GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 659
TO BE ANSWERED ON 22.07.2026
RAJPURA - MOHALI RAILWAY PROJECT
659. SHRI GURMEET SINGH MEET HAYER:
Will the Minister of RAILWAYS be pleased to state:
(a) the details of the current status, financial outlay and completion
timeline of the approved Rajpura-Mohali railway line project;
(b) the details of the section-wise maximum permissible speed limit from
Bathinda to Chandigarh via new track and plans to upgrade the tracks
to increase train speeds on this route;
(c) whether trains coming from the Malwa region require an engine reversal
at Rajpura Junction to reach Mohali and if so, the details thereof;
(d) whether the feasibility of a crossing with the Ambala-Sirhind via grade-
separated crossing track was studied and if so, the details thereof;
(e) whether new trains are planned from Delhi to Chandigarh via this new
route with a stop at Mohali and if so, the details thereof; and
(f) whether any new stations, logistics hubs or dry ports are planned along
this new track to boost local trade and if so, the details thereof?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (f) : Rajpura – Mohali new line project (18 Km) has been sanctioned
recently at a cost of Rs. 443 crore. This project will directly connect
Southern Punjab (Bathinda area), between Sirhind – Gobindgarh and
Rajpura area to Chandigarh avoiding Ambala. Land acquisition has been
taken up. The project has been declared as special Railway Project. Total
73 Ha of land is required for the project. Preliminary notification for land
§ Page 1 of 11acquisition has been issued. An outlay of Rs. 100 crore has been allocated
for this project in FY 2026-27.
This new Railway line connecting Rajpura to Sahibzada Ajit Singh Nagar
(Mohali) is set to transform regional connectivity by seamlessly linking
major hubs like Rajpura Junction, Sarai Banjara and Sahibzada Ajit Singh
Nagar (Mohali). This project addresses a long-standing demand of the
people of Punjab’s Malwa region for shorter and more direct rail
connectivity to the state capital. This project will provide a boost to local
economy.
The speed potential of Bathinda - Rajpura route has been upgraded to 110
kmph.
Further, strengthening, upgradation, modernisation and improvement of
track infrastructure is a continuous and ongoing process over Indian
Railways. The following measures are being taken by Indian Railways to
upgrade railway tracks:
i. Modern track structure consisting of 60kg, 90 Ultimate Tensile
Strength (UTS) rails, Wider and heavier Pre-stressed Concrete Sleepers
(PSC) with elastic fastening, fan-shaped layout turnout on PSC
sleepers and H-beam Sleepers on girder bridges are being used while
carrying out primary track renewals.
ii. The Thick Web Switches and Weldable CMS Crossings are being used
in turnout renewal works.
iii. Supply of 260m long rail panels have been increased to avoid welding
of joints, thereby improving safety and riding quality
iv. Thick Web Switch Expansion Joints are being used in place of earlier
Conventional/Improved SEJs.
v. Adoption of better welding technology for rails i.e. Flash Butt Welding.
Page 2 of 11vi. Adoption of mechanized system for track maintenance using high
output plain tampers and points & crossing tampers for improved
maintainability & reliability of track.
vii. Deployment of state-of-the-art modern machines including Rail
Grinding Machines to further improve asset reliability.
viii. Mechanisation of track laying activities through use of track machines
like PQRS, TRT, T-28 etc.
ix. Interlocking of Level Crossing (LC) Gates for enhancing safety at LC
gates.
x. Use of advanced Phased Array technology of testing of rail and welds.
xi. Deployment of Integrated Track Monitoring Systems (ITMS) and
Oscillation Monitoring System (OMS) for comprehensive health
assessment to ascertain optimal maintenance requirements.
xii. Adoption of portable Track Measuring Trolley for continuous recording
of track parameters in yards.
xiii. Using web enabled Track Management System (TMS) for integration
and data analytics of the track inspection records received through
various sources to enable precise maintenance inputs.
As a result of above measures, there has been significant increase in
speed potential of the tracks. The details of speed potential of railway
tracks during 2014 vis-a-vis 2026 are as under:
2014 2026
Sectional Speed
(kmph)
Track Km % Track Km %
130 & above 5,036 6.3 24,173 22.5
110 - 130 26,409 33.3 62,482 58.1
< 110 47,897 60.4 20,897 19.4
Total 79,342 100 1,07,552 100
Page 3 of 11Punjab:
Railway Budget:
Budget allocation for Infrastructure projects and safety works, falling
fully/partly in the Punjab is as under:
Period Outlay
2009-14 ₹225 crore/year
2026-27 ₹ 5,673 Cr. (More than 25 times)
Projects Sanctioned:
As on 01.04.2026, 11 projects (06 new line and 05 doubling) of total length
745 Km, costing Rs.24,708 crore, falling fully/partly in the Punjab including
Fatehgarh Sahib are sanctioned. The summary is as under:-
Category No. of Total Length Expenditure upto
project Length Commissi March 2025
s oned (Rs.in Crore)
New line 06 283 Km 75 Km 9,246
Doubling
/multitrack 05 462 Km 80 Km 1,631
ing
Total 11 745 Km 155 Km 10,878
Recently Completed Projects:
Details of some of the recently completed projects falling fully/partly in the
Punjab are as under:
S. Cost
Project
No. (Rs. in Cr.)
1 Chakki Bank-Bharoli Doubling (3 Km) 15
2 Jakhal- Mansa Doubling (45 Km) 163
3 Mirthal-Bhangala Beas River Doubling (3 Km) 74
Page 4 of 114 Ambala-Dhapper-Chandigarh Doubling (45 Km) 339
5 Mansa – Bhatinda Doubling (49 Km) 216
6 Amritsar - Chheharta Doubling (7 Km) 31
Jallandhar-Pathankot-Jammu Tawi Doubling (209 850
7
km)
Kathua-Madhopur Punjab - doubling including 257
8
Bridge on Ravi (3 Km)
9 Rajpura-Bhatinda Doubling (173 Km) 2,459
Ongoing Projects:
Some of the projects falling fully/partly in the Punjab including Fatehgarh
Sahib which have been taken up are as under:
SN. Project Cost
(Rs. in
Cr.)
1 Nangal Dam-Talwara - Mukerian New line (123 Km) 3,726
2 Bhanupalli-Bilaspur-Beri New Line(63 Km) 13,770
3 Qadian-Beas New Line(40 km) 842
4 Ferozpur-Patti New Line (26 Km) 764
5 Rama Mandi( Raman)-Maur Mandi(Maur) via 154
Talwandi Sabo ( 29 km) New Line
6 Ludhiana-Kila Raipur doubling (19 Km) 260
7 Ludhiana-Mullanpur doubling (21 Km) 359
8 Rajpura-Mohali New Line (18 km) 443
9 Rajpura Bypass line (14 km) 412
Page 5 of 11Details of some major projects which are delayed due to land acquisition are
as under: -
SN Name of the project Total land Land Balance Land to
required acquired be acquired
(in Ha) (in Ha) (in Ha)
1 Firozpur-Patti new line 166 0 166
2 Alal-Himmatana Chord 20 0 20
line
3 Qadian-Beas New Line 167 0 167
4 Rama Mandi( Raman)- 192 0 192
Talwandi Sabo New Line
Details of Projects delayed on account of State Govt:
Firozpur-Patti New line (26 km):
Firozpur-Patti New line (26 km) situated fully in Punjab is an important
project near the international border. This project was sanctioned in the
year 2017-18 at a cost of Rs.300 crore.
Land for this project was to be handed over free of cost by State
Government of Punjab. However, land acquisition was not done by State
Government. Total 166 Ha land is to be acquired in the districts of Firozpur
and Tarn Taran.
Considering importance of this project on strategic consideration, it has
been decided to take up this new line project at Central Government cost
including land acquisition. Now, Land acquisition is in advanced stage and
Award has been declared.
Page 6 of 11Rama Mandi-Sadda Singhwala New Line via Talwandi Sabo (43 km):
To provide direct rail connectivity to Talwandi Sabo, the work of new rail
line between Rama Mandi to Sadda Singhwala via Talwandi Sabo was
sanctioned at an estimated cost of Rs. 231 Crore.
Land for this project was to be handed over free of cost by State
Government of Punjab. However, land acquisition was not started by State
Government of Punjab even after passage of several years .
Considering importance of this project for providing direct connectivity to
Takht Shri Damdama Sahib at Talwandi Sabo, it has been decided to take
up this new line project at Central Government cost including land
acquisition.
The project has been declared as special Railway Project and land
acquisition has been taken up. Competent Authority for Land Acquisition
(CALA) has also been nominated for taking up land acquisition.
Qadian – Beas New line (40 km):
Qadian-Beas (40 Km) New Rail Line Project was sanctioned in 2011-12.
However, the project could not be taken forward due to law and order
issues. The project was then kept in abeyance. However, considering
importance of this project, it has been decided to take up the work again.
The project has been declared as special Railway Project.
Government of India is geared up to execute projects, however success
depends upon the support of Government of Punjab.
Page 7 of 11Completion of Railway project/s depends on various factors which include
the following:
Land acquisition by State Government
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s
Train Services:
At Present, there is no direct rail link between Rajpura and Sahibzada Ajeet
Singh Nagar (Mohali). Further, no direct passenger train services are
available from Bathinda, Patiala and Ludhiana to directly connect
Sahibzada Ajeet Singh Nagar (Mohali) via Rajpura. The direct route from
Ludhiana to Mohali is via Sanehwal with no engine reversal. However,
presently goods train movement is done from Dhuri/Bathinda to Sirhind side
by engine reversal at Rajpura.
The direct route from Delhi to Chandigarh is via Ambala Cantt. without
passing through Sahibzada Ajeet Singh Nagar (Mohali). The new proposed
route can provide additional means of connectivity to Chandigarh via
Sahibzada Ajeet Singh Nagar (Mohali).
Presently, Chandigarh - Delhi sector is served by 21 pairs of trains as listed
below:-
SN Train No. and Name
1 14217/14218 Prayagraj Sangam - Chandigarh Express
Page 8 of 112 12217/12218 Thiruvananthapuram North - Chandigarh Express
3 22447/22448 New Delhi - Amb Andaura Vande Bharat Express
4 22455/22456 Sainagar Shirdi - Kalka Express
5 12011/12012 New Delhi - Kalka Shatabdi Express
6 22451/22452 Bandra (T)- Chandigarh Express
7 22685/22686 Yesvantpur - Chandigarh Express
8 20977/20978 Ajmer - Chandigarh Vande Bharat Express
9 12449/12450 Madgaon Junction - Chandigarh Express
10 14331/14332 Delhi - Kalka Express
11 12005/12006 New Delhi - Kalka Shatabdi Express
12 12045/12046 New Delhi - Chandigarh Shatabdi Express
13 13051/13052 Howrah - Kalka Express
14 18101/18102 Tatanagar - Jammu Tawi Express
15 18309/18310 Sambalpur - Jammu Tawi Express
16 20493/20494 Madurai - Chandigarh Express
17 11905/11906 Agra Cantt - Hoshiarpur Express
18 12925/12926 Bandra (T)- Amritsar Express
19 22709/22710 Nanded - Amb Andaura Express
20 12057/12058 New Delhi - Daulatpur Chowk Jan Shatabdi
Express
21 19307/19308 Indore - Una Himachal Express
Page 9 of 11Similarly, Mohali - Delhi sector is served by 04 pairs of trains as under:-
SN Train No. and Name
1 12925/12926 Bandra Terminus - Amritsar Express
2 22709/22710 Nanded - Amb Andaura Express
3 12057/12058 New Delhi - Daulatpur Chowk Jan Shatabdi
Express
4 19307/19308 Indore - Una Himachal Express
Likewise, Mohali - Chandigarh sector is served by 28 train services, as
under:-
SN Train No. and Name
1 12057/12058 New Delhi - Daulatpur Chowk Jan Shatabdi
Express
2 12411/12412 Chandigarh - Amritsar Express
3 12925/12926 Bandra (T) - Amritsar Express
4 14503/14504 Kalka - Shri Mata Vaishno Devi Katra Express
5 14541/14542 Chandigarh - Amritsar Express
6 14609/14610 Yog Nagari Rishikesh - Shri Mata Vaishno Devi
Katra Express
7 14615/14616 Lalkua - Amritsar Express
8 19307/19308 Indore - Una Himachal Express
9 14629/14630 Chandigarh - Firozpur Cant Express
Page 10 of 1110 19411/19412 Gandhinagar Capital - Daulatpur Chowk
Express
11 22709/22710 Nanded - Amb Andaura Express
12 64563/64564 Raipur Hariyana - Amb Andaura MEMU
13 74991/74992 Ambala Cantt - Daulatpur Chowk DMU
14 64516 Nangal Dam - Ambala Cantt MEMU
15 74645 Ambala Cantt - Jalandhar City DMU
Introduction of new train services, which is an on-going process, depends
on various factors which include-
● Capacity of that section
● Availability of path
● Availability of required rolling stock
● Availability of matching infrastructure for rolling stock
● Maintenance requirement of railway tracks and other assets.
● Occupancy and the traffic requirement of the section
*****
Page 11 of 11