GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
RAJYA SABHA
UNSTARRED QUESTION NO. 1731
ANSWERED ON 13.02.2026
RAILWAY INFRASTRUCTURE AND PASSENGER FACILITIES IN GUJARAT
1731 SHRI BABUBHAI JESANGBHAI DESAI:
Will the Minister of RAILWAYS be pleased to state:
(a) whether Government proposes enhanced budgetary allocation for railway infrastructure
development in Gujarat, including new lines, doubling, electrification and modernization of
stations;
(b) the steps being taken to improve passenger amenities, safety and punctuality of trains in the
State;
(c) whether freight corridors, port connectivity and industrial rail link projects in Gujarat are
being expedited; and
(d) whether employment generation and local vendor participation in railway projects across
Gujarat are being prioritized in the upcoming Budget?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (d): Budget allocation in the recent years has increased significantly. Budget allocation for
infrastructure projects and safety works, falling fully/partly in the State of Gujarat is as under:
Period Outlay
2009-14 ₹589 crore/year
2025-26 ₹17,155 crore (More than 29 times)
The details of commissioning/laying of new track, falling fully/partly in the State of Gujarat during
2009-14 and 2014-25, is as under:
Period New Track Commissioned Average Commissioning of new tracks
660 Km 132 Km/year
2009-14
2,764 Km 251 Km/yr (nearly 2 times)
2014-25
As on 01.04.2025, 36 Railway projects (6 New Lines, 17 Gauge Conversion and 13 Doubling), of a
total length of 2,564 Km, costing ₹30,275 crore, falling fully/partly in the State of Gujarat have
Contd…2
§-2-
been sanctioned, out of which, 863 Km length has been commissioned and an expenditure of
₹12,865 crore has been incurred upto March 2025. The summary is as under:-
Category No. of sanctioned Total length Length Total
projects (Km) commissioned Expenditure upto
upto Mar'25 (Km)
Mar'25 (Cr.)
New Lines 6 532 105 5,494
Gauge
17 1,379 718 6,213
Conversion
Doubling /
13 653 40 1,158
Multitracking
Total 36 2,564 863 12,865
Details of some of the completed projects, falling fully/partly in the State of Gujarat, are as under:
S.No. Name of Project Cost (₹ in Cr.)
1 Mahesana-Taranga Hill Gauge Conversion (210 Km) 891
2 Himmatnagar-Khedbrahma Gauge Conversion (55 Km) 482
3 Ahmedabad-Botad Gauge Conversion (170 Km) 1,810
4 Dhasa-Jetalsar Gauge Conversion (104 Km) 1,024
5 Ahmedabad-Mahesana Gauge Conversion (69 Km) 874
6 Katosan-Chanasma Gauge Conversion (38 Km) 484
7 Kalol-Kadi-Katosan Gauge Conversion (37 Km) 347
8 Vijapur-Ambliyasan Gauge Conversion (42 Km) 415
9 Dabhoi-Chandod with extension up to Kevadiya Gauge 1,018
Conversion (50 Km)
10 Viramgam-Samakhiali Doubling (182 Km) 1,492
11 Palanpur-Samakhayali Doubling (247 Km) 2,538
12 Mahesana-Palanpur Doubling (65 Km) 537
13 Surendranagar-Rajkot Doubling (116 Km) 1,425
14 Anand-Godhara Doubling (79 Km) 692
15 Vatva-Ahmedabad 3rd Line (8 Km) 61
16 Viramgram-Surendranagar Doubling (65 Km) 382
17 Udhna-Jalgaon Doubling (307 Km) 2,448
Details of some of the projects falling fully/partly in the State of Gujarat which have been taken up
are as under:
S. No. Project Cost (₹ in
Cr.)
1 Naliya-Jakhau Port New Line (25 Km) 410
2 Miyagam Karjan-Choranda-Malsar Gauge Conversion (37 Km) 450
3 Jambusar-Kavi Gauge Conversion (26 Km) 318
4 Kosamba-Umarpada Gauge Conversion (70 Km) 468
5 Khijadiya-Amreli Gauge Conversion (17 Km) 178
6 Gandhidham-Adipur Quadrupling (11 Km) 152
7 Barejadi-Nandej (Geratpur)- Sanand 4th Line (38 Km) 962
Contd…3
§-3-
8 Samakhiali-Gandhidham Quadrupling (53 Km) 1430
9 Vishvamitri-Dabhoi Doubling (33 Km) 394
10 Taranga Hill-Ambaji-Abu Road New Line (116 Km) 2798
11 Sabarmati D Cabin-Sarkhej Doubling (21 Km) 323
12 Deshalpar-Hajipir-Luna and Vayor-Lakhpat New Line (145 Km) 2526
13 Vadodara-Ratlam 3rd & 4th Line (259 Km) 8387
14 Rajkot-Kanalus Doubling (111 Km) 1081
In last 3 years i.e. (2022-23, 2023-24, 2024-25) and current Financial Year i.e. 2025-26, 60 surveys
(27 New Line, 08 Gauge Conversion and 25 Doubling) covering a total length of 6,471 Km have
been sanctioned falling fully/partly in the State of Gujarat.
Sanction of any railway project depends upon many parameters/factors which include the following:
Anticipated traffic projections and remunerativeness of the proposed route
First and last mile connectivity provided by the project
Connection of missing links and providing additional route
Augmentation of congested/saturated lines
Demands raised by State Governments/Central Ministries/Public representatives,
Railway’s operational requirements
Socio-economic considerations
Overall availability of funds
Completion of Railway project/s depends on various factors which include the following:
Land acquisition
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
Dedicated Freight Corridor:
Ministry of Railways (MoR) has taken up construction of two Dedicated Freight Corridors (DFC)
viz. Eastern Dedicated Freight Corridor (EDFC) from Ludhiana to Sonnagar (1,337 Km) and the
Contd…4
§-4-
Western Dedicated Freight Corridor (WDFC) from Jawaharlal Nehru Port Terminal (JNPT) to Dadri
(1,506 Km). The work on EDFC has been completed and commissioned. In WDFC, 1,404 RKm out
of total 1,506 RKm has been completed and commissioned. The balance work on WDFC from
Vaitarna-JNPT section (102 Rkm) has been taken up. The Western Dedicated Freight Corridor
(WDFC) consisting of 565 Km route in the State of Gujarat is already operational.
Punctuality:
Indian Railways makes all possible efforts to run trains on time. However, several factors affect
punctual running of trains which include path constraints, asset maintenance, alarm chain pulling,
agitations, cattle run over, bad/foggy weather and other unforeseen circumstances. Based on
assessments of factors impeding the punctual running of trains, remedial measures, both short term
and long term, are initiated. High priority is accorded to making resources available for speedy
execution of critical capacity augmentation as these on completion inter-alia facilitate improved
efficiency and reliability in train operations.
Introduction of upgraded and modern trains: Modernization and Improvement/up-gradation of
Rolling Stock to enhance safety, convenience and comfort of passengers is a continuous and ongoing
process on Indian Railways.
Indian Railways has proliferated technologically superior LHB coaches with better riding, improved
aesthetics and features like lightweight design, anti climbing features, air suspension (Secondary)
with failure indication system, stainless steel shell and disc brake system etc.
Production of LHB coaches during 2014-25 vis-à-vis 2004-14 is as under:
Period LHB coaches manufactured
2004-2014 2,337
2014-2025 42,677 (more than 18 times)
Further, with a view to improve travel experience of the passengers, Indian Railways has introduced
indigenously designed and manufactured Vande Bharat trains with modern coaches, advanced safety
features and passenger amenities. Presently, 164 Vande Bharat services are in operation on the Indian
Railway network.
These new Vande Bharat Trains have following features:
Fitted with KAVACH.
Jerk Free Semi-Permanent couplers.
Contd…5
§-5-
Centrally controlled Automatic Plug Doors and Fully Sealed wider gangways.
Emergency Alarm Push buttons and Talk Back Units on all Coaches.
Improved fire safety - Aerosol based fire detection and suppression system in electrical
cabinets and lavatories.
Higher acceleration with design/operating speed of 180/160 KMPH.
Driver-Guard communication with voice recording facility & Crash hardened memory.
Air conditioning units with indigenously developed UV-C lamp based disinfection system.
Better Ride Comfort.
CCTVs in all coaches.
For Divyangjan passengers special lavatory in the driving coaches on each end.
Coach Condition Monitoring System (CCMS) display with remote monitoring.
Railways have developed fully non-AC modern train named as Amrit Bharat express. Already 54
services are in operation. Presently, these modern trains comprise of 11 General Class coaches, 8
Sleeper Class coaches, 01 Pantry car and 02 Luggage cum Divyangjan coaches.
These trains have following enhanced features and amenities:
Better aesthetics of seat and berths with enhanced look & feel on the lines of Vande Bharat
Sleeper.
Jerk Free Semi-Automatic Couplers.
Improved Crashworthiness in coaches by provision of crash tube.
Provision of CCTV system in all coaches and Luggage room.
Improved designs of toilets.
Improved design of Ladder for ease of climbing on to the berth.
Improved LED Light fitting & Charging Sockets.
Provision of EP assisted braking system.
Aerosol based fire suppression system in toilets and electrical cubicles.
USB Type-A and Type-C mobile charging sockets.
Emergency Talk Back system for two-way communication between Passenger and
Guard/Train Manager.
Non-AC pantry with enhanced heating capacity.
Fully sealed gangways with quick release mechanism for easy attachment and detachment.
Contd…6
§-6-
Namo Bharat Rapid Rail has been introduced to enhance the travelling experience of suburban and
regional commuters for inter-city short distance movement by harnessing the features of Vande
Bharat Trains. Presently, 4 Namo Bharat Rapid Rail services are in operation on the Indian Railway
network.
The prominent features of Namo Bharat Rapid Rail are as follows:
Centrally controlled Double Leaf Automatic Sliding Doors.
CCTVs for safety and passenger surveillance.
Modular interior with Cushioned Seats and Sealed Flexible Gangway.
Emergency Talk System.
Continuous LED lighting with Energy Efficient Lighting system.
FRP Modular Toilets with vacuum evacuation.
Fully Air-Conditioned trains with Driver cab AC.
For long distance travel, the sleeper variant of Vande Bharat Express has been indigenously designed
and developed. Two such trains have already been manufactured. After extensive trials, these are
presently operational between Howrah and Kamakhya.
To improve travel experience of the passengers and set new benchmarks in terms of safe and
comfortable journey, these train sets have been provided with modern coaches having advanced
safety features and passenger amenities like:
Jerk-Free Semi permanent couplers and Anti Climbers.
Fitted with KAVACH.
Higher acceleration with design/operating speed of 180/160 KMPH.
Crashworthy Design of Car body complying with EN standards.
Fire barrier doors at the end of each coach for compliance of fire safety standards.
Improved fire safety - Aerosol based fire detection and suppression system in electrical
cabinets and lavatories.
Regenerative braking system for energy efficiency.
Air conditioning units provided with indigenously developed UV-C lamp- based disinfection
system for deactivating 99% harmful bacteria from conditioned air to improve the hygiene
standards inside the passenger area.
Contd…7
§-7-
Centrally controlled Automatic Plug Doors and Fully Sealed wider gangways.
CCTVs in all coaches.
Emergency talk-back unit for communication between Passenger and Train Manager/Loco
Pilot in case of emergency.
For Divyangjan passengers, special lavatory in the driving coaches on each end.
Centralized Coach Monitoring System for better condition monitoring of passenger amenities
such as Air conditioning, Saloon Lighting etc.
Ergonomically designed ladder for ease of climbing on to upper berths.
Electrification:
Electrification of railway network on Indian Railways has been taken up in mission mode. So far,
about 99.4% of Broad Gauge (BG) network has been electrified. The electrification in remaining
network has been taken up. Electrification carried out during 2014-25 and before 2014 is as under:
Period Route Kilometer
Before 2014 (about 60 years) 21,801
2014-2025 46,900
In Gujarat, entire existing BG network has been electrified. Further, all new line / multi-tracking
projects are being sanctioned and constructed with electrification.
In addition to providing opportunities for direct employment in the Indian Railways through regular
& contractual employees, Indian Railways also creates employment opportunities indirectly in the
form of vendors, hoteliers, logistic players like transport operators, tourism industry, small economy
around railway stations etc.
Safety:
Safety is accorded the highest priority on Indian Railways. As a consequence of various safety
measures taken over the years, there has been a steep decline in the number of accidents.
Number of Consequential Train Accidents has reduced as shown in the table below:-
Year Consequential Accidents
2014-15 135
2025-26 (upto 31.01.2026) 12 (90% lesser)
Another important index showing improvement in safety in train operations is Consequential
Accidents Index, the details of which are as under:-
Contd…8
§-8-
Consequential Accident Index:-
Year Accident Index
2014-15 0.11
2024-25 0.03 (73% lesser)
This index measures number of consequential accidents as a ratio of total running Kilometers of all
trains.
Accident Index =
234
165
135
55
31
12
2005-06 2009-10 2014-15 2019-20 2024-25 2025-26
(upto Jan)
The various safety measures taken to enhance safety in train operations are as under-
1. On Indian Railways, the expenditure on Safety related activities has increased over the years as
under:-
Expenditure/Budget on Safety related activities (₹ in Cr.)
2013-14 2022-23 2023-24 2024-25 2025-26
39,200 87,336 1,01,662 1,14,022 1,17,693
2. Electrical/Electronic Interlocking Systems with centralized operation of points and signals have
been provided at 6,660 stations up to 31.12.2025 to reduce accidents due to human failure.
3. Interlocking of Level Crossing (LC) Gates has been provided at 10,097 Level Crossing Gates up
to 31.12.2025 for enhancing safety at LC Gates.
Contd…9
stnediccA
niarT
laitneuqesnoC
fo
.oN
No. of consequential accidents
No. of trains X million kilometers-9-
4. Complete Track Circuiting of stations to enhance safety by verification of track occupancy by
electrical means has been provided at 6,665 stations up to 31.12.2025.
5. Kavach is a highly technology intensive system, which requires safety certification of highest
order. Kavach was adopted as a National ATP system in July 2020. Based on deployment of
Kavach version 3.2 on 1,465 RKm on South Central Railway and experience gained, further
improvements were made. Finally, Kavach specification version 4.0 was approved by RDSO on
16.07 2024.
After extensive and elaborate trials, Kavach Version 4.0 has been successfully commissioned on
1,297 RKm, covering the high density Delhi - Mumbai and Delhi - Howrah routes. On the Delhi
Mumbai route Kavach ver 4.0 has been commissioned on Junction cabin-Palwal-Mathura-
Nagda section (667 Rkm) & Ahmedabad-Vadodara-Virar section (432 Rkm) and on the Delhi-
Howrah route on Gaya - Sarmatanr (93 Rkm) and Bardhaman - Howrah section (105 Rkm).
6. Detailed instructions on issues related with safety of Signalling, e.g. mandatory correspondence
check, alteration work protocol, preparation of completion drawing, etc. have been issued.
7. System of disconnection and reconnection for S&T equipment as per protocol has been re-
emphasized.
8. All locomotives are equipped with Vigilance Control Devices (VCD) to improve alertness of
Loco Pilots.
9. Retro-reflective sigma boards are provided on the mast which is located two OHE masts prior to
the signals in electrified territories to alert the crew about the signal ahead when visibility is low
due to foggy weather.
10. A GPS based Fog Safety Device (FSD) is provided to loco pilots in fog affected areas which
enables loco pilots to know the distance of the approaching landmarks like signals, level
crossing gates, etc.
11. Modern track structure consisting of 60kg, 90 Ultimate Tensile Strength (UTS) rails, Prestressed
Concrete Sleeper (PSC) Normal/Wide base sleepers with elastic fastening, fan shaped layout
turnout on PSC sleepers, Steel Channel/H-beam Sleepers on girder bridges is used while
carrying out primary track renewals.
Contd…10
§-10-
12. Mechanisation of track laying activity through use of track machines like PQRS, TRT, T-28 etc.
to reduce human errors.
13. Maxımızing supply of 130m/260m long rail panels for increasing progress of rail renewal and
avoiding welding of joints, thereby improving safety.
14. Ultrasonic Flaw Detection (USFD) testing of rails to detect flaws and timely removal of
defective rails.
15. Laying of longer rails, minimizing the use of Alumino Thermic Welding and adoption of better
welding technology for rails i.e., Flash Butt Welding.
16. Monitoring of track geometry by OMS (Oscillation Monitoring System) and TRC (Track
Recording Cars).
17. Patrolling of railway tracks to look out for weld/rail fractures
18. The use of Thick Web Switches and Weldable CMS Crossing in turnout renewal works.
19. Inspections at regular intervals are carried out to monitor and educate staff for observance of
safe practices.
20. Web based online monitoring system of track assets viz. Track database and decision support
system has been adopted to decide rationalized maintenance requirement and optimize inputs.
21. Detailed instructions on issues related with safety of Track, e.g. integrated block, corridor block,
worksite safety, monsoon precautions, etc. have been issued.
22. Preventive maintenance of railway assets (Coaches & Wagons) is undertaken to ensure safe
train operations.
23. Replacement of conventional ICF design coaches with LHB design coaches is being done.
24. All unmanned level crossings (UMLCs) on Broad Gauge (BG) route have been eliminated by
January 2019.
25. Safety of Railway Bridges is ensured through regular inspection of Bridges. The requirement of
repair/rehabilitation of Bridges is taken up based upon the conditions assessed during these
inspections.
Contd…11
§-11-
26. Indian Railways has displayed Statutory "Fire Notices" for widespread passenger information in
all coaches. Fire posters are provided in every coach so as to educate and alert passengers
regarding various Do's and Don'ts to prevent fire. These include messages regarding not
carrying any inflammable material, explosives, prohibition of smoking inside the coaches,
penalties etc.
27. Production Units are providing Fire detection and suppression system in newly manufactured
Power Cars and Pantry Cars, Fire and Smoke detection system in newly manufactured coaches.
Progressive fitment of the same in existing coaches is also underway by Zonal Railways in a
phased manner.
28. Regular counselling and training of staff is undertaken.
29. Concept of Rolling Block introduced in Indian Railways (Open Lines) General Rules vide
Gazette notification dated 30.11.2023, wherein work of integrated maintenance/
repair/replacement of assets is planned up to 52 weeks in advance on rolling basis and executed
as per plan.
The details of the Safety related works related to better maintenance practices, technological
improvements, better infrastructure and rolling stock etc. undertaken by Railways are tabulated
below:-
SN Item 2004-05 to 2014-15 to 2024-25 2014-25 Vs.
2013-14 2004-14
Technological Improvements
1 Use of high-quality rails 57,450 Km 1.43 Lakh Km More than 2 times
(60 Kg) (Km)
2 Longer Rail Panels 9,917 Km 77,522 Km Nearly 8 times
(260m) (Km)
3 Electronic Interlocking 837 Stations 3,691 Stations More than 4 times
(Station
4 Fog Pass Safety Devices As on As on 31.03.25: 288 times
(Nos.) 31.03.14: 25,939 Nos.
90 Nos.
5 Thick Web Switches Nil 28,301 Nos. -
(Nos.)
Better Maintenance Practices
1 Primary Rail Renewal 32,260 Km 49,941 Km 1.5 times
(Track Km)
Contd…12
§-12-
2 USFD (Ultra Sonic Flaw 79.43 Lakh 2 Crore More than 2
Detection) Testing of times
Welds (Nos.)
3 Weld failures (Nos.) In 2013-14: In 2024-25: 370 90% reduction
3,699 Nos. Nos.
4 Rail fractures (Nos.) In 2013-14: In 2024-25: 289 More than
2,548 Nos. Nos. 88% reduction
Better Infrastructure and Rolling Stock
1 New Track Km added 14,985 Km 34,428 Km More than 2
(Track Km) times
2 Flyovers 4,148 Nos. 13,808 Nos. More than 3
(RoBs)/Underpasses times
(RUBs) (Nos.)
3 Unmanned crossings As on As on 31.03.24:Nil Removed
(Nos.) on BG 31.03.24: (All eliminated by
8,948 31.01.19)
4 Manufacture of LHB 2,337 Nos. 42,677 More than 18
Coaches (Nos.) times
Station redevelopment:
Ministry of Railways has launched Amrit Bharat Station Scheme for redevelopment of stations with
a long-term approach.
The scheme involves preparation of master plans and their implementation in phases to improve the
stations. The master planning includes:
Improvement of access to station and circulating areas
Integration of station with both sides of city
Improvement of station building
Improvement of waiting halls, toilets, sitting arrangement, water booths
Provision of wider foot over bridge/air concourse commensurate with passenger traffic
Provision of lift/escalators/ramp
Improvement /Provision of platform surface and cover over platforms
Provision of kiosks for local products through schemes like ‘One Station One Product’
Parking areas, Multimodal integration
Amenities for Divyangjans
Better passenger information systems
Provision of executive lounges, nominated spaces for business meetings, landscaping, etc.
keeping in view the necessity at each station
Contd…13
§-13-
The scheme also envisages sustainable and environment friendly solutions, provision of ballastless
tracks etc. as per necessity, phasing and feasibility and creation of city centre at the station in the
long term.
So far, 1,337 stations have been identified for development under this scheme, out of which 87
stations are located in Gujarat. The names of stations identified for development under Amrit Bharat
Station Scheme in Gujarat are as following:
State No. of Name of Stations
Stations
Ahmedabad, Anand, Ankleshwar, Asarva, Bardoli, Bhachau,
Bhaktinagar, Bhanvad, Bharuch, Bhatiya, Bhavnagar, Bhestan, Bhildi,
Bilimora Jn, Botad Jn., Chandlodia, Chorvad Road, Dabhoi Jn, Dahod,
Dakor, Derol, Dhrangadhra, Dwarka, Gandhidham, Godhra Jn,
Gondal, Hapa, Himmatnagar, Jam Jodhpur, Jam Wanthali, Jamnagar,
Junagadh Jn, Kalol Jn, Kanalus Jn, Karamsad, Keshod, Khambhaliya,
Kim, Kosamba Jn, Lakhtar, Limbdi, Limkheda, Mahemadabad Kheda
Gujarat 87
Road, Mahesana Jn, Mahuva, Maninagar, Mithapur, Miyagam Karjan
Jn, Morbi, Nadiad Jn, Navsari, New Bhuj, Okha, Paddhari, Palanpur
Jn, Palitana, Patan, Porbandar, Pratapnagar, Rajkot Jn, Rajula Jn,
Sabarmati BG, Sabarmati MG, Sachin, Samakhiyali, Sanjan,
Savarkundla, Sayan, Siddhpur, Sihor Jn., Somnath, Songadh, Surat,
Surendranagar, Than, Udhna, Udvada, Umargaon Road, Unjha, Utran,
Vadodara, Vapi, Vatva, Veraval, Viramgam, Vishvamitri Jn., Wankaner
Development works at railway stations under Amrit Bharat Station Scheme in Gujarat have been
taken up at a good pace. Till now, works of 21 stations (Dakor, Derol, Godhra Jn, Hapa, Jam
Jodhpur, Jam Wanthali, Kanalus Jn, Karamsad, Khambhaliya, Kosamba Jn, Limbdi, Mahuva,
Mithapur, Morbi, Okha, Palitana, Porbandar, Rajula Jn, Samakhiyali, Sihor Jn., Utran) in Gujarat
have been completed under this scheme.
The activities for development at other stations have also been taken up at good pace and
progress of some of the stations is as given below:
Bardoli station: The work of widening of platform no.1 has been completed. The works
of improvement to station building, first class waiting room, toilet block, circulating area
and 12m Foot Over Bridge have been taken up.
Contd…14
§-14-
Limkheda station: The works of new station building, improvement of existing station
building, raising of platform no. 1 & 2/3, improvement of platform surface, toilet block at
platform no. 1 & 2/3, improvement of circulating area and entry/exit gate have been
completed. The works of platform shelter, lighting and 6 m Foot Over Bridge have been
taken up.
Asarva station: The works of new station building, porch, waiting room, toilet and
booking counter have been completed. The works of platform shelter, platform surfacing,
circulating area, parking and Divyangjan facilities have been taken up.
Sehore station: The works of platform shelter, platform surface, waiting hall, toilet,
circulating area, approach road, signage and station illumination have been completed.
The work of 12 m Foot Over Bridge has been taken up.
Further, development / redevelopment / upgradation / modernization of stations on Indian Railways
is a continuous and ongoing process and works in this regard are undertaken as per requirement,
subject to inter-se priority and availability of funds. Development / redevelopment / upgradation /
modernization of a station is carried out based on category of station/condition/traffic handled etc.
Development / Upgradation of railway stations is complex in nature involving safety of passengers
& trains and requires various statutory clearances such as fire clearance, heritage, tree cutting, airport
clearance etc. The progress also gets affected due to brownfield related challenges such as shifting of
utilities (involving water/sewage lines, optical fibre cables, gas pipe lines, power/signal cables, etc.),
infringements, operation of trains without hindering passenger movement, speed restrictions due to
works carried out in close proximity of tracks and high voltage power lines, etc. and these factors
affect the completion time.
Further, development / upgradation / modernization of stations including Amrit Bharat Station
Scheme is generally funded under Plan Head-53 ‘Customer Amenities’. The details of allocation and
expenditure under Plan Head-53 are maintained Zonal Railway-wise and not work-wise or station-
wise or state-wise. Gujarat is covered under the jurisdiction of two railway zones, namely, North
Western Railway and Western Railway. For these zones, an allocation of ₹2,081 crore has been made
for the financial year 2025-26, out of which an expenditure of ₹1,629 crore (up to December, 2025)
has been incurred so far.
*****
§