**Executive Summary**
This document is an answer to Unstarred Question No. 1782 in Lok Sabha, regarding the redevelopment of railway stations in Delhi under the Amrit Bharat Station Scheme (ABSS). The Ministry of Railways has identified 13 railway stations in Delhi for redevelopment under the ABSS. No completion date for New Delhi Railway Station redevelopment is given in the document.
**Key Points / Main Content**
* **Amrit Bharat Station Scheme (ABSS)**
* Launched by the Ministry of Railways for the redevelopment of railway stations.
* 1337 stations identified for development across India.
* Development is envisioned on a continuous basis with a long-term approach involving master plans and phased implementation.
* Master planning addresses access, integration with the city, building improvement, waiting halls, foot over bridges, lifts, platform improvements, kiosks, parking, Divyangjan amenities, passenger information, and executive spaces.
* Emphasizes sustainable and environment-friendly solutions.
* **Delhi Stations Under ABSS**
* 13 stations in Delhi are identified for development: Adarshnagar Delhi, Anand Vihar, Bijwasan, Delhi, Delhi Cantt, Delhi Sarai Rohilla, Delhi Shahadra, Hazrat Nizamuddin, Narela, New Delhi, Sabzi Mandi, Safdarjung, Tilak Bridge.
* **Status of Development Works**
* *Safdarjang Station*: Signal & telecom building completed and operational, station building structure complete, MEP works underway, structural works of operational building completed, foundation work of air concourse complete, departure plaza canopy completed, platform shelter, circulation, and approach road work underway.
* *Bijwasan Station*: Structural work of station building complete, masonry and finishing work underway, air concourse, foundation, girder work complete, roofing work underway, platform shelters work underway, electrical substation work complete, sewage treatment plant and subway finishing work underway.
* *Delhi Cantt Station*: Structural work of east side station building (part 1) and residential quarters complete; other east side station building work underway.
* *Tilak Bridge Station*: Platform surfacing, approach road, and temporary booking window complete; new station building work underway.
* *Sabzi Mandi Station*: New platforms, washable apron, coach watering facility, platform surfacing, entry road widening, and PRS relocation complete; new station building and toilet block finishing work underway.
* *Narela Station*: Platform surfacing, platform widening, additional platform shelters, booking window shifting, and toilet block finishing work underway.
* *New Delhi Station*: Holding area at Ajmeri Gate complete (equipped with facilities like ticket counters, ATVMs, public announcement, display boards, CCTV, scanners, metal detectors, uninterrupted power supply, lighting, fans, fire-fighting system, RO water, and toilets), basement work at Paharganj side, demolition, and utility shifting underway.
* **Master Planning**
* Stations are at various stages of master planning.
* Master planning is an iterative process.
* **Factors Affecting Completion Time**
* Complex nature of work involving passenger safety.
* Statutory clearances such as fire clearance, heritage, tree cutting, airport clearance etc.
* Challenges such as shifting of utilities.
* Operation of trains without hindering passenger movement.
* Speed restrictions due to works carried out in close proximity of high voltage power lines etc.
**Impact Analysis**
**Stakeholder: Passengers**
* **Impact:** Improved station facilities, enhanced passenger convenience, particularly during peak travel periods, eased congestion, and better passenger information systems.
* **Action Required:** No direct action required from passengers.
**Stakeholder: Ministry of Railways**
* **Impact:** Responsibility for executing and overseeing the redevelopment projects, managing various statutory clearances and logistical challenges, ensuring passenger safety, optimizing master planning, and implementing the scheme in phases.
* **Action Required:** Continue implementation of the Amrit Bharat Station Scheme, address factors affecting completion time, manage master planning processes, and oversee all associated works.
**Stakeholder: Local Businesses and Communities**
* **Impact:** Potential for new business opportunities through initiatives like "One Station One Product," improved connectivity, and potential economic benefits from enhanced station facilities.
* **Action Required:** Engage with the Ministry of Railways to explore opportunities related to the redevelopment projects and “One Station One Product”.
Key Entities Referenced
Amrit Bharat Station Scheme: A scheme by the Ministry of Railways for the redevelopment of railway stations in India.
Ministry of Railways: The Indian government ministry responsible for the country's railway network.
Delhi: The state where railway stations are being redeveloped under the Amrit Bharat Station Scheme.
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 1782
TO BE ANSWERED ON 10.12.2025
REDEVELOPMENT OF NEW DELHI RAILWAY STATION UNDER ABSS
†1782. SHRI RAMVIR SINGH BIDHURI:
Will the Minister of RAILWAYS be pleased to state:
(a) the total number of railway stations in Delhi to be redeveloped
under the Amrit Bharat Station Scheme;
(b) the time by which the redevelopment work of New Delhi Railway
Station is likely to be completed; and
(c) the present status of redevelopment work at the remaining railway
stations in the Capital?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (c): Ministry of Railways has launched Amrit Bharat Station
Scheme for redevelopment of stations. So far, 1337 stations have been
identified for development under Amrit Bharat Station Scheme, out of
which 13 stations are located in the state of Delhi. The names ofstations identified for development under Amrit Bharat Station Scheme
in the state of Delhi are as following:-
No. of Amrit
State Names of Amrit Stations
Stations
Adarshnagar Delhi, Anand Vihar, Bijwasan,
Delhi, Delhi Cantt, Delhi Sarai Rohilla, Delhi
Delhi 13
Shahadra, Hazrat Nizamuddin, Narela, New
Delhi, Sabzi Mandi, Safdarjung, Tilak Bridge.
Development works at railway stations under Amrit Bharat Station
Scheme in the state of Delhi have been taken up at a good pace. For
example,
At Safdarjang station, the works for construction of signal &
telecom building has been completed and it has been made
operational. The structural works of station building have been
completed and finishing and Mechanical, Electrical, Plumbing
(MEP) works have been taken up. The structural works of
operational building completed and finishing work has been
taken up. Foundation work of air concourse has been completed
and works of erection of columns and launching of girders have
been taken up. The work for construction of departure plaza
canopy has been completed. The work for provision of platform
shelter, improvement of circulation and approach road has been
taken up.
At Bijwasan station, the structural work of station building has
been completed; masonry work and finishing works have beentaken up. The work for construction of air concourse, works of
foundations, columns, launching of girders and casting of deck
slab have been completed and roofing work has been taken up.
The work for platform shelters has been taken up. The structural
work of electrical sub-station has been completed and trench
laying has been taken up. The structural work of sewage
treatment plant and subway completed and finishing works have
been taken up.
• At Delhi Cantt. Station, the structural work of east side station
building (part 1), and the structural work of residential quarters
have been completed. The structural works for east side station
building (part 2), elevated road, arrival and departure concourse
and finishing of east side station building (part 1) have been
taken up.
• At Tilak Bridge station, works of improvement of platform
surfacing at platform no. 4 & 5, approach road and construction
of temporary booking window have been completed and work of
construction of new station building has been taken up.
• At Sabzi Mandi station, works of construction of new platforms
with washable apron and coach watering facility, improvement of
platform surfacing, widening of entry road and shifting of
Passenger Reservation System (PRS) to renovated building have
been completed and works of construction of new station
building, finishing works of toilet block, etc. have been taken up.• At Narela station, works of improvement of platform surfacing,
widening of platform no. 2, provision of additional platform
shelters, shifting of booking window, finishing works of toilet
block, etc. have been taken up.
• At New Delhi station, the work for provision of holding area at
Ajmeri Gate side has been completed. The holding area is
equipped with a wide range of commuter-friendly facilities,
including an increased number of ticket counters, Automatic
Ticket Vending Machine(ATVMs), public announcement system,
electronic train information display boards, CCTV surveillance,
luggage scanners, Door Frame Metal Detector (DFMDs),
uninterrupted power supply, improved night-time lighting, High
Volume Low Speed (HVLS) fans, fire-fighting system, lightning
protection system, RO drinking water, and separate toilets for
men, women and Divyangjans, along with seating arrangements.
This has significantly helped to ease congestion and enhance
passenger convenience, particularly during peak travel periods.
Further, the work for basement at Paharganj side, demolition of
old structures and utility shifting have been taken up.
Stations taken up for Master planning are at various stages. Master
planning is an iterative process requiring optimization and the time
frame for such optimization cannot be indicated at this stage.
Amrit Bharat Station Scheme envisages development of stations on a
continuous basis with a long-term approach. The scheme involves
preparation of master plans and their implementation in phases toimprove the stations. The master planning, keeping in view the
necessity at each station includes:-
Improvement of access to station and circulating areas
Integration of station with both sides of city
Improvement of station building
Improvement of waiting halls, toilets, sitting arrangement,
water booths
Provision of wider foot over bridge/air concourse
commensurate with passenger traffic
Provision of lift/escalators/ramp
Improvement /Provision of platform surface and cover over
platforms
Provision of kiosks for local products through schemes like
‘One Station One Product’
Parking areas, Multimodal integration
Amenities for Divyangjans
Better passenger information systems
Provision of executive lounges, nominated spaces for
business meetings, landscaping, etc.
The scheme also envisages sustainable and environment friendly
solutions, provision of ballastless tracks, etc. as per necessity,
phasing and feasibility and creation of city centre at the station in the
long term.Further, development/redevelopment/upgradation of Railway Stations
is complex in nature involving safety of passengers & trains and
requires various statutory clearances such as fire clearance, heritage,
tree cutting, airport clearance etc. The progress also gets affected
due to brown field related challenges such as shifting of utilities,
(involving water/sewage lines, optical fiber cables, gas pipe lines,
power/signal cables etc.,) infringements, operation of trains without
hindering passenger movement, speed restrictions due to works
carried out in close proximity of high voltage power lines etc. and
these factors affect the completion time. Therefore, no time frame can
be indicated at this stage.
*****