See Full Document Text
O.I.H
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
RAJYA SABHA
UNSTARRED QUESTION NO. 2502
ANSWERED ON 13.03.2026
RECRUITMENT AGAINST SANCTIONED AND VACANT POSTS IN INDIAN RAILWAYS
2502# DR. SANDEEP KUMAR PATHAK:
Will the Minister of RAILWAYS be pleased to state:
(a) the total number of sanctioned posts in Indian Railways at present and the number of posts lying
vacant against those posts, the category-wise details thereof;
(b) the number of vacancies specifically in Loco Pilot, Guard, Track Maintainer and other technical
categories, the zone-wise/State-wise details thereof;
(c) whether these vacancies have impacted punctuality of trains, operational efficiency and passenger
safety, if so, the assessment thereof; and
(d) the number of recruitments made by the Railways in the last three years and the details of the time-
bound recruitment calendar prepared for the next two years?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (d): Recruitment done in Indian Railways during 2004-05 to 2013-14 vis-à-vis during 2014-15 to
2025-26 is given as under: -
Period Recruitments
2004-2005 to 2013-2014 4.11 lakh
2014-2015 to 2024-2025 5.08 lakh
2025-26 till date 41,343
Occurrence and filling up of vacancies are continuous processes on Indian Railways considering its
size, spatial distribution and criticality of operation. Adequate and suitable manpower is provided to
cater to the regular operations, changes in technology, mechanisations and innovative practices. The
vacancies are filled up primarily by placement of indents by Railways with Recruitment agencies as per
operational and technological requirements.
The RRB examinations are quite technical in nature entailing large scale mobilization of men and
resources and training of manpower. Railway overcame all these challenges and successfully conducted
the recruitment in a transparent manner following all laid down guidelines. No instance of paper
leakage or similar malpractice has occurred during the entire process.
§Further, as system improvement, the Ministry of Railways has introduced a system of publishing the
annual calendar from 2024 for recruitment to various categories of Group ‘C’ posts. The introduction of
the annual calendar is benefitting the aspirants in the following manner:
•More opportunities for candidates;
•Opportunities to those becoming eligible every year;
•Certainty of exams;
•Faster Recruitment process, Training and Appointments
Presently, recruitment against 1,43,086 vacancies of non-gazetted personnel has been taken up on
Indian Railways as per Annual Calendar 2024 and 2025.
During January to December 2024, ten Centralized Employment Notifications (CENs) for 92,116
vacancies were notified for filling up of posts of Assistant Loco Pilots (ALPs), Technicians, Sub-
Inspectors, Constables in Railway Protection Force (RPF), Junior Engineers (JEs)/ Depot Material
Superintendent (DMS)/ Chemical & Metallurgical Assistant (CMA), Paramedical Categories, Non-
Technical Popular Categories (Graduate), Non-Technical Popular Categories (Under-Graduate),
Ministerial & Isolated Categories and Level-1 categories such as Assistants, Track Maintainers
and Pointsman.
First stage/Single stage Computer Based Tests (CBTs) for 92,116 posts have been completed. Details
are as under: -
Exam Candidates Cities Languages
1st Stage CBT for the post of ALP (18,799 vacancies) 18,40,347 156 15
CBT for the post of Technician (14,298 vacancies) 26,99,892 139 15
1st Stage CBT for the post of JE/DMS/CMA 11,01,266 146 15
(7,951 vacancies)
CBT for the post of RPF-SI (452 vacancies) 15,35,635 143 15
CBT for the post of RPF-Constable (4,208 vacancies) 45,30,288 147 15
CBT for Paramedical Categories (1,376 vacancies) 7,08,321 143 15
1st Stage CBT for Non-Technical Popular Categories 58,41,774 141 15
(Graduate) (8,113 vacancies)
1st Stage CBT for Non-Technical Popular Categories (Under 63,27,473 157 15
Graduate) (3,445 vacancies)
§CBT for Ministerial & Isolated categories 4,46,013 139 15
(1,036 vacancies)
CBT for level-1 post (32,438 vacancies) 1,08,28,261 152 15
Total Candidates 3,58,59,270
2nd stage CBTs for the posts of ALP, JE/DMS/CMA and Non-Technical Popular Categories (Graduate
& Under-Graduate) have also been completed. Details are as under: -
Exam Candidates Cities Languages
2nd Stage CBT for the post of ALP 2,66,363 112 15
(18,799 vacancies)
2nd Stage CBT for the post of JE/DMS/CMA 1,17,339 118 15
(7,951 vacancies)
2nd Stage CBT for Non-Technical Popular Categories 1,21,931 129 15
(Graduate) (8,113 vacancies)
2nd Stage CBT for Non-Technical Popular Categories 51,978 79 15
(Under-Graduate) (3,445 vacancies)
Total Candidates 5,57,611
Computer Based Aptitude Test (CBAT) for the post of ALP and Non-Technical Popular Categories
(Graduate) and Computer based Skill Test for the post of Non-Technical Popular Categories (Graduate
and Under Graduate) and Ministerial & Isolated Categories have also been completed. Details are
as under: -
Exam Candidates Cities Languages
CBAT for the post of ALP 1,32,044 84 2
Translation Test for Ministerial and Isolated 1,233 8 2
Categories
CBAT for the post of Non-Technical Popular 13,616 38 2
Categories (Graduate)
Computer Based Typing Skill Test (CBTST) for the 30,341 58 2
post of Non-Technical Popular Categories
(Graduate-level)
Computer Based Typing Skill Test (CBTST) for the 13,145 44 2
post of Non-Technical Popular Categories (Under-
Graduate-level)
Total Candidates 1,90,379
§Panels for more than 41,000 candidates for various posts including the posts of Technicians, Junior
Engineers, Paramedical Categories, Sub-Inspectors & Constable (RPF) and Assistant Loco Pilots have
been finalised. Majority of them are in safety categories.
In addition, as per Annual Calendar for the year 2025, nine Centralized Employment Notifications
(CENs) for 50,970 vacancies have also been issued. Details are as under: -
CEN No. Post Name No. of Vacancies Month
notified of Notification
01/2025 Assistant Loco Pilots 9,970 March 2025
02/2025 Technician 6,238 June 2025
03/2025 Paramedical categories 434 July 2025
04/2025 Section Controller 368 August 2025
Junior Engineer/ Depot 2,585 October 2025
05/2025 Material Superintendent
Non-Technical Popular 5,810 October 2025
06/2025 Categories (Graduate)
Non-Technical Popular 3,058 October 2025
07/2025 Categories (Under-Graduate)
08/2025 Isolated Categories 312 December 2025
09/2025 Level-1 22,195 December 2025
First stage/Single stage Computer Based Tests (CBTs) for 2,953 posts have been completed. Details
are as under: -
Exam Candidates Cities Languages
CBT for the post of Section Controller (368 vacancies) 4,33,748 131 15
5,74,351 133 15
1st Stage CBT for the post of JE/DMS (2585 vacancies)
10,08,099
Total Candidates
Safety
Safety is accorded the highest priority on Indian Railways. As a consequence of various safety
measures taken over the years, there has been a steep decline in the number of accidents.
§Number of Consequential Train Accidents has reduced as shown in the table below:-
Year Consequential Accidents
2014-15 135
2025-26 (upto 28.02.2026) 14 (90% lesser)
Another important index showing improvement in safety in train operations is Consequential Accident
Index, the details of which are as under:-
Consequential Accident Index:-
Year Accident Index
2014-15 0.11
2024-25 0.03 (73% lesser)
This index measures number of consequential accidents as a ratio of total running kilometers of all
trains.
Accident Index =
234
165
135
55
31
14
2005-06 2009-10 2014-15 2019-20 2024-25 2025-26
(Feb 2026)
The various safety measures taken to enhance safety in train operations are as under:-
1. On Indian Railways, the expenditure on Safety related activities has increased over the years as
under:-
Expenditure/Budget on Safety related activities (Rs. in Cr.)
2013-14 2022-23 2023-24 2024-25 2025-26 2026-27
39,200 87,336 1,01,662 1,14,022 1,17,693 1,20,389
stnediccA
niarT
laitneuqesnoC
fo
.oN
No. of consequential accidents
No. of trains X million kilometers run2. Electrical/Electronic Interlocking Systems with centralized operation of points and signals have
been provided at 6,665 stations up to 28.02.2026 to reduce accidents due to human failure.
3. Interlocking of Level Crossing (LC) Gates has been provided at 10,153 Level Crossing Gates up to
28.02.2026 for enhancing safety at LC Gates.
4. Complete Track Circuiting of stations to enhance safety by verification of track occupancy by
electrical means has been provided at 6,669 stations up to 28.02.2026.
5. Indian Railways has gone for implementation of indigenously developed Automatic Train
Protection (ATP) system, which required safety certification of highest order (SIL 4). Kavach has
been adopted as a National ATP system in July 2020. Based on deployment of Kavach version 3.2
on 1465 RKm on South Central Railway and experience gained, further improvements were made.
Finally, Kavach specification version 4.0 was approved by RDSO on 16.07.2024. After extensive
and elaborate trials, Kavach Version 4.0 has been successfully commissioned on 1,452 Route
Kilometres, covering the high density Delhi-Mumbai and Delhi-Howrah routes as below:
SN Section Progress Route (Km)
(1) Delhi-Mumbai route:
i Junction cabin – Palwal – Mathura –Nagda section 667
ii Vadodara - Ahmedabad section 96
iii Vadodara - Virar section 336
(2) Delhi – Howrah route:
i Gaya Sarmatanr section 93
ii Chota Ambana - Bardhaman – Howrah section 260
Further, track side Kavach implementation work has been taken up on 24,427 RKM covering all
GQ, GD, HDN and identified sections of Indian Railways.
6. Detailed instructions on issues related with safety of Signalling, e.g. mandatory correspondence
check, alteration work protocol, preparation of completion drawing, etc. have been issued.
7. System of disconnection and reconnection for S&T equipment as per protocol has been re-
emphasized.
8. All locomotives are equipped with Vigilance Control Devices (VCD) to improve alertness of Loco
Pilots.
9. Retro-reflective sigma boards are provided on the mast which is located two OHE masts prior to
the signals in electrified territories to alert the crew about the signal ahead when visibility is low
due to foggy weather.
10. A GPS based Fog Safety Device (FSD) is provided to loco pilots in fog affected areas which
enables loco pilots to know the distance of the approaching landmarks like signals, level crossing
gates, etc.
§11. Modern track structure consisting of 60kg, 90 Ultimate Tensile Strength (UTS) rails, Pre-stressed
Concrete Sleeper (PSC) Normal/Wide base sleepers with elastic fastening, fan shaped layout
turnout on PSC sleepers, Steel Channel/H-beam Sleepers on girder bridges is used while carrying
out primary track renewals.
12. Mechanisation of track laying activity through use of track machines like PQRS, TRT, T-28 etc. to
reduce human errors.
13. Maximizing supply of 130m/260m long rail panels for increasing progress of rail renewal and
avoiding welding of joints, thereby improving safety.
14. Ultrasonic Flaw Detection (USFD) testing of rails to detect flaws and timely removal of defective
rails.
15. Laying of longer rails, minimizing the use of Alumino Thermic Welding and adoption of better
welding technology for rails i.e., Flash Butt Welding.
16. Monitoring of track geometry by OMS (Oscillation Monitoring System) and TRC (Track
Recording Cars).
17. Patrolling of railway tracks to look out for weld/rail fractures.
18. The use of Thick Web Switches and Weldable CMS Crossing in turnout renewal works.
19. Inspections at regular intervals are carried out to monitor and educate staff for observance of safe
practices.
20. Web based online monitoring system of track assets viz. Track database and decision support
system has been adopted to decide rationalized maintenance requirement and optimize inputs.
21. Detailed instructions on issues related with safety of Track, e.g. integrated block, corridor block,
worksite safety, monsoon precautions, etc. have been issued.
22. Preventive maintenance of railway assets (Coaches & Wagons) is undertaken to ensure safe train
operations.
23. Replacement of conventional ICF design coaches with LHB design coaches is being done.
24. All unmanned level crossings (UMLCs) on Broad Gauge (BG) route have been eliminated by
January 2019.
25. Safety of Railway Bridges is ensured through regular inspection of Bridges. The requirement of
repair/rehabilitation of Bridges is taken up based upon the conditions assessed during these
inspections.
26. Indian Railways has displayed Statutory “Fire Notices” for widespread passenger information in
all coaches. Fire posters are provided in every coach so as to educate and alert passengers
regarding various Do’s and Don’ts to prevent fire. These include messages regarding not carrying
any inflammable material, explosives, prohibition of smoking inside the coaches, penalties etc.
27. Production Units are providing Fire detection and suppression system in newly manufactured
Power Cars and Pantry Cars, Fire and Smoke detection system in newly manufactured coaches.
§Progressive fitment of the same in existing coaches is also underway by Zonal Railways in a
phased manner.
28. Regular counselling and training of staff is undertaken.
29. Concept of Rolling Block introduced in Indian Railways (Open Lines) General Rules vide Gazette
notification dated 30.11.2023, wherein work of integrated maintenance/ repair/replacement of
assets is planned up to 52 weeks in advance on rolling basis and executed as per plan.
The details of the Safety related works related to better maintenance practices, Technological
improvements, better infrastructure and rolling stock etc. undertaken by Railways are tabulated below:-
2004-05 to 2014-15 to 2024- 2014-25 Vs.
S.N. Item
2013-14 25 2004-14
Technological Improvements
1. Use of high-quality rails 57,450 Km 1.43 Lakh Km More than 2
(60 Kg) (Km) times
2. Longer Rail Panels 9,917 Km 77,522 Km Nearly 8 times
(260m) (Km)
3. Electronic Interlocking (Stations) 837 Stations 3,691 Stations More than 4
times
4. Fog Pass Safety Devices (Nos.) As on 31.03.14: As on 31.03.25: 288 times
90 Nos. 25,939 Nos.
5. Thick Web Switches (Nos.) Nil 28,301 Nos.
Better Maintenance Practices
1. Primary Rail Renewal (Track Km) 32,260 Km 49,941 Km 1.5 times
2. USFD (Ultra Sonic Flaw detection) 79.43 Lakh 2 Crore More than 2
Testing of Welds (Nos.) times
3. Weld failures (Nos.) In 2013-14: 3699 In 2024-25: 90 % reduction
Nos. 370 Nos.
4. Rail fractures (Nos.) In 2013-14: 2548 In 2024-25: More than 88%
Nos. 289 Nos. reduction
Better Infrastructure and Rolling Stock
1. New Track KM added (Track Km) 14,985 Km 34,428 Km More than 2
times
2. Flyovers (RoBs) / Underpasses 4,148 Nos. 13,808 Nos. More than 3
(RUBs) (Nos.) times
3. Unmanned Level crossings As on 31.03.14: As on Removed
(Nos.) on BG 8,948 31.03.24:Nil
(All eliminated
by 31.01.19)
4. Manufacture of LHB Coaches 2,337 Nos. 42,677 More than 18
(Nos.) times
*****
§