deccan station: The works of platform shelter and improvement
of platform surface of platform no. 2 have been completed. The worksof new station building, improvement of existing station building,
platform surface of platform no. 1, circulating area, lift and 12 m Foot
Over Bridge have been taken up.
● Kinwat station: The works of improvement of station building, porch,
platform shelter, improvement of platform surface, waiting hall, toilet,
circulating area, lift and 12 m Foot Over Bridge have been taken up.
● Washim station: The works of improvement of station building, porch,
improvement of platforms, platform shelter, improvement of waiting
hall, toilet, circulating area, lift and 12 m Foot Over Bridge have been
taken up.
● Manwath Road station: The work of platform shelter has been
completed. The works of improvement to station building, entrance
porch, platform surfacing, waiting hall, toilet and lift have been taken
up.
Further, development / redevelopment / upgradation / modernisation of
stations on Indian Railways including provision for toilet, drinking water,
lighting, Foot Over Bridge, platforms etc. is a continuous and ongoing process
and works in this regard are undertaken as per requirement, subject to inter-
se priority and availability of funds. Development / redevelopment /
upgradation / modernisation of a station is carried out based on category of
station/condition/traffic handled etc.
Development / Upgradation of railway stations is complex in nature involving
safety of passengers & trains and requires various statutory clearances such
as fire clearance, heritage, tree cutting, airport clearance etc. The progress
also gets affected due to brownfield related challenges such as shifting of
utilities (involving water/sewage lines, optical fibre cables, gas pipe lines,
power/signal cables, etc.), infringements, operation of trains without
hindering passenger movement, speed restrictions due to works carried outin close proximity of tracks and high voltage power lines, etc. and these
factors affect the completion time.
Suggestions / Representations, both formal and informal for Railway projects
/ Works across the country are received on the basis of demands raised by
State Governments, Members of Parliament, Ministries of Central
Government, elected representatives, Railways' own requirements,
organizations / rail users etc., at various levels including Railway Board,
Zonal Railways, Division Office etc. Receipt of such suggestions /
representations is a continuous and dynamic process and these are
examined and action as found feasible and justified is taken from time to
time.
Development / Upgradation / Modernization of stations including Amrit
Bharat Station Scheme is generally funded under Plan Head-53 ‘Customer
Amenities’. The details of allocation and expenditure under Plan Head-53 are
maintained Zonal Railway-wise and not work-wise or station-wise or state-
wise. Maharashtra is covered under the jurisdiction of four railway zones,
namely, Central Railway, South Central Railway, South East Central Railway
and Western Railway. For these zones, an allocation of ₹ 3,834 crore has
been made for the financial year 2025-26, out of which an expenditure (up to
December, 2025) of ₹ 3,122 crore has been incurred so far.
Safety:
Safety is accorded the highest priority on Indian Railways. As a consequence
of various safety measures taken over the years, including those for level
crossings, there has been a steep decline in the number of accidents.
Number of Consequential Train Accidents has reduced as shown in the table
below:-Year Consequential Accidents
2014-15 135
2025-26 (Till 31.01.2026) 12 (90% lesser)
Another important index showing improvement in safety in train operations
is Consequential Accidents Index, the details of which are as under:-
Consequential Accident Index:-
Year Accident Index
2014-15 0.11
2024-25 0.03 (73% lesser)
This index measures number of consequential accidents as a ratio of total
running Kilometers of all trains.
No. of consequential accidents
Accident Index =
No. of trains X million kilometers runThe various safety measures taken to enhance safety in train operations are
as under:-
1. On Indian Railways, the expenditure on Safety related activities has
increased over the years as under:-
Expenditure/Budget on Safety related activities (Rs. in Cr.)
2013-14 2022-23 2023-24 2024-25 2025-26
39,200 87,336 1,01,662 1,14,022 1,17,693
2. Electrical/Electronic Interlocking Systems with centralized operation of
points and signals have been provided at 6,660 stations up to 31.12.2025 to
reduce accidents due to human failure.
3. Interlocking of Level Crossing (LC) Gates has been provided at 10,097
Level Crossing Gates up to 31.12.2025 for enhancing safety at LC Gates.
4. Complete Track Circuiting of stations to enhance safety by verification of
track occupancy by electrical means has been provided at 6,665 stations up
to 31.12.2025.
5. Kavach is a highly technology intensive system, which requires safety
certification of highest order. Kavach was adopted as a National ATP system
in July 2020. Based on deployment of Kavach version 3.2 on 1465 RKm on
South Central Railway and experience gained, further improvements were
made. Finally, Kavach specification version 4.0 was approved by RDSO on
16.07.2024.
After extensive and elaborate trials, Kavach Version 4.0 has been
successfully commissioned on 1297 Route Kilometres, covering the high
density Delhi - Mumbai and Delhi - Howrah routes. On the Delhi - Mumbai
route Kavach ver 4.0 has been commissioned on Junction cabin - Palwal -
Mathura - Nagda section (667 Rkm) & Ahmedabad - Vadodara - Virar section(432 Rkm) and on the Delhi - Howrah route on Gaya - Sarmatanr (93 Rkm) and
Bardhaman - Howrah section (105 Rkm).
6. Detailed instructions on issues related with safety of Signalling, e.g.
mandatory correspondence check, alteration work protocol, preparation of
completion drawing, etc. have been issued.
7. System of disconnection and reconnection for S&T equipment as per
protocol has been re-emphasized.
8. All locomotives are equipped with Vigilance Control Devices (VCD) to
improve alertness of Loco Pilots.
9. Retro-reflective sigma boards are provided on the mast which is located
two OHE masts prior to the signals in electrified territories to alert the crew
about the signal ahead when visibility is low due to foggy weather.
10. A GPS based Fog Safety Device (FSD) is provided to loco pilots in fog
affected areas which enables loco pilots to know the distance of the
approaching landmarks like signals, level crossing gates, etc.
11. Modern track structure consisting of 60 kg, 90 Ultimate Tensile Strength
(UTS) rails, Prestressed Concrete Sleeper (PSC) Normal/Wide base sleepers
with elastic fastening, fan shaped layout turnout on PSC sleepers, Steel
Channel/H-beam Sleepers on girder bridges is used while carrying out
primary track renewals.
12. Mechanisation of track laying activity through use of track machines like
PQRS, TRT, T-28 etc. to reduce human errors.
13. Maximizing supply of 130m/260m long rail panels for increasing progress
of rail renewal and avoiding welding of joints, thereby improving safety.
14. Ultrasonic Flaw Detection (USFD) testing of rails to detect flaws and
timely removal of defective rails.15. Laying of longer rails, minimizing the use of Alumino Thermic Welding
and adoption of better welding technology for rails i.e., Flash Butt Welding.
16. Monitoring of track geometry by OMS (Oscillation Monitoring System) and
TRC (Track Recording Cars).
17. Patrolling of railway tracks to look out for weld/rail fractures.
18. The use of Thick Web Switches and Weldable CMS Crossing in turnout
renewal works.
19. Inspections at regular intervals are carried out to monitor and educate
staff for observance of safe practices.
20. Web based online monitoring system of track assets viz. Track database
and decision support system has been adopted to decide rationalized
maintenance requirement and optimize inputs.
21. Detailed instructions on issues related with safety of Track, e.g.
integrated block, corridor block, worksite safety, monsoon precautions, etc.
have been issued.
22. Preventive maintenance of railway assets (Coaches & Wagons) is
undertaken to ensure safe train operations.
23. Replacement of conventional ICF design coaches with LHB design
coaches is being done.
24. All unmanned level crossings (UMLCs) on Broad Gauge (BG) route have
been eliminated by January 2019.
25. Safety of Railway Bridges is ensured through regular inspection of
Bridges. The requirement of repair/rehabilitation of Bridges is taken up
based upon the conditions assessed during these inspections.
26. Indian Railways has displayed Statutory “Fire Notices” for widespread
passenger information in all coaches. Fire posters are provided in everycoach so as to educate and alert passengers regarding various Do’s and
Don’ts to prevent fire. These include messages regarding not carrying any
inflammable material, explosives, prohibition of smoking inside the coaches,
penalties etc.
27. Production Units are providing Fire detection and suppression system in
newly manufactured Power Cars and Pantry Cars, Fire and Smoke detection
system in newly manufactured coaches. Progressive fitment of the same in
existing coaches is also underway by Zonal Railways in a phased manner.
28. Regular counselling and training of staff is undertaken.
29. Concept of Rolling Block introduced in Indian Railways (Open Lines)
General Rules vide Gazette notification dated 30.11.2023, wherein work of
integrated maintenance/ repair/replacement of assets is planned up to 52
weeks in advance on rolling basis and executed as per plan.
The details of the Safety related works related to better maintenance
practices, Technological improvements, better infrastructure and rolling
stock etc. undertaken by Railways are tabulated below:-
Item 2004-05 to 2014-15 to 2014-25 Vs.
SN 2013-14 2024-25 2004-14
Technological Improvements
1. Use of high-quality 57,450 1.43 Lakh More than 2
rails(60 Kg) (Km) Km Km times
2. Longer Rail Panels 9,917 Km 77,522 Km Nearly 8
(260m) (Km) times
3. Electronic 837 3,691 More than 4
Interlocking Stations Stations times
(Stations)
4. Fog Pass Safety As on As on 288 times
Devices (Nos.) 31.03.14: 31.03.25:
90 Nos. 25,939
Nos.5. Thick Web Switches Nil 28,301
(Nos.) Nos.
Better Maintenance Practices
1. Primary Rail 32,260 Km 49,941 Km 1.5 times
Renewal (Track Km)
2. USFD (Ultra Sonic 79.43 2 Crore More than 2
Flaw detection) Lakh times
Testing of Welds
(Nos.)
3. Weld failures (Nos.) In 2013- In 2024-25: 90 %
14: 3699 370 Nos. reduction
Nos.
4. Rail fractures (Nos.) In 2013- In 2024-25: More than
14: 2548 289 Nos. 88%
Nos. reduction
Better Infrastructure and Rolling Stock
1. New Track KM added 14,985 34,428 Km More than 2
(Track Km) Km times
2. Flyovers 4,148 13,808 More than 3
(RoBs)/Underpasses Nos. Nos. times
(RUBs) (Nos.)
3. Unmanned Level As on As on Removed
crossings 31.03.14: 31.03.24:Nil
(Nos.) on BG 8,948 (All
eliminated
by
31.01.19)
4. Manufacture of LHB 2,337 42,677 More than 18
Coaches (Nos.) Nos. times
*****