See Full Document Text
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 2864
TO BE ANSWERED ON 05.08.2026
REDEVELOPMENT OF HARDOI RAILWAY STATION UNDER ABSS
2864. SHRI JAI PRAKASH:
Will the Minister of RAILWAYS be pleased to state:
(a) whether Hardoi Railway Station has been selected for redevelopment
under the Amrit Bharat Station Scheme (ABSS) and if so, the details
thereof;
(b) the details of the sanctioned fund for the said project, along with the
major components of the redevelopment works;
(c) the details of present physical and financial progress of the said project
including the percentage of work completed and the expenditure
incurred so far;
(d) the details of original and revised timelines fixed for the completion of
the said project along with the reasons for delay;
(e) whether the Government has modified the earlier original approved
redevelopment/design plan of the said project and if so, the details
thereof and if not, the reasons therefor; and
(f) the details of revised project cost, the present status of execution and
the expected date of completion?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (f) Ministry of Railways has launched Amrit Bharat Station Scheme
for redevelopment of stations with a long-term approach.
Hardoi station, located in Uttar Pradesh, has been identified for
development under the Amrit Bharat Station Scheme. At Hardoi station,
facilities like platform shelter, waiting hall, drinking water arrangement,
§ Page 1 of 7urinal, lavatory, seating arrangement, foot over bridge etc. are available.
The structural work of new station building, platform raising and surfacing
of platform no. 1, 2 & 3 and platform shelter at platform no. 1, 2 & 3 and 4 &
5 have been completed. The finishing work of station building, waiting
lounge, toilets, 12 m wide foot over bridge, improvement of circulating
area, parking and lift have been taken up.
Amrit Bharat Station Scheme involves preparation of master plans and their
implementation in phases to improve the stations of Indian Railways. The
master planning, keeping in view the necessity of each station, includes:
● Improvement of access to station and circulating areas
● Integration of station with both sides of city
● Improvement of station building
● Improvement of waiting halls, toilets, sitting arrangement, water
booths
● Provision of wider foot over bridge/subway to commensurate with
passenger traffic
● Provision of lifts/escalators/ramps
● Improvement of platform surface/ provision of platform shelter
● Provision of kiosks for local products through schemes like ‘One
Station One Product’
● Parking development
● Amenities for Divyangjans
● Better passenger information systems
● Provision of air concourse, executive lounges, Multimodal integration,
landscaping, etc.
The scheme also envisages sustainable and environment friendly solutions
etc. as per necessity, phasing and feasibility and creation of city centre at
the station in the long term.
Page 2 of 7Master Planning is an iterative process requiring optimization and the time
frame and other details for such optimization.
So far, 1,340 stations have been identified for development under this
scheme, out of which 157 stations, including Hardoi station, are located in
Uttar Pradesh. The names of stations identified for development under
Amrit Bharat Station Scheme in Uttar Pradesh are as following:
No. of Name of Stations
State
Stations
Uttar 157 Achnera, Agra Cantt., Agra Fort, Aishbagh Jn,
Pradesh Akbarpur Jn, Aligarh, Amethi, Amroha, Anand
Nagar Jn., Aonla, Ayodhya Dham Junction,
Azamgarh, Babatpur, Bachhrawan, Badaun,
Badshahnagar, Badshahpur, Baheri, Bahraich,
Balamau Jn., Ballia, Balrampur, Banaras, Banda,
Barabanki Jn, Bareilly, Bareilly City, Barhni,
Basti, Belthara Road, Bhadohi, Bharatkund,
Bhatni, Bhuteshwar, Bijnor, Bulandsahar,
Chandauli Majhwar, Chandausi, Chilbila,
Chitrakut dham karwi, Chopan, Chunar Jn.,
Daliganj, Darshannagar, Deoria Sadar, Dhampur,
Dildarnagar, Etawah Jn., Farrukhabad,
Fatehabad, Fatehpur, Fatehpur Sikri, Firozabad,
Gajraula, Garhmuktesar, Gauriganj, Ghatampur,
Ghaziabad, Ghazipur City, Gola Gokarnath,
Gomtinagar, Gonda, Gorakhpur, Govardhan,
Govindpuri, Gursahaiganj, Haidergarh, Hapur,
Hardoi, Hathras City, Idgah Agra Jn, Izzatnagar,
Page 3 of 7No. of Name of Stations
State
Stations
Janghai Jn, Jaunpur City, Jaunpur Jn, Kannauj,
Kanpur Anwarganj, Kanpur Bridge Left Bank,
Kanpur Central, Kaptanganj Jn, Kasganj Jn,
Kashi, Khalilabad, Khorason road, Khurja Jn.,
Kosi Kalan, Kunda Harnamganj, Lakhimpur,
Lalganj, Lalitpur Jn, Lambhua, Lohta, Lucknow
(Charbagh) NR, Lucknow city, Lucknow Jn.
(NER), Maa Belha Devi Pratapgarh Junction,
Maghar, Maharaja Bijli Pasi, Mahoba Jn, Mailani
Jn, Mainpuri Jn, Malhaur, Manak Nagar,
Manikpur Jn, Mariahu, Mathura Jn, Mau Jn,
Meerut City Jn, Mirzapur, Modinagar,
Mohanlalganj, Moradabad Jn, Muzaffarnagar,
Nagina, Najibabad Jn, Orai, Panki Dham,
Phaphamau Jn, Phulpur, Pilibhit Jn, Pokhrayan,
Prayag Jn, Prayagraj Jn, Pt. Deen Dayal
Upadhyay Jn , Rae Bareli Jn, Raja Ki Mandi,
Ramghat Halt, Rampur Jn, Renukoot,
Saharanpur Jn., Salempur, Seohara, Shahganj
Jn, Shahjahanpur, Shamli, Shikohabad Jn.,
Shivpur, Siddharth nagar, Sitapur Jn.,
Sonbhadra, Sri Krishna Nagar, Sultanpur Jn,
Suraimanpur, Swaminarayan Chappia, Takia,
Tulsipur, Tundla Jn., Ujhani, Unchahar, Unnao
Jn, Utraitia Jn, Varanasi Cantt., Varanasi City,
Vindhyachal, Virangana Lakshmibai Jhansi,
Vyasnagar, Zafarabad
Page 4 of 7Completed Stations of Uttar Pradesh:
Development works at railway stations under Amrit Bharat Station
Scheme in Uttar Pradesh have been taken up at a good pace. Details of
stations completed in Uttar Pradesh are as under:
State No. of Name of stations
stations
Uttar 38 Aishbagh Junction, Ayodhya Dham Junction,
Pradesh Bachhrawan, Baheri, Balrampur, Bareilly City,
Bijnor, Chunar Junction, Daliganj, Dhampur,
Fatehabad, Fatehpur, Gauriganj, Gola Gokarnath,
Gomtinagar, Govardhan, Govindpuri, Hathras City,
Idgah Agra Junction, Izzatnagar, Khalilabad,
Mailani Junction, Modinagar, Mohanlalganj, Orai,
Panki Dham, Phaphamau Junction, Pokhrayan,
Prayag Junction, Ramghat Halt, Saharanpur
Junction, Salempur, Shamli, Siddharth Nagar,
Suraimanpur, Swaminarayan Chappia, Ujhani,
Vindhyachal
The activities for development at other stations of Uttar Pradesh have also
been taken up at good pace and progress of some of the stations is as
given below:
Hapur station: The works of improvement of station building, new
platform shelter, improvement of platform surface, improvement of
circulating area and approach road have been completed. The work of
12 m wide foot over bridge has been taken up.
Page 5 of 7 Kanpur Central station: The structural works of new station building,
commercial building, electrical substation at city side and
Cantonment side have been completed. The finishing works of new
station building, commercial building, electrical substation at city and
Cantonment side, structural work of air concourse, new platform
shelters, improvement of platform surface and underground parking
have been taken up.
Lucknow (Charbagh) NR station: The structural work of new station
building at second entry has been completed. The finishing work of
new station building, concourse, 10 m wide foot over bridge,
development of circulating area at second entry and improvement of
circulating area at main entry have been taken up.
Nagina station: The works of new station building, improvement of
platform surface, new platform shelter, improvement of circulating
area, parking and new 12 m wide foot over bridge have been
completed. The work of installation of lift has been taken up.
Prayagraj Junction station: The structural work of station building at
Civil lines side, Railway Mail Service building, parcel building, two
arrival blocks, 2 electric substations and improvement of surface
parking have been completed. The finishing works of station building,
Railway Mail Service building, parcel building and electrical
substation, basement parking at city side, air concourse and new
platform shelter have been taken up.
Further, development / redevelopment / upgradation / modernisation of
stations on Indian Railways is a continuous and ongoing process and works
in this regard are undertaken as per requirement, feasibility and
Page 6 of 7maintainability of various passenger amenities required at stations, as per
the category of station/condition/traffic handled.
Development / Upgradation / Modernisation of stations including under
Amrit Bharat Station Scheme is generally funded under Plan Head-53
‘Customer Amenities’. The details of allocation and expenditure under Plan
Head-53 are maintained Zonal Railway-wise and not station-wise or state-
wise. Uttar Pradesh is covered under the jurisdiction of five railway zones,
namely, East Central Railway, North Central Railway, Northern Railway,
North Eastern Railway and West Central Railway. For these zones, an
allocation of ₹ 4,118 crore has been made for the financial year 2026-27,
out of which an expenditure (up to June, 2026) of ₹ 1,256 crore has been
incurred so far.
Development / Upgradation of railway stations is a complex in nature
involving safety of passengers & trains and requires various statutory
clearances such as tree cutting, heritage, fire clearance, airport clearance
etc. These stations are in operation since long, so brownfield work
challenges are being faced, such as shifting of utilities (involving
water/sewage lines, optical fibre cables, gas pipelines, power/signal
cables, etc.), infringements, operation of trains without hindering
passenger movement, speed restrictions due to works carried out in close
proximity of the tracks and near to high voltage power lines, etc. and these
factors affect the progress of work and completion time.
*****
Page 7 of 7