UNSTARRED QUESTION NO. 923
ANSWERED ON 06.02.2026
RAILWAY LINE BETWEEN BELAGAVI AND DHARWAD
923 SHRI IRANNA KADADI:
Will the Minister of RAILWAYS be pleased to state:
(a) the current physical and financial progress of the new railway line project between Belagavi and
Dharwad via Kittur as of January 2026;
(b) the status of the land acquisition process in the Belagavi and Dharwad districts;
(c) the details of the funds allocated and utilized for the project;
(d) the measures taken to expedite the construction of bridges and tunnels on the route; and
(e) the expected timeline for the completion of the project to reduce travel time?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (e): Dharwad – Belgaum (Belagavi) via Kittur new line project (73 km) has been sanctioned on
50:50 cost sharing basis and land to be provided free of cost by Government of Karnataka (GoK). The
project is held up on account of delay in land acquisition by State Government of Karnataka.
Karnataka
Budget allocation in the recent years has increased significantly. Budget allocation for infrastructure
projects and safety works, falling fully/partly in the State of Karnataka is as under:
Period Outlay
2009-14 ₹835 crore/year
2025-26 ₹7,564 crore (more than 9 times)
...2/--2-
As on 01.04.2025, 25 projects (15 new lines, 10 doubling) of 3,264 km length, costing ₹ 42,517 crore
falling fully/partly in Karnataka are sanctioned. The summary is as under:-
Category No of sanctioned Total Length Exp
Projects Length Commissioned upto Mar'25
(in km) Upto Mar'25 (km) (₹ in cr.)
New Line 15 2,034 421 8,794
Doubling/ Multitracking 10 1,230 973 12,516
Total 25 3,264 1,394 21,310
Details of some of the recently completed projects falling fully/partly in Karnataka are as under :
S. No Project Cost
(₹in Crores)
1 Kottur-Harihar new line (65 km) 468
2 Hassan-Bangalore new line (167 km) 1,290
3 Bidar-Gulbarga new line (110 km) 1,543
4 Shivani-Hosadurga Road doubling (10 km) 50
5 Shivani-Birur Doubling (29 km) 143
6 Hosadurga-Chikjajur doubling (29 km) 260
7 Ramanagram-Mysore patch doubling (94 km) 998
8 Yelahanka – Chennasadra doubling (13 km) 108
9 Yeshwantpur-Yelahanka doubling (12 km) 95
10 Netrawati-Mangalore Central doubling (2 km) 28
11 Kankanadi-Panambur doubling (19 km) 350
12 Arsikere-Tumkur doubling (96 km) 758
13 Yelahanka-Penukonda doubling (123 km) 1,104
14 Daund-Gulbarga doubling (225 km) 3,182
15 Hubli-Chikjajur doubling (190 km) 1,850
Some of the projects falling fully/partly in Karnataka which have been taken up are as under:
Cost
S
Project (₹ in
No.
Crores)
1 Hospet-Hubli-Londa-Vasco-de-Gama doubling (312 km) 4,153
2 Hotgi-Gadag doubling (284 km) 2,459
3 Ginigera - Raichur new line (165 km) 3,401
4 Gadag - Wadi new line (257 km) 2,842
...3/--3-
5 Bagalkot – Kudachi new line (142 km) 1,649
6 Tumkur – Rayadurga new line (207 km) 2,496
7 Tumkur – Davangere new line (182 km) 2,142
8 Kadur – Chikmagalur – Belur new line (68 km) 825
9 Baiyyapanahalli – Hosur doubling (48 km) 336
10 Yeshwanthpur – Channasandra doubling (22 km) 314
In last three years 2022-23, 2023-24, 2024-25 and current financial year 2025-26, 65 surveys (25 new
line and 40 doubling) covering a total length of 7,240 km has been sanctioned falling fully/partly in the
State of Karnataka.
Details of some major projects which are delayed due to land acquisition are as under:-
Total Land Balance
S Land acquired Land to be
Project
No. required (in ha) acquired (in
(in ha) ha)
1 Shimoga – Rannebennur new line (96 km) 559 226 333
2 Belgaum – Dharwad new line (73 km) 581 0 581
3 Shimoga – Harihar new line (79 km) 488 0 488
4 Whitefield-Kolar new line (53 km) 337 0 337
5 Hassan-Belur new line (32 km) 206 0 206
Summary of the status of land acquisition in Karnataka is as under:-
Total Land required for Projects in Karnataka 9,064 ha
Land Acquired 5,707 ha (63%)
Balance Land to be acquired 3,357 ha (37%)
Government of India is geared up to execute projects, however success depends upon the support of
Government of Karnataka.
Sanction of any railway project depends upon many parameters/factors which include the following:
Anticipated traffic projections and remunerativeness of the proposed route
First and last mile connectivity provided by the project
Connection of missing links and providing additional route
...4/--4-
Augmentation of congested/saturated lines
Demands raised by State Governments/Central Ministries/Public representatives
Railway’s own operational requirements
Socio-economic considerations
Overall availability of funds
Completion of Railway project/s depends on various factors which include the following:
Land acquisition by State Government
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
*****