GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
RAJYA SABHA
UNSTARRED QUESTION NO. 1718
ANSWERED ON 13.02.2026
RAILWAYS PROJECTS ON COST-SHARING BASIS
1718 SHRI ANIL KUMAR YADAV MANDADI:
Will the Minister of RAILWAYS be pleased to state:
(a) whether Government is implementing various projects in the country including Telangana on cost
sharing basis between State Government and Union Government;
(b) if so, the details thereof, project –wise;
(c) whether Government has identified challenges in implementing projects on cost-sharing basis
between State Government and Union Government; and
(d) if so, the details thereof and remedial measures, if any, that Government contemplates to resolve
those challenges?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (d): Capacity enhancement of railway network has been taken up by Indian Railways in a big
way during last 11 years. The details of commissioning/laying of new track across Indian Railways is
given below:-
Period New track Commissioned Average commissioning of new tracks
2009-14 7,599 Km 4.2 Km/day
2014-25 34,428 Km 8.6 Km/day (more than 2 times)
As on 01.04.2025, across Indian Railways, 431 Railway infrastructure projects (154 New Line, 33
Gauge Conversion and 244 Doubling) of total length 35,966 Km, costing approx. 6.75 lakh crore are
sanctioned. The summary is as under:-
§Total Length Length Commissioned
No of Total Exp upto Mar'25
Category NL/GC/DL till Mar'25
Projects ( in Cr)
(km) (Km)
New Lines 154 16,142 3,036 1,45,318
Gauge Conversion 33 4,180 2,997 22,753
Doubling /
244 15,644 6,736 1,22,858
Multitracking
Total 431 35,966 12,769 2,90,929
Zone-wise/year-wise details of all Railway projects are made available in public domain on Indian
Railway’s website.
68 Railway infrastructure projects have been undertaken through different cost-sharing arrangements.
However, in several such projects, delays have been experienced in release of the State Government’s
share of funds, adversely affecting project timelines.
In order to streamline and improve the cost sharing mechanism, a tri-partite agreement among the
Ministry of Railways, concerned State Government and Reserve Bank of India is being promoted.
Under this arrangement, a mandate would be created by the State Government enabling direct debit of
its share of cost due to Ministry of Railways, thereby ensuring timely and automatic transfer of funds.
Telangana
Budget allocation in the recent years has increased significantly. Budget allocation for infrastructure
projects and safety works, falling fully/partly in the State of Telangana is as under:
Period Outlay
2009-14 886 Cr./Yr.(including Andhra Pradesh)
2025-26 5,337 Cr.
The details of commissioning/laying of new track falling fully/partly in the State of Telangana during
2009-14 and 2014-25 is as under:
Period New Track Average Commissioning of new tracks
Commissioned
2009-14 87 Km 17.4 km/per year
2014-25 774 Km 70.4 km /per year (more than 4 times)
§Details of some of the completed projects falling fully/partly in the State of Telangana are as under:
Cost
S. No. Project
( in Crore)
1 Peddapalli- Nizamabad new line (178 Km) 926
2 Jaggayyapeta- Janpahad new line (48 Km) 737
3 Akkanapet – Medak new line (17 Km) 205
4 Bhadrachalam Road-Sattupalli new line (56 Km) 990
5 Raghavapuram-Mandamari Doubling (24 Km) 165
6 Raichur-Guntakal Doubling (81 Km) 388
7 Secunderabad- Mehboobnagar Doubling (85 Km) 1,266
8 Multi- Modal Transport System (MMTS) Phase-II, Hyderabad (103
1,156
Km)
9 Byepass line at Peddapalli (2 Km) 37
As on 01.04.2025, 20 Railway projects (6 New Lines and 14 Doubling), of a total length of 2,166 Km,
costing 35,045 crore falling fully/partly in the State of Telangana have been sanctioned, out of which,
548 Km length has been commissioned and an expenditure of 11,550 crore has been incurred upto
March, 2025. The summary is as under:-
Category No. of Total Length Length Total Exp. upto
projects (in Km) Commissioned till March, 2025
March, 2025 ( in Crore)
(in Km)
New Line 6 840 245 4,611
Doubling/Multi- 14 1,326 303 6,939
tracking
Total 20 2,166 548 11,550
Details of some of the projects falling fully/partly in the State of Telangana which have been sanctioned
are as under:
Cost
S.N Name of Project
( in Crore)
1 Manoharabad-Kothapalli new line (151 Km) 2,781
2 Malkangiri-Pandurangapuram new line (174 Km) 3,592
3 Kazipet -Vijaywada - 3rd line (220 Km) 3,315
4 Kazipet -Ballarshah - 3rd line (202 Km) 3,183
5 Guntur- Bibinagar Doubling(239 Km) 2,853
§Cost
S.N Name of Project
( in Crore)
6 Mudkhed - Medchal - Dhone Doubling (417 Km) 4,686
7 Bhadrachalam Road – Dornakal Doubling(55 Km) 770
8 Motumari-Vishnupuram doubling and RoR at Motumari (100 Km) 1,596
9 Nashkal (Pindial)-Hasanparthi Road bypass (25 Km) 465
10 Secunderabad (Sanathnagar)- Wadi 3rd and 4th line (173 Km) 5,012
11 Dornakal Rail over Rail (RoR) Flyover (11 Km) 327
Execution of important infrastructure projects falling fully/partly in the State of Telangana is held up
due to delay in land acquisition. Status of land acquisition in Telangana is as under:
Total Land required 2,343 Ha
Land Acquired 1,580 Ha (67%)
Balance Land to be acquired 764 Ha (33%)
Details of some major projects which are delayed due to land acquisition are as under:-
SN Name of the project Total land Land Balance Land Amount Paid
required acquired to be acquired to State
(Ha) (Ha) (Ha) ( in Crore)
1. Guntur- Bibinagar Doubling 31 0 31 40
2. Mudkhed – Medchal & 70 0 70 30
Mahbubnagar – Dhone Doubling
3. Kazipet-Vijaywada 3rd Line 135 118 17 159
4. Manoharabad – Kothapalli New 1,146 1,050 96 -
Line
04 projects in Telangana have been sanctioned on cost sharing basis at a cost of 4,704 Crore. As on
01.04.2025, share of Telangana Government in these projects is 2,181 Cr. Telangana had to deposit
1,708 Crore to Ministry of Railways for these cost sharing projects. However they have deposited only
894 Crore. Thus there is a shortfall of 814 Crore which is adversely affecting progress of works. The
details of projects taken up on cost sharing basis is as under:-
§S Project Cost Cost sharing Expenditure State Amount Outstanding Remarks
N Name ( in Arrangement upto March, Share deposited ( in Cr.)
Cr.) 2025 till till
( in Cr.) March, March,25
2025 ( in Cr.)
( in
Cr.)
1 Hyderabad 1,306 Govt of 1,225 821 379 442 Progress of
- Telangana- works adversely
Secunderab 67% affected due to
ad - Multi Railways- non-deposition
modal 33% of State
transport Government
system (82 share
km)
2 Ghatkesar- 412 Govt of 0.03 0.02 0 0.02 Progress of
Raigir Telangana- works adversely
(Yadadri) 67% affected due to
Extn. of Railways- non-deposition
MMTS 33% of State
Government
share
3 Akanapet- 205 Govt. of 212 106 99 7 Project
Medak Telangana - completed and
New line (50% of commissioned.
(17 km) Cost) +
land free
Railways -
(50% of
Cost)
4 Manoharaba 278 Govt. of 1,562 781 416 365 Manoharabad to
d-Kothapalli Telangana- Siddipet, (76
New line (1/3 of km)
(151 km) Cost) + commissioned.
land free There are
+Free significant
Annuity for delays in
first 05 handing over of
years. land and sharing
Railways - of project cost
(2/3 of by Government
Cost of Telangana.
excluding This has
land) adversely
affected the
execution of this
project.
Total 4,704 3,000 1,708 894 814
§Completion of Railway project/s depends on various factors which include the following:
Land acquisition by State Government
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
*****
§