GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
RAJYA SABHA
UNSTARRED QUESTION NO. 3333
ANSWERED ON 20.03.2026
RAILWAY PROJECTS IN RAJASTHAN
3333# SHRI RAJENDRA GEHLOT:
Will the Minister of RAILWAYS be pleased to state:
(a) the details of the pending railway projects and proposed new railway projects in Rajasthan;
(b) the project-wise details of the total amount to be spent on these projects; and
(c) whether any timeline has been set for completing these projects, if so, the project-wise details of the
said timeline?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (c): Railway Budget:
Budget allocation in the recent years has increased significantly. Budget allocation for infrastructure
projects and safety works, falling fully/partly in the State of Rajasthan is as under:-
Period Outlay
2009-14 ₹682 crore/year
2025-26 ₹9,960 crore (Nearly 15 times)
Track Construction:
The details of constructing new track falling fully/partly in the State of Rajasthan during 2009-14 and
2014-25 is as under:-
Period New Track Commissioned Average commissioning of new tracks
2009-14 798 Km 159.60 Km/year
2014-25 3,815 Km 346.82 Km/year (More than 2 times)
Project Sanctioned:
As on 01.04.2025, 28 projects (13 New Lines, 05 Gauge Conversion and 10 Doubling), covering a total
length of 3,409 Km, costing ₹43,918 crore, falling fully/partly in Rajasthan are sanctioned. The
summary is as under:-
…2/-
§-:2:-
Category No. of Total Length Length Commissioned Expenditure
projects (in Km) (in Km) (₹ in Cr)
New Lines 13 981 196 5769
Gauge Conversion 5 1252 788 6829
Doubling/
10 1176 254 6357
Multitracking
Total 28 3,409 1,238 18,954
Zone-wise/year-wise details of all Railway projects are made available in public domain on Indian
Railway’s website.
Recently completed projects:
Details of some of the recently completed projects falling fully/partly in the State of Rajasthan are as
under:
S.No. Name of Project Latest Cost
(₹ in crore)
1 Bangurgram-Ras New Line (28 km) 175
2 ThaiyatHamira-Sonu New Line (58 Km) 350
3 Suratpura- Sriganganagar Gauge Conversion (241 Km) 896
4 Sadulpur-Bikaner &Ratangarh-Degana Gauge Conversion (438 Km) 886
5 Jaipur -Churu & Sikar-Loharu Gauge Conversion (320 Km) 1105
6 Bhagat ki Kothi-Luni Doubling (28 Km) 128
7 Rani-Keshav Ganj Doubling (59 Km) 290
8 Guriya-Marwar &Karjoda-Palanpur Doubling (49 Km) 251
9 Rani-Marwar Doubling (52 Km) 346
10 Abu Road-Swaroop Ganj Doubling (26 Km) 195
11 Abu Road-Sarotra Road Doubling (24 Km) 152
12 Alwar-Bandikui Doubling (60 Km) 450
13 Ajmer-Bangurgram Doubling (48 Km) 375
14 Bangurgram-Guriya Patch Doubling (47 Km) 395
15 Degana-Rai ka Bagh Doubling (146 Km) 809
16 Bina-Kota Doubling (283 Km) 2476
…3/-
§-:3:-
17 Nimach-Chittaurgarh Doubling (56 Km) 560
18 Dausa-Gangapur City Doubling (93 Km) 950
19 Phulera-Degana Doubling (108 Km) 702
20 Churu-Ratangarh Doubling (43 Km) 423
Ongoing projects:
Some of the projects falling fully/partly in the State of Rajasthan which have been taken up are as
under:
S.No. Name of Project Cost
(₹ in crore)
1 Nimach-Badi Sadri New Line (48 Km) 495
2 Taranga Hill-Abu Road New Line (116 Km) 2798
3 Ramganjmandi-Bhopal New Line (277 Km) 5073
4 Pushkar-Merta New Line (51 Km) 800
5 Ringus-Khatu Shyam Ji New Line (17 Km) 254
6 Merta city-Ras New Line & Bye Pass at Merta Road Station 947
(56 Km)
7 Gwalior-Sheopurkalan Gauge Conversion with extension to Kota 2913
(284 Km)
8 Dholpur-Sirmuttra Gauge Conversion with extension to Gangapur 747
City (145 Km)
9 Mavli-DevgarhMadariya Gauge Conversion (83 Km) 969
10 Mathura-Jhansi 3rd Line (274 Km) 5924
11 Agra Fort-Bandikui Doubling (150 Km) 988
12 Sawaimadhopur-Jaipur Doubling (131 Km) 1204
13 Churu-Sadulpur& Luni-Bhildi Doubling (330 Km) 3554
14 Ajmer-Chanderiya Doubling (178 Km) 1635
15 Bye Pass line at Sawaimadhopur (14 Km) 304
16 Rewari-Khatuwas Doubling (28 Km) 352
17 Khatuwas-Narnaul Doubling (24 Km) 313
18 Bye Pass line at Marwar (4 Km) 71
19 Bypass line at Churu (5 Km) 63
20 Bypass line at Samdari (1 Km) 26
…4/-
§-:4:-
21 Ramdevra-Pokhran new line (13 Km) 189
22 Lalgarh-Bikaner East Cabin doubling (11 Km) 279
23 Ringas-Sikar Doubling (50 Km) 470
24 Umra-Debari Doubling (25 Km) 492
In last three years, 2022-23, 2023-24, 2024-25 and current financial year 2025-26, 59 surveys (25 new
line & 34 doubling) of total length 5,666 Km falling fully/partly in the State of Rajasthan have been
sanctioned.
Sanction of any railway project depends upon many parameters/factors which include the following:
Anticipated traffic projections and Remunerativeness of the proposed route
First and last mile connectivity provided by the project
Connection of missing links and providing additional route
Augmentation of congested/saturated lines
Demands raised by State Governments/Central Ministries/Public representatives,
Railway's own operational requirements
Socio-economic considerations
Overall availability of funds
Completion of Railway project/s depends on various factors which include the following:
Land acquisition by State Government
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
*****
§