**Executive Summary**
This document is an answer provided by the Minister of Railways, Information & Broadcasting and Electronics & Information Technology to Lok Sabha Unstarred Question No. 689 regarding railway projects in Haryana, to be answered on December 3, 2025. It details various aspects of railway projects in Haryana, including budget allocations, sanctioned projects, and the Amrit Bharat Station Scheme. No specific deadlines or action items for immediate implementation are outlined in this document, but it notes the importance of inter-agency coordination to support project progress.
**Key Points / Main Content**
* **Scope and Methodology:**
* Railway projects are considered Railway-wise and not State-wise/Constituency-wise.
* Projects are sanctioned based on remunerativeness, traffic projections, connectivity, and demands from various stakeholders.
* **Budget Allocation:**
* The budget allocation for infrastructure projects and safety works in Haryana has significantly increased from ₹315 crore/year (2009-14) to ₹3,416 crore (2025-26).
* **Sanctioned and Completed Projects:**
* As of April 1, 2025, 8 projects (1 new line and 7 doubling) are sanctioned, covering 491 km at a cost of ₹6775 crore, with an expenditure of ₹1571 crore incurred up to March 2025.
* Lists of recently completed projects falling fully/partly in Haryana are provided, along with costs.
* **Ongoing Surveys:**
* In the past three years (2022-23 to 2024-25) and current financial year 2025-26, 20 surveys have been sanctioned, covering 778 km.
* **Project Completion Factors:**
* Completion is dependent on various factors, including land acquisition, forest clearance, utility shifting, statutory clearances, geological conditions, law and order, and working months.
* **Amrit Bharat Station Scheme:**
* The Ministry of Railways has launched the Amrit Bharat Station Scheme for station redevelopment.
* The scheme includes master planning with improvements to station access, integration with the city, station building, waiting areas, foot over bridges, lifts/escalators, platform surfaces, kiosks, parking, and amenities.
* 1337 stations have been identified for development under this scheme, including 34 in Haryana.
* Phase-I works of 01 stations (Mandi Dabwali) in the state of Haryana have been completed under this scheme.
* Details of ongoing works at Narwana, Jind, Rewari, and Hodal stations are provided.
* Funding for this scheme falls under Plan Head-53 'Customer Amenities,' maintained Zonal Railway-wise.
* An allocation of ₹3,729 crore has been made for these zones for the financial year 2025-26, with ₹1,860 crore spent until October 2025.
* **Coordination and Monitoring:**
* Haryana Rail Infrastructure Development Corporation Ltd. (HRIDC) is executing the Haryana Orbital Rail Corridor project (125.98 km).
* Coordination and monitoring mechanisms are in place, including:
* Zonal Railways consultation and approval of designs.
* Technical inspection and authorization for freight train sections.
* Regular review meetings at Zonal Railway and Railway Board levels.
* State authority review meetings.
* Monthly progress reports from HRIDC.
* HRIDC Board meetings.
**Impact Analysis**
**Stakeholder: Ministry of Railways**
* **Impact:** Responsible for the execution and monitoring of railway projects in Haryana.
* **Action Required:** Ensure projects are executed efficiently, coordinate with HRIDC and State Government, and oversee the Amrit Bharat Station Scheme.
**Stakeholder: Haryana Rail Infrastructure Development Corporation Ltd. (HRIDC)**
* **Impact:** Directly involved in executing the Haryana Orbital Rail Corridor project.
* **Action Required:** Adhere to the monitoring mechanisms, submit progress reports, and coordinate with the Railways and State Government.
**Stakeholder: State Government of Haryana**
* **Impact:** Involved in land acquisition, statutory clearances, and providing necessary support for project implementation.
* **Action Required:** Facilitate land acquisition, ensure statutory clearances, and participate in review meetings to monitor project progress.
**Stakeholder: Citizens of Haryana**
* **Impact:** Will benefit from improved railway infrastructure, enhanced station amenities, and increased connectivity.
* **Action Required:** No direct action required.
**Stakeholder: Railway Passengers**
* **Impact:** Will benefit from improved passenger amenities.
* **Action Required:** No direct action required.
Key Entities Referenced
Haryana: The Indian state where the railway projects mentioned in the question are located.
Ministry of Railways: The government ministry responsible for the railway projects in question.
Amrit Bharat Station Scheme: A scheme for the redevelopment and modernization of railway stations, with long-term approach.
Haryana Rail Infrastructure Development Corporation Limited (HRIDC): A State Joint Venture Company of Haryana (51%) and Ministry of Railways (49%) executing Haryana Orbital Rail Corridor project.
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 689
TO BE ANSWERED ON 03.12.2025
RAILWAY PROJECTS IN HARYANA
689. SHRI DEEPENDER SINGH HOODA:
Will the Minister of RAILWAYS be pleased to state:
(a) the details of the number of railway projects presently under
execution in Haryana along with the year of commencement and the
expected time period for completion of each;
(b) the year-wise details of funds allocated and utilised for every such
project since its inception;
(c) the details of projects that have faced delay/cost overruns including
the original sanctioned cost, the revised estimated cost, percentage
of escalation and specific reasons for such cost variations;
(d) the steps taken by the Government for the modernisation and
redevelopment of railway stations in Haryana along with the
proposed timeline for their completion; and
(e) whether any monitoring mechanism has been established to ensure
timely completion and effective coordination between Railways,
Haryana Rail Infrastructure Development Corporation Limited
(HRIDC) and the State Government for expeditious implementation of
these projects and if so, the details thereof?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (e): Railway projects are surveyed/ sanctioned/executed ZonalRailway wise and not State-wise/Constituency-wise as the Railways’
projects may span across State boundaries. Railway projects are
sanctioned on the basis of remunerativeness, traffic projections, last mile
connectivity, missing links and alternate routes, augmentation of
congested/saturated lines, demands raised by State Governments, Central
Ministries, Members of Parliament, other public representatives, Railway’s
own operational requirement, socio-economic considerations etc.
depending upon throwforward of ongoing projects and overall availability of
funds.
Budget allocation for Infrastructure projects and safety works, falling
fully/partly in the State of Haryana is as under:
Period Outlay
2009-14 ₹315 crore/year
2025-26 ₹ 3,416 Cr. (nearly 11 times)
As on 01.04.2025, 8 projects(01 New Lines and 07 Doubling), covering a
total length of 491 km, costing ₹6775 crore, falling fully/partly in Haryana
are sanctioned and an expenditure of ₹1571 crore has been incurred upto
March 2025.
The status of work is summarized as under:
Category No. of Total Length Expenditure upto
project Length Commissioned March 2025
s (in Km) (in Km) (₹in Cr)
New Lines 1 28 0 925
Doubling / 7 463 0 646
Multitracking
Total 8 491 0 1571
Details of some of the recently completed projects falling fully/partly in
the State of Haryana are as under:S. Cost
Project
No. (Rs. in Cr.)
1 Jind-Sonepat New Line (89 Km) 800
Rewari-Rohtak including MM bye-pass line. (85
2 1001
Km)
3 Rohtak-Mehem-Hansi New Line (64 Km) 889
Suratpura-Hanumangarh-Sriganganagar (241
4 896
Km)
Jaipur-Ringus-Sikar-Churu & Sikar-Loharu (320
5 1105
Km)
6 Jakhal- Mansa Doubling (45 Km) 163
7 Khukhrana- Panipat Doubling (8 Km) 58
8 Ambala-Dhapper-Chandigarh Doubling (45 Km) 339
9 Rewari-Manheru Doubling (69 Km) 465
10 Tughlakhabad-Palwal 4th line (34 Km) 366
11 Mathura – Palwal 4th Line (80 Km) 669
Connectivity between Palwal and New Prithala
12 66
(10 Km)
Some of the projects falling fully/partly in the State of Haryana which
have been taken up are as under:
SN. Project Cost
(Rs. in
Cr.)
1 Chandigarh-Baddi (28 Km) 1540
2 Connectivity between Palwal and New Prithala (4 66
Km)
3 Doubling between Churu-Sadulpur BG Line and 3554
Doubling between Luni-Samdari-Bhildi section (330
Km)
4 Rewari-Khatuwas Doubling (28 Km) 352
5 Bhiwani-Dobh-Bahali Doubling (42 Km) 471
6 Doubling between Manheru-Bawani Khera (32 Km) 413
7 Doubling between Khatuwas – Narnaul (24 Km) 313
In last three years 2022-23, 2023-24, 2024-25 and current financial year
2025-26, 20 surveys (06 New Line and14 Doubling) covering a total length
of 778 Km has been sanctioned falling fully/partly in the State of Haryana.Completion of Railway project/s depends on various factors which include
the following:
Land acquisition by State Government
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
Ministry of Railways has launched Amrit Bharat Station Scheme for
redevelopment of stations with a long-term approach.
The scheme involves preparation of master plans and their
implementation in phases to improve the stations. The master planning
includes:
Improvement of access to station and circulating areas
Integration of station with both sides of city
Improvement of station building
Improvement of waiting halls, toilets, sitting arrangement,
water booths
Provision of wider foot over bridge/air concourse
commensurate with passenger traffic
Provision of lift/escalators/ramp
Improvement /Provision of platform surface and cover over
platforms
Provision of kiosks for local products through schemes like
‘One Station One Product’
Parking areas, Multimodal integration
Amenities for Divyangjans Better passenger information systems
Provision of executive lounges, nominated spaces for
business meetings, landscaping, etc. keeping in view the
necessity at each station.
The scheme also envisages sustainable and environment friendly
solutions, provision of ballastless tracks etc. as per necessity,
phasing and feasibility and creation of city centre at the station in
the long term.
So far, 1337 stations, including 34 stations located in the state of
Haryana have been identified for development under Amrit Bharat
Station Scheme. The name of stations identified for development under
Amrit Bharat Station Scheme in the state of Haryana are as following:
State No. of Name of Stations
Stations
Haryana 34 Ambala Cantt., Ambala City, Bahadurgarh,
Ballabhgarh, Bhattu, Bhiwani Jn, Charkhi Dadri,
Faridabad, Faridabad New Town, Gohana,
Gurugram, Hansi, Hisar, Hodal, Jind Jn,
Kalanwali, Kalka, Karnal, Kosli, Kurukshetra Jn,
Loharu, Mahendragarh, Mandi Adampur, Mandi
Dabwali, Narnaul, Narwana Jn, Palwal, Panipat
Jn, Pataudi Road, Rewari, Rohtak, Sirsa, Sonipat,
Yamunanagar Jagadhari
Development works at railway stations under Amrit Bharat Station
Scheme in the state of Haryana have been taken up at a good pace. Till
now, phase-I works of 01 stations (Mandi Dabwali) in the state of
Haryana have been completed under this scheme.The works at other
stations have also been taken up at good pace and progress of some of
the above stations is as given below:
Narwana station: The works of new station building, waiting rooms,
toilets, platform shelters, improvement of platform surface,circulating area, parking area, lifts and 12 m Foot Over Bridge have
been completed. The finishing works have been taken up.
Jind station: The works of station building, waiting rooms, toilets,
platform shelter, improvement of platform surface, circulating area,
parking area, lifts, escalators and 12 m Foot Over Bridge have been
completed. The finishing works have been taken up.
Rewari station: The works of improvement of station building,
platform surface, waiting hall, toilet, circulating area, lifts,
escalators, Foot Over Bridge have been completed. The finishing
works have been taken up.
Hodal station: The works of new main entry station building, second
entry station building, waiting hall, toilet, platform shelter,
circulating area, parking area and improvement of platform surface
have been completed. The finishing works have been taken up.
Development / redevelopment / upgradation / modernisation of stations on
Indian Railways is a continuous and ongoing process and works in this
regard are undertaken as per requirement, subject to inter-se priority and
availability of funds. The priority for development / redevelopment /
upgradation / modernisation of stations is accorded to higher category of
station over lower category of station while sanctioning and executing the
works.
Further, development / upgradation / modernization of stations including
Amrit Bharat Station Scheme is generally funded under Plan Head-53
‘Customer Amenities’.The details of expenditure incurred for development
and maintenance of stations are maintained Zonal Railway-wise under Plan
Head-53 ‘Customer Amenities’ and not work-wise or Station-wise. The state
of Haryana is covered under the jurisdiction of three railway zones, namely,
Northern Railway, North Central Railway and North Western Railway. For
these zones, an allocation of ₹ 3,729 crore has been made for the financialyear 2025-26, out of which an expenditure (up to October, 2025) of ₹ 1,860
crore has been incurred so far.
Proposals / requests / suggestions / representations, both formal and
informal for Railway projects / Works across the country are received on
the basis of demands raised by State Governments, Members of
Parliament, Ministries of Central Government, elected representatives,
Railways' own requirements, organizations / rail users etc., at various
levels including Railway Board, Zonal Railways, Division Office etc. Receipt
of such proposals / requests / suggestions / representations is a continuous
and dynamic process and these are examined and action as found feasible
and justified is taken from time to time and centralized compendium for the
same is not maintained.
Development / Upgradation of railway stations is complex in nature
involving safety of passengers & trains and requires various statutory
clearances such as fire clearance, heritage, tree cutting, air-port
clearance etc. The progress also gets affected due to brownfield related
challenges such as shifting of utilities (involving water/sewage lines,
optical fibre cables, gas pipe lines, power/signal cables, etc.),
infringements, operation of trains without hindering passenger movement,
speed restrictions due to works carried out in close proximity of tracks
and high voltage power lines, etc. and these factors affect the completion
time. Therefore, no time frame can be indicated at this stage.
Haryana Rail Infrastructure Development Corporation Ltd. (HRIDC), a State
Joint Venture Company of Haryana (51%) and Ministry of Railways (49%) is
executing Haryana Orbital Rail Corridor project (125.98 km) at a cost of Rs.
5618 Cr. So far, Patli-Manesar-MSIL (10 Km) section has been
commissioned for freight trains operations and work in balance section is
in progress. For expeditious implementation of the project the following
mechanism are being adopted:- All drawings and designs of the projects are prepared in
consultation with the Zonal Railways and approved by the
nominated officers of the Indian Railways.
The opening of the section for freight trains is only after technical
inspection by the nominated committee of the Indian Railways and
authorization by the General Manager of Northern Railways.
Regular review meetings are held up at Zonal Railway as well as
Railway Board level.
Review meetings are held regularly by the state authorities at the
level of Chief Secretary or ACS/PW for monitoring the progress.
Monthly Progress reports of the projects are submitted by the
HRIDC to the Railways and the State government.
Progress of the Projects are reviewed in all the Board meetings of
HRIDC, chaired by the Chief Secretary.
*****