Executive Summary:
The Ministry of Railways responded to questions regarding the redevelopment of Chandigarh Railway Station under the Amrit Bharat Station Scheme. The redevelopment is underway with a sanctioned cost of ₹436.29 Crores. While improvements to amenities and cleanliness are being made, a specific completion timeframe cannot be provided due to the complexity of the project and required clearances.
Key Points / Main Content:
* **Chandigarh Railway Station Redevelopment:**
* The station is being redeveloped under the Amrit Bharat Station Scheme.
* The estimated cost of the redevelopment project is ₹436.29 Crores.
* Structural works for the station building on both the Panchkula and Chandigarh sides are complete.
* Work is in progress on the air concourse, foot over bridge, parking, platform upgrades (including shelters), and station building finishes.
* Redevelopment work is being carried out with minimal impact on station operations.
* **Amrit Bharat Station Scheme:**
* 1337 stations have been identified for development under the scheme, including Chandigarh.
* Phase I work has been completed for 105 stations (list of stations provided in original document).
* The scheme involves phased implementation of master plans for station improvements, including access, waiting areas, amenities for Divyangjans, and integration with the city.
* Funding is allocated under Plan Head-53 Customer Amenities, with ₹2216 crores allocated to the Northern Railway zone for the financial year 2025-26.
* **Project Challenges and Timelines:**
* The redevelopment is complex due to safety requirements, necessary clearances, and brownfield challenges (shifting utilities, etc.).
* No specific completion timeframe can be indicated due to these factors.
* **Hygiene and Crowd Management:**
* Efforts are being made to maintain cleanliness and hygiene during redevelopment.
* Passenger facilities are being maintained in hygienic condition.
* Frequent inspections are conducted by officials to ensure cleanliness.
* Measures are in place to regulate platform rush and prevent incidents, including queue systems, CCTV monitoring, deployment of staff, and coordination with police.
* **Monitoring and Audits:**
* Indian Railways has mechanisms for project monitoring, including reviews, inspections, feedback, quality checks, and audits.
* Works are carried out adhering to established standards and specifications.
Impact Analysis
* **Passengers:**
* *Impact:* Passengers will experience improved amenities, station access, and overall cleanliness at Chandigarh Railway Station, as well as other stations being redeveloped under the Amrit Bharat Station Scheme. However, they may also face temporary disruptions during the redevelopment process.
* *Action Required:* Passengers should be aware of potential disruptions and plan their travel accordingly. They can also provide feedback through available channels to help monitor the quality of work.
* **Railway Authorities (including Northern Railway):**
* *Impact:* Responsible for overseeing and managing the redevelopment project at Chandigarh Railway Station and other stations within their jurisdiction. They must ensure adherence to standards, manage project challenges, and minimize disruptions.
* *Action Required:* Continue to monitor the progress of the redevelopment work, address any challenges that arise, and ensure that passenger safety and convenience are prioritized. Adhere to established monitoring and auditing mechanisms.
* **Government of India (Ministry of Railways):**
* *Impact:* Responsible for the overall success of the Amrit Bharat Station Scheme and the effective utilization of funds allocated for station redevelopment.
* *Action Required:* Continue to monitor the progress of the scheme, address any systemic issues that arise, and ensure that the objectives of the scheme are being met.
Key Entities Referenced
Chandigarh Railway Station: A railway station located in Chandigarh, India, which is the subject of a redevelopment project.
Amrit Bharat Station Scheme: A scheme under which Chandigarh Railway Station is being redeveloped and aims to develop stations continuously with long-term approach.
SHRI ASHWINI VAISHNAW: Minister of Railways, Information Broadcasting and Electronics Information Technology.
Panchkula: A city in Haryana, India, where structural works for the station building are being carried out.
Northern Railway: The Zonal Railway under whose jurisdiction Chandigarh railway station falls.
Plan Head-53 Customer Amenities: The plan head under which development/upgradation of stations including under Amrit Bharat Station Scheme is generally funded.
State Level Security Committee of Railways: Committees constituted for all States/Union Territories under the Chairmanship of respective Director General of Police/Commissioner of States/Union Territories for regular monitoring and review of security arrangements of the Railways
Ayodhya Dham: One of the stations where Phase-I work has been completed under Amrit Bharat Station Scheme
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 2847
TO BE ANSWERED ON 06.08.2025
REDEVELOPMENT OF CHANDIGARH RAILWAY STATION
UNDER ABS SCHEME
2847. SHRI MANISH TEWARI :
Will the Minister of RAILWAYS be pleased to state:
(a) whether Chandigarh Railway Station is being redeveloped under the
Amrit Bharat Station Scheme;
(b) if so, the total estimated cost and timeline of the redevelopment
project, along with the percentage of work completed so far;
(c) whether the Government is aware of reports regarding poor hygiene,
inadequate basic amenities and persistent crowding at the station
despite the ongoing redevelopment;
(d) if so, the steps taken/proposed to be taken to improve sanitation,
passenger facilities and crowd management at the station during and
after the redevelopment process;
(e) whether any third-party or citizen feedback mechanisms are being
used to monitor the quality and progress of the redevelopment work, if
so, the details thereof; and
(f) whether any audit/review has been conducted of similar railway
station redevelopment projects across the country and , if so, the
details thereof?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (f): Chandigarh railway station has been identified for
development under Amrit Bharat Station Scheme. Redevelopment
..2/--2-
work of Chandigarh railway station has been sanctioned at an
estimated cost of ₹436.29 Crores.
The work for redevelopment of Chandigarh has progressed well and
the structural works for station building at Panchkula side and
Chandigarh side have been completed. The works of air concourse,
foot over bridge, parking, platform upgradation including platform
shelters, finishes of station building etc have been taken up. The
station redevelopment works are being taken up with minimum effect
on the station operation.
So far, 1337 stations have been identified for development under
Amrit Bharat Station Scheme including Chandigarh railway stations.
Presently Phase-I work of 105 stations have been completed. The
names of these stations are given below:
Ambikapur, Amgaon, Ayodhya Dham, Bagalkot, Baijnath Paprola,
Balrampur, Bareilly City, Begumpet, Bhanupratappur, Bhilai, Bijnor,
Bundi, Chanda Fort, Chidambaram, Chinchpokli, Chirayinkeezh,
Cuttack, Dakor, Derol, Deshnoke, Devlali, Dharwad, Dhule,
Dongargarh, Fatehabad, Fatehpur Shekhawati, Gadag, Gogameri,
Gokak Road, Gola Gokarnath, Gomti Nagar, Govardhan, Govind Garh,
Govindpuri, Govindpur Road, Haibargaon, Hathras City, Hapa, Idgah
Agra Jn., Izzatnagar, Jam Jodhpur, Jam Wanthali, Joychandi Pahar,
Kalyani Ghoshpara, Kanalus Jn., Karamsad, Karimnagar, Katni South,
Kedgaon, Kosamba Jn., Kulitturai, Lasalgaon, Limbdi, Lonand Jn.,
Mahe, Mahuva, Mailani, Mandal Garh, MandawarMahwa Road, Mandi
Dabwali, Mannargudi, Matunga, Mithapur, Morbi, Munirabad,
Murtizapur Jn., Narmadapuram (Hoshangabad), Netaji Subhash
Chandra Bose Itwari Junction, Okha, Orchha, Palitana, Panagarh,
Parel, Pirpainti, Pokhrayan, Polur, Rajgarh, Rajmahal, Rajula Jn.,
Ramghat Halt, Saharanpur Jn., Samakhiyali, Samalpatti, Sankarpur,
..3/--3-
Savda, Seoni, Shahad, Shajapur, Shridham, Siddharth Nagar, Sihor
Jn., Srirangam, St.Thomas Mount, Sullurpeta, Suraimanpur,
Swaminarayan Chappia, Thawe, Tiruvannamalai, Ujhani, Urkura,
Utran, Vadakara, Vadala Road, Vriddhachalam Jn., Warangal.
The Amrit Bharat Station scheme envisages development of stations
on a continuous basis with a long-term approach. It involves
preparation of master plans and their implementation in phases to
improve the amenities at the stations like improvement of station
access, circulating areas, waiting halls, toilets, lift/escalators as
necessary, platform surfacing and cover over platform, cleanliness,
free Wi-Fi, kiosks for local products through schemes like ‘One
Station One Product’, better passenger information systems,
executive lounges, nominated spaces for business meetings,
landscaping, etc. keeping in view the necessity at each station.
The scheme also envisages improvement of building, integrating the
station with both sides of the city, multimodal integration, amenities
for Divyangjans, sustainable and environment friendly solutions,
provision of ballastless tracks, etc. as per necessity, phasing and
feasibility and creation of city centre at the station in the long term.
Development / upgradation of stations including under Amrit Bharat
Station Scheme is generally funded under Plan Head-53 ‘Customer
Amenities’. The details of allocation under Plan Head-53 are
maintained Zonal Railway-wise and not work-wise or station-wise or
State-wise. Chandigarh railway station falls under the jurisdiction of
Northern Railway for which a total allocation of Rs 2216 crores
(Budget Estimate) has been made for the financial year 2025-26 under
Plan Head-53.
..4/--4-
Further, development/redevelopment/upgradation of Railway Stations
is complex in nature involving safety of passengers & trains and
requires various statutory clearances such as fire clearance,
heritage, tree cutting, airport clearance etc. The progress also gets
affected due to brown field related challenges such as shifting of
utilities, (involving water/sewage lines, optical fiber cables, gas pipe
lines, power/signal cables etc.) infringements, operation of trains
without hindering passenger movement, speed restrictions due to
works carried out in close proximity of high voltage power lines etc.
and these factors affect the completion time. Therefore, no time
frame can be indicated at this stage.
Cleanliness is a continuous process and every endeavour is made to
keep the station premises in properly maintained and clean condition.
The housekeeping work at Chandigarh Railway Station is being done
at good standards while the station redevelopment work is being
carried out. All the passenger facilities such as Platforms, waiting
rooms, Toilets and bathrooms etc are being maintained in hygienic
condition for the comfort of passengers. Frequent inspections by the
concerned officials are being conducted at Chandigarh railway
station to ensure its cleanliness.
In order to regulate rush at platforms and to prevent any untoward
incident, following steps are taken by railways in coordination with
GRP/Local Police:-
1. Queue System is maintained for hassle free boarding of passengers
in general coaches of important trains at originating stations.
2. Skilled RPF staff is deployed in CCTV Control Room to keep a close
watch on the crowded areas.
..5/--5-
3. GRP & RPF staffs are deployed at foot-over bridges to regulate
crowd smoothly in order to avoid stampede like situation during the
heavy rush period and render real time assistance to passengers.
4. State Level Security Committee of Railways (SLSCR) have been
constituted for all State/Union Territories under the Chairmanship of
respective Director General of Police/Commissioner of States/Union
Territories for regular monitoring and review of security
arrangements of the Railways.
5. Intelligence units (CIB/SIB) and plain cloth staff are deployed for
collection of intelligence, gathering more information about rush and
accordingly arrangements are made associating GRP/Police.
6. Coordination with GRP/State Police is made for ensuring crowd
management.
Indian Railways has a well established mechanism to monitor
implementation of projects including their reviews, inspection,
feedbacks, check for quality of works and audits. Works are carried
out adhering to the standards and specifications laid down in various
codes and manuals. Inspections/audits/checks are carried out from
time to time by various agencies/officials/multi-disciplinary teams as
per laid down instructions and actions for correction are taken
immediately. This is a continuous and ongoing process.
****