GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 2846
TO BE ANSWERED ON 05.08.2026
RAILWAY INFRASTRUCTURE DEVELOPMENT IN TELANGANA AND TAMIL
NADU
2846. SHRI SURESH KUMAR SHETKAR:
SHRI VIJAYAKUMAR ALIAS VIJAY VASANTH:
Will the Minister of RAILWAYS be pleased to state:
(a) whether the Government has allocated adequate funds for railway
infrastructure development in Telangana and Tamil Nadu and if so, the
details of allocation and utilisation of funds, year-wise;
(b) whether new railway routes and expansions are expected to reduce
congestion and improve passenger and freight movement in Telangana
and Tamil Nadu and if so, the details thereof including projected
outcomes;
(c) whether land acquisition, environmental clearances and regulatory
approvals are causing delays in railway projects in Telangana and Tamil
Nadu and if so, the details thereof and steps taken to resolve the
issue/expedite the process;
(d) whether coordination issues between Central and State authorities have
impacted progress of railway projects and if so, the details thereof
including the corrective measures taken;
(e) whether Government proposes to formulate a time-bound action plan to
complete all pending railway projects and new routes in Telangana and
Tamil Nadu and if so, the details thereof including the implementation
roadmap;
(f) whether Government has conducted surveys for new railway routes in
Telangana and Tamil Nadu and if so, the details thereof including
number of surveys, proposed routes and status of approvals;
(g) whether Government has introduced new train services on newly
developed or upgraded routes in Telangana and Tamil Nadu and if so,
the details thereof including the passenger benefits achieved; and
§ Page 1 of 24(h) whether doubling projects in high-density routes are progressing as per
schedule in country and if so, the details thereof including the
bottlenecks, if any?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (h):
TELANGANA
Railway Budget:
Budget allocation in the recent years has increased significantly. Budget
allocation for infrastructure projects and safety works, falling fully/partly in
the State of Telangana is as under:
Period Outlay
2009-14 ₹886 Cr./Yr. (including Andhra Pradesh)
2026-27 ₹5,454 crore (more than 6 times)
Track Construction:
The details of commissioning/laying of new track falling fully/partly in the
State of Telangana is as under:
Period New Track Average Commissioning of new tracks
Commissioned
2009-14 87 Km 17.4 km/per year
2014-26 888 Km 73.98 km /per year (more than 4 times)
Projects Sanctioned:
As on 01.04.2026, 21 Railway projects (6 New Lines and 15 Doubling), of a
total length of 2,347 Km, costing ₹40,769 crore falling fully/partly in the
State of Telangana have been sanctioned. The summary is as under:-
Page 2 of 24Category No. of Total Length Total Exp.
projects Length (in Commissioned till upto March,
Km) March, 2026 2026 (₹ in Cr.)
(in Km)
New Line 6 840 245 3,969
Doubling/Multi- 15 1,507 432 8,136
tracking
Total 21 2,347 677 12,105
Recently Completed Projects:
Details of some of the recently completed projects falling fully/partly in the
State of Telangana are as under:
S.No. Name of Project Cost (₹ in Cr.)
1 Peddapalli-Nizamabad new line (178 Km) 926
2 Jaggayyapeta-Janpahad new line (48 Km) 737
3 Akkanpet-Medak new line (17 Km) 205
4 Bhadrachalam Road-Sattupalli new line (56 Km) 990
5 Raghavapuram-Mandamari doubling (24 Km) 165
6 Raichur-Guntakal doubling (81 Km) 388
7 Macheryal-Peddampet tripling (9 Km) 120
8 Secunderabad-Mehboobnagar doubling (85 Km) 1,266
9 MMTS Phase-II (103 Km) 1,156
10 Peddapalli Byepass line (2 Km) 37
Ongoing Projects:
Some of the major projects falling fully/partly in the State of Telangana
which have been taken up are as under:
Page 3 of 24S.N Name of Project Cost
(₹ in Cr.)
1 Munirabad-Mahabubnagar new line (247 Km) 3,978
2 Manoharabad-Kotapalli new line (151 Km) 3,203
3 Malkangiri-Pandurangapuram via Bhadrachalam new line 3,592
(174 Km)
4 Kazipet-Vijaywada 3rd line (220 km) 3,315
5 Kazipet-Ballarshah 3rd line (202 Km) 4,063
6 Guntur-Bibinagar doubling (239 Km) 2,853
7 Mudkhed-Medchal & Mahbubnagar-Dhone doubling (417 4,686
Km)
8 Bhadrachalam Road-Dornakal doubling (55 Km) 770
9 Motumari-Vishnupuram doubling (89 Km) & Rail over Rail 1,596
at Motumari (11 Km) (100 Km)
10 Secunderabad Wadi 3rd and 4th line (173 Km) 5,012
11 Rail over Rail (RoR) Flyover at Dornakal (11 Km) 327
12 Guntakal-Wadi 3rd & 4th line (230 Km) 4,758
In last three years i.e. 2023-24, 2024-25, 2025-26 and current financial year
2026-27, 31 surveys (15 new line and 16 doubling) covering a total length of
3,902 km falling fully/partly in the State of Telangana have been
sanctioned.
Execution of important infrastructure projects falling fully/partly in the
State of Telangana is held up due to delay in land acquisition. Status of land
acquisition in Telangana is as under:
Total Land required 2,792 Ha
Land Acquired 1,772 Ha (63%)
Balance Land to be acquired 1020 Ha (37%)
Page 4 of 24Details of some major projects which are delayed due to land acquisition
are as under:-
SN Name of the project Total Land Balance Amount
land acquired Land to Paid to
required (Ha) be State (Cr.)
(Ha) acquired
(Ha)
1. Guntur- Bibinagar 63 7 56 40
Doubling
2. Mudkhed – Medchal & 184 12 172 38
Mahbubnagar – Dhone
Doubling
Tamil Nadu:
Railway Budget:-
Budget allocation in recent years has increased significantly. Budget
allocation for infrastructure projects and safety works, falling fully/partly in
the State of Tamil Nadu is as under:
Period Outlay
2009-14 ₹879 crore/year
2026-27 ₹ 7,611 crore (more than 8 times)
Track Construction:
The details of constructing new track falling fully/partly in the State of
Tamil Nadu are as under:
Period New track Commissioned
2009-14 923 Km
2014-26 1,356 Km
Page 5 of 24Projects sanctioned:-
As on 01.04.2026, 19 projects (08 new line, 03 gauge conversion and 08
doubling) of total length of 1,874 km, costing ₹27,282 Crore, falling
fully/partly in the State of Tamil Nadu have been sanctioned. The summary
is as under:-
Category No. of Total Length Total Exp. upto
projects Length Commissioned March, 2026
(in km) upto March, 2026 (₹ in Cr.)
(in Km)
New Line 8 811 24 1,514
Gauge
3 748 631 3,605
Conversion
Doubling
8 314 54 3,693
/Multitracking
Total 19 1,874 709 8,812
Recently Completed Projects:-
Details of some of the recently completed projects falling fully/partly in the
State of Tamil Nadu are as under:-
S.N. Project Cost
(₹ in Crores)
1 Dindigul- Pollachi gauge conversion (121 km) 610
2 Pollachi-Palghat gauge conversion (56 km) 350
3 Pollachi-Podhanur gauge conversion (40 km) 400
4 Quilon- Tiruchendur gauge conversion (357 km) 1,122
5 Mayiladuturai - Karaikkudi gauge conversion (187 km) 1,338
6 Madurai-Bodinayakkanur gauge conversion (90 km) 593
7 Chengalpattu-Villupuram doubling (102 km) 670
8 Tiruvallur-Arakkonam 4th line (27 km) 83
9 Thanjavur-Ponmalai doubling (48 km) 370
Page 6 of 24S.N. Project Cost
(₹ in Crores)
10 Villupuram-Dindigul doubling (273 km) 2,000
11 Chennai Beach-Attipattu 4th line (22 km) 293
12 Omalur-Metturdam Patch doubling (29 km) 327
13 Chengalpattu - Villupuram and Tambaram - 1,122
Chengalpattu-3rd line (133 km)
14 Salem- Omalur doubling (11 km) 115
15 Madurai- Tuticorin doubling (160 km) 1,891
16 Maniyachi-Nagercoil doubling (102 km) 1,752
17 Chennai Beach-Chennai Egmore doubling (4 km) 272
Ongoing Projects:-
Some of the projects falling fully/partly in the State of Tamil Nadu which
have been taken up are as under:
S.N. Project Cost
(₹ in Crores)
1 Tindivanam-Nagari new line (184 km) 3,631
2 Morappur-Dharmapuri new line (36 km) 359
3 Trivandrum-Kanyakumari doubling (87 km) 4,494
4 Irugur-Podanur doubling (11 km) 277
5 Tambaram-Chengalpattu 4th line (30 km) 757
6 Attipattu-Gummidipundi 3rd & 4th line (23 km) 365
7 Tirupati- Katpadi doubling (105 km) 1,216
8 Tindivanam- Tiruvannamalai new line (71 km) 1,400
9 Atipattu – Puttur new line (88 km) 1,700
10 Chennai – Cuddalore new line (179 km) 2,670
11 Baiyapannahalli to Hosur doubling (48 km) 1,160
12 Arakkonam-Chengalpattu doubling (68 km) 993
13 Erode- Karur doubling (67 km) 986
Page 7 of 24In last three years i.e. 2023-24, 2024-25, 2025-26 and current financial year
2026-27, 29 surveys (04 new line and 25 doubling) covering a total length of
3,517 km falling fully/partly in the State of Tamil Nadu has been sanctioned.
Execution of important infrastructure projects falling fully/partly in the
State of Tamil Nadu are held up due to delay in land acquisition. Status of
land acquisition in Tamil Nadu is as under:
Total Land required for Projects in Tamil Nadu 4,612 ha
Land Acquired 1,178 ha (26%)
Balance Land to be acquired 3,434 ha (74%)
Support of the Government of Tamil Nadu is needed to expedite the land
acquisition.
Details of some major projects which are delayed due to land acquisition
are as under:-
SN Name of the project Total land Land Balance
required acquired Land to be
(in ha) (in ha) acquired
(in ha)
1. Tindivanam - Tiruvannamalai new 276 33 243
line (71 km)
2. Attiputtu-Puttur new line (88 km) 189 0 189
3. Morappur-Dharmapuri new line (36 93 47 46
km)
4. Mannargudi-Pattukkottai new line 204 0 204
(41 km)
5. Thanjavur-Pattukottai new line (52 152 0 152
km)
Page 8 of 24Further, Rameshwaram – Dhanushkodi new line (18 km) was sanctioned at
a cost of ₹734 Cr. The Foundation Stone of the project was laid on
01.03.2019. However, the project could not be started because the land
acquisition has not been undertaken by the State Govt. of Tamil Nadu.
Government of India is geared up to execute projects, however success
depends upon the support of Government of Tamil Nadu.
Sanction of any railway project depends upon many parameters/factors
which include the following:
Anticipated traffic projections and remunerativeness of the
proposed route
First and last mile connectivity provided by the project
Connection of missing links and providing additional route
Augmentation of congested/saturated lines
Demands raised by State Governments/Central Ministries/Public
representatives
Railway’s own operational requirements
Socio-economic considerations
Overall availability of funds
Railway Infrastructure projects enable socio-economic development of the
region including:
Better integration of the region with other parts of the country
Faster movement of goods and services
Improving logistics efficiency
Enhance line capacity
Page 9 of 24 Increase in direct and indirect employment opportunities for the
people of the region
Reduces operational bottlenecks
Development of tourism industry and increase in industrial activities
in the region.
Completion of Railway project/s depends on various factors which include
the following:
Land acquisition by State Government
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
Train Services:
As the railway network straddles across State boundaries, trains are
introduced as per network requirement, across such boundaries.
However, during 2025–26 and 2026–27 (up to 30.06.2026), Indian Railways (on
originating/terminating basis), with a view to facilitate the passengers of
various stations located in the State of Telangana and Tamil Nadu has
introduced 21 pairs of train services (including 10 Amrit Bharat Express) and
23 pairs of train services (including 16 Amrit Bharat Express train services)
respectively. These are as listed below:
Page 10 of 24Train services introduced in the State of Telangana:
SN Train No. & Name
1 17065/17066 Charlapalli - Shalimar Amrit Bharat Express
2 15673/15674 Charlapalli - Kamakhya Amrit Bharat Express
3 16357/16358 Nagercoil - Charlapalli Amrit Bharat Express
4 17041/17042 Charlapalli - Thiruvananthapuram North Amrit Bharat
Express
5 15293/15294 Muzaffarpur - Charlapalli Amrit Bharat Express
6 17047/17048 Charlapalli - Tiruchanur Express
7 17443/17444 Tirupati - Charlapalli Express
8 17441/17442 Tirupati - Charlapalli Express
9 17067/17068 Charlapalli - Bhubaneswar New Express
10 17043/17044 Secunderabad - Anakapalle Express
11 17071/17072 Hyderabad - Belagavi Express
12 17073/17074 Secunderabad - Belagavi Express
13 17059/17060 Charlapalli - Tiruchanur Express
14 17075/17076 Charlapalli - Belagavi Express
15 17053/17054 Charlapalli - Anakapalle Express
16 17045/17046 Charlapalli - Anakapalle Express
17 17061/17062 Charlapalli - Narasapur Express
18 17615/17616 Kacheguda - Tuticorin Express
19 18527/18528 Visakhapatnam - Charlapalli Express
20 17069/17070 Hyderabad Deccan - Kanniyakumari Express
21 17605/17606 Kacheguda-Bhagat Ki Kothi Express
Page 11 of 24Train services introduced in the State of Tamil Nadu:
SN Train No & Name
1 16601/16602 Erode-Jogbani Amrit Bharat Express
2 20603/20604 New Jalpaiguri - Nagercoil Amrit Bharat Express
3 20609/20610 New Jalpaiguri - Tiruchchirappalli Amrit Bharat Express
4 16107/16108 Tambaram – Santragachi Amrit Bharat Express
5 16121/16122 Tambaram - Thiruvananthapuram Central Amrit Bharat
Express
6 16329/16330 Nagercoil - Mangaluru Jn. Amrit Bharat Express
7 16619/16620 Podanur- Dhanbad Amrit Bharat Express
8 16357/16358 Nagercoil - Charlapalli Amrit Bharat Express
9 20625/20626 MGR Chennai Central - Bhagat Ki Kothi Express
10 16103/16104 Tambaram - Rameswaram Express
11 16807/16808 Tambaram - Tiruchchirappalli Express
12 16707/16708 Mangaluru Jn. -Tirunelveli Express
13 16621/16622 Rameswaram - Mangaluru Central Express
14 16363/16364 Ernakulam - Velankanni Express
15 17069/17070 Hyderabad - Kanniyakumari Express
16 17615/17616 Kacheguda - Tuticorin Express
17 18041/18042 Shalimar - M.G.R. Chennai Central Express
18 56007/56008 Mayiladuthurai - Velankanni Passenger
19 56009/56010 Mayiladuthurai - Karaikal Passenger
20 66621/66622 Salem - Erode MEMU
Page 12 of 24SN Train No & Name
21 66595/66596 Yesvantpur - Hosur MEMU
22 66623/66624 Palakkad - Pollachi MEMU
23 56835/56836 Mayiladuthurai - Karaikkudi Passenger
Besides, introduction of train services on any route/section is an on-going
process, which depends on various factors including:
● Capacity of that section
● Availability of path
● Availability of required rolling stock
● Availability of matching infrastructure for rolling stock
● Maintenance requirement of railway tracks and other assets
● Occupancy and the traffic requirement of the section
Gati Shakti Multi-Modal Cargo Terminal:
In order to encourage setting up of cargo terminals through private
investment, ‘Gati Shakti Multi-Modal Cargo Terminal (GCT)’ policy has been
launched. Location of the GCTs is decided on the basis of demand from
industry, potential of Cargo traffic, availability of railway infrastructure and
overall logistics potential of the area.
So far, 142 Gati Shakti Cargo Terminals (GCTs) have been commissioned,
including 6 GCTs in Telangana and 5 GCTs in Tamil Nadu. The 142
commissioned GCTs have an estimated freight handling capacity of 224
million tonnes per annum (MTPA). The policy has mobilized private
investment of approximately ₹10,000 crore through these GCTs. Freight
handled at these GCTs during 2025-26 is 146 MT. The detail of GCTs
commissioned in Telangana and Tamil Nadu are as under –
Page 13 of 24Telangana:
SN Serving Stations / Locations
1 Sattupalli
2 Sultanabad
3 Tipparthy
4 Ramagundam
5 Chityal-CTYL
6 Vishnupuram
Tamil Nadu:
SN Serving Stations/ Locations
1 Sivadi (SZV)
2 Tondiarpet
3 Velliyana
4 Ponneri
5 Arakkonam (AJJ)
In addition, In-Principle Approvals (IPAs) have been granted for the
development of GCTs at 310 more locations, including 8 locations in
Telangana and 9 locations in Tamil Nadu.
Also for improvement of customer amenities at goods and parcel terminals
all across the country, an amount of Rs. 15,500 crore has been allocated
for the financial year 2023-24 onwards.
ROBs and RUBs:
Sanctioning of works of Road over Bridge (ROB)/Road under Bridge (RUB) in
lieu of Level crossings (LCs) is a continuous and dynamic process of Indian
Page 14 of 24Railway. Such works are prioritised and taken up on the basis of their
impact on safety in train operations, mobility of trains & impact for road
users and feasibility etc.
No. of ROBs/ RUBs constructed on Indian Railways during the period 2004-
14 vis a vis 2014-26 (Upto May’26) is as under:
Period ROBs/ RUBs constructed
2004-14 4,148 Nos.
2014-26 (Upto May’26) 14,451 Nos. (520 Nos. in the State of Telangana
and 814 Nos. in the State of Tamilnadu)
As on 01.06.2026, 4,993 Nos. ROB / RUB works are sanctioned at a cost of
approx. ₹1,17,492 Cr on Indian Railways which are at various stages of
planning and execution.
118 Nos. ROB / RUB works at a cost of approx. ₹ 4,883 Cr are sanctioned in
the state of Telangana and 248 Nos. ROB / RUB works at a cost of approx. ₹
4952 Cr are sanctioned and Tamil Nadu which are at various stages of
planning and execution.
In the State of Telanagana, 16 Nos. ROBs are delayed on account of the
State Govt. The details are as under:
S.No. Reason ROBs/RUBs (in No.)
1. Delay in Land Acquisition by State Govt. 15
2. Finalization of Alignment by State Govt. 01
In the State of Tamil Nadu, 14 Nos. ROBs are delayed on account of the
State Government the details are as under:
S.No. Reason ROBs/RUBs (in No.)
1. Delay in Land Acquisition by State Govt. 10
Page 15 of 242. Finalization of Alignment by State Govt. 03
3. NOC for closure from State Govt. 01
Completion & commissioning of ROB/RUB works depends on various
factors like cooperation of State Governments in giving consent for
closure of LC, fixing of approach alignment, approval of General
Arrangement Drawing (GAD), land acquisition, removal of encroachment,
shifting of infringing utilities, statutory clearances from various
authorities, law and order situation in the area of project / work sites,
duration of working season in a year for the particular project / area due to
climatic conditions etc. All these factors affect the completion time of the
projects / works.
Further, Railways have taken following measures to expedite the progress
of work:
i. Joint survey with concerned State Govt./Road Owning Authority is
done before finalizing the General Arrangement Drawing (GAD) to
ensure smooth execution.
ii. Periodic meetings of Railway & State Government officials are done
to resolve various issues related to ROB/RUB works.
iii. Standardization of superstructure and substructure drawings for
various combinations of span, skewness and width of road on the
Railway portion has been done to avoid delays during the design
approval. This has been issued in the form of a compendium, which
can be directly adopted for Road Over Bridge across Railway lines for
expeditious planning.
Page 16 of 24Station Redevelopment:
Development / upgradation / modernisation of stations including under
Amrit Bharat Station Scheme is generally funded under Plan Head-53
‘Customer Amenities’. The details of allocation and expenditure under
Plan Head-53 are maintained Zonal Railway-wise and not station-wise
or state-wise.
Telangana is covered under the jurisdiction of two railway zones,
namely South Central Railway and South Coast Railway. For these
zones, an allocation of ₹ 967 crore has been made for the financial year
2026-27, out of which an expenditure (up to June, 2026) of ₹ 482 crore
has been incurred so far.
Tamil Nadu is covered under the jurisdiction of three railway zones,
namely Southern Railway, South Western Railway and South Coast
Railway. For these zones, an allocation of ₹ 1,298 crore has been made
for the financial year 2026-27, out of which an expenditure (up to June,
2026) of ₹ 582 crore has been incurred so far.
Ministry of Railways has launched Amrit Bharat Station Scheme for
redevelopment of stations with a long-term approach.
The scheme involves preparation of master plans and their
implementation in phases to improve the stations of Indian Railways.
The master planning, keeping in view the necessity of each station,
includes:
Improvement of access to station and circulating areas
Integration of station with both sides of city
Page 17 of 24 Improvement of station building
Improvement of waiting halls, toilets, sitting arrangement, water
booths
Provision of wider foot over bridge/subway to commensurate with
passenger traffic
Provision of lifts/escalators/ramps
Improvement of platform surface/ provision of platform shelter
Provision of kiosks for local products through schemes like ‘One
Station One Product’
Parking development
Amenities for Divyangjans
Better passenger information systems
Provision of air concourse, executive lounges, Multimodal integration,
landscaping, etc.
The scheme also envisages sustainable and environment friendly solutions
etc. as per necessity, phasing and feasibility and creation of city centre at
the station in the long term.
So far, 1,340 stations have been identified for development under this
scheme, out of which 40 stations, are located in Telangana and 77
stations, are located in Tamil Nadu. The names of stations identified for
development under Amrit Bharat Station Scheme in Telangana and
Tamil Nadu are as following:
State No. of Name of Stations
Stations
Telangana 40 Adilabad, Basar, Begumpet, Bhadrachalam
Road, Gadwal, Hafizpet, Hi-Tech city,
Huppuguda, Hyderabad, Jadcherla,
Page 18 of 24State No. of Name of Stations
Stations
Jangaon, Kacheguda, Kamareddi,
Karimnagar, Kazipet Jn, Khammam,
Lingampalli, Madhira, Mahbubabad,
Mahbubnagar, Malakpet, Malkajgiri Jn,
Manchiryal, Medak, Medchal, Miryalaguda,
Nalgonda, Nizamabad Jn, Peddapalli Jn,
Ramagundam, Secunderabad, Shadnagar,
Sri Bala Brahmeswara Jogulamba, Tandur,
Umdanagar, Vikarabad, Warangal, Yadadri,
Yakutpura, Zahirabad
Tamil Nadu 77 Ambasamudram, Ambattur, Arakkonam Jn,
Ariyalur, Avadi, Bommidi, Chengalpattu Jn,
Chennai Beach, Chennai Egmore, Chennai
Park, Chidambaram, Chinna Salem,
Chrompet, Coimbatore Jn, Coimbatore
North, Coonoor, Dharmapuri, Dindigul, Erode
Jn., Guduvancheri, Guindy, Gummidipundi,
Hosur, Jolarpettai Jn, Kanniyakumari
Terminus, Karaikkudi Jn, Karur Jn, Katpadi
Jn, Kovilpatti, Kulitturai, Kumbakonam,
Lalgudi, Madurai Jn, Mambalam, Manaparai,
Mannargudi, Mayiladuturai Jn,
Mettupalayam, Morappur, Nagercoil Jn,
Namakkal, Palani, Paramakkudi, Perambur,
Podanur Jn., Pollachi Jn, Polur, Pudukkottai,
Puratchi Thalaivar Dr. M.G. Ramachandran
Central, Rajapalayam, Ramanathapuram,
Rameswaram, Salem, Samalpatti,
Page 19 of 24State No. of Name of Stations
Stations
Sholavandan, Srirangam, Srivilliputtur,
St.Thomas Mount, Tambaram, Tenkasi,
Thanjavur Jn, Thiruvarur Jn., Tiruchendur,
Tirunelveli Jn, Tirupadripulyur, Tirupattur,
Tiruppur, Tirusulam, Tiruttani, Tiruvallur,
Tiruvannamalai, Tuticorin, Udagamandalam,
Vellore Cantt., Villupuram Jn., Virudhunagar,
Vriddhachalam Jn.
Completed stations of Telangana and Tamil Nadu:
Development works at railway stations under Amrit Bharat Station
Scheme in Telangana and Tamil Nadu have been taken up at a good
pace. Details of stations completed in Telangana and Tamil Nadu are as
under:
State No. of Name of stations
stations
Telangana 9 Begumpet, Hafizpet, Hi-Tech City, Jangaon,
Karimnagar, Mahbubabad, Ramagundam, Sri Bala
Brahmeswara Jogulamba, Warangal
Tamil 26 Ambasamudram, Bommidi, Chennai Park,
Nadu Chidambaram, Chinna Salem, Coonoor,
Karaikkudi Junction, Kulitturai, Mambalam,
Manaparai, Mannargudi, Morappur, Namakkal,
Palani, Paramakkudi, Pollachi Junction, Polur,
Samalpatti, Sholavandan, Srirangam,
Page 20 of 24State No. of Name of stations
stations
Srivilliputtur, St.Thomas Mount, Thiruvarur
Junction, Tiruvannamalai, Udagamandalam,
Vriddhachalam Junction
The activities for development at other stations have also been taken up at
good pace and progress of some of the stations is as given below:
Stations of Telangana
Secunderabad station: The works of 7.5 m wide foot over bridge at
Kazipet end, new basement parking-1 & 2 at South side, new
departure and arrival area of ground floor at South side, new
approach road at South side, new 33 KV electrical sub-station and
new Railway Protection Force building have been completed. The
works of new station building at North side, new station building
at South side, air concourse, 7.5 m wide foot over bridge, 7.5 m
wide foot over bridge and travelator at platform no. 1 & 10, sky
walk, through roof, improvement of platform surface, improvement
of circulating area at North side, new Multi Level Car Parking
(MLCP) at North side, lift, escalator, amenities for Divyangjan and
new sewage treatment plant have been taken up.
Huppuguda station: The works of new station building at main
entry, platform shelter, improvement of platform surface, new
waiting hall, new toilet, improvement of booking office at main
entry, improvement of circulating area at main entry, lift, escalator
and 12 m wide foot over bridge have been completed. The works
of improvement of station building at second entry, parking at
Page 21 of 24second entry and entrance gate at main and second entry have
been taken up.
Malkajgiri Junction station: The works of extension of station
building at second entry, platform shelter, new waiting hall, new
toilet and 12 m wide foot over bridge have been completed. The
works of improvement of platform surface, improvement of
booking office at main entry, improvement of circulating area at
main entry, parking at main entry, new entry/exit gates at main
entry, lift and escalator have been taken up.
Manchiryal station: The work of platform shelter has been
completed. The works of extension of station building at main
entry, improvement of station building at main entry, new entrance
porch at main entry, improvement of platform surface, new waiting
hall, new toilet, improvement of circulating area at main entry,
parking at main entry, lift, escalator and 12 m wide foot over
bridge have been taken up.
Kazipet Junction station: The works of platform shelter,
improvement of general waiting hall, new Pay & Use toilet, parking
at main entry, lift, escalator and 12 m wide foot over bridge have
been completed. The works of station building at main entry, new
entrance porch at main entry, improvement of platform surface of
platform no. 1 & 2/3, new Air Conditioned waiting hall,
improvement of circulating area at main entry and amenities for
Divyangjan have been up.
Page 22 of 24Stations of Tamil Nadu
Rameswaram station: The works of revamping of Multi Functional
Complex (MFC) building into retiring rooms, structural works of
East and North terminal building, parcel office, residential tower,
departure forecourt, arrival forecourt, sub station building and
sewage treatment plant have been completed. The finishing works
of East terminal building and North terminal building, departure
forecourt, sewage treatment plant, arrival forecourt, platform
shelter and improvement of waiting hall have been taken up.
Chennai Egmore station: The work of parcel building, structural
works of Gandhi-Irwin (GI) road side multi-level car parking,
Poonamallee High (PH) road side multi-level car parking and sub-
station building have been completed. The work of finishing of GI
side multi-level car parking, PH side multi-level car parking,
substation building, structural work of GI side terminal building,
foundation work of PH side terminal building, arrival foot over
bridge and air concourse have been taken up.
Virudhunagar station: The works of improvement of circulating
area, parking, entry/exit gate, installation of Coach Indication
Boards and Train Indication Boards have been completed. The
works of improvement of station building, entrance porch and 6 m
wide foot over bridge have been taken up.
Karur Junction station: The works of improvement of station
building, 12 m wide foot over bridge, improvement of circulating
area, parking, main entrance gate, waiting hall, toilets, parcel
office building, improvement of platform surface and widening of
Page 23 of 24platform no. 1 have been completed. The works of lifts and
escalators have been taken up.
Thanjavur Junction station: The works of entrance porch,
improvement of circulating area, concourse, subway, platform
shelter, arrival lobby, exit gate, booking office, installation of
Coach Indication Board, Train Indication Board and signages have
been completed. The works of parking, lift and escalator have
been taken up.
Further, development / redevelopment / upgradation / modernisation of
stations on Indian Railways, is a continuous and ongoing process and
works in this regard are undertaken as per requirement, subject to
inter-se priority and availability of funds. Development / redevelopment /
upgradation / modernisation of a station is carried out based on
category of station/condition/traffic handled etc.
Development / Upgradation of railway stations is a complex in nature
involving safety of passengers & trains and requires various statutory
clearances such as tree cutting, heritage, fire clearance, airport
clearance etc. These stations are in operation since long, so brownfield
work challenges are being faced, such as shifting of utilities (involving
water/sewage lines, optical fibre cables, gas pipelines, power/signal
cables, etc.), infringements, operation of trains without hindering
passenger movement, speed restrictions due to works carried out in
close proximity of the tracks and near to high voltage power lines, etc.
and these factors affect the progress of work and completion time.
*****