GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 656
TO BE ANSWERED ON 22.07.2026
REDEVELOPMENT OF RAILWAY STATION AT TIRUVALLUR AND
GUMMIDIPOONDI UNDER ABSS
656. SHRI SASIKANTH SENTHIL:
Will the Minister of RAILWAYS be pleased to state:
(a) the steps taken/being taken by the Government to augment frequency
and capacity on the Chennai–Tiruvallur–Arakkonam suburban section;
(b) the status of station redevelopment at Tiruvallur and Gummidipoondi
under the Amrit Bharat Station Scheme (ABSS);
(c) whether new sub-urban lines, halt stations or foot-over-bridges in
Tiruvallur district are under consideration and if so, the details thereof;
and
(d) whether the level crossings in Tiruvallur district approved for
conversion to Road Over-Bridges and if so, the details thereof?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (d) Presently, there are 4 existing lines in Chennai – Tiruvallur –
Arakkonam section. Further, to improve the connectivity and capacity of
Rail network in Chennai Suburban Area, Final Location Survey for 5th and 6th
line Chennai – Tiruvallur – Arakkonam (68 km) has been sanctioned.
Sanctioning of projects requires consultation with various stakeholders
including State Governments and necessary approvals viz. appraisal of NITI
Aayog, Ministry of Finance etc. As sanctioning of projects is a continuous
and dynamic process.
§ Page 1 of 15Station Redevelopment
Tiruvallur and Gummidipundi stations, located in Tamil Nadu, have been
identified for development under Amrit Bharat Station Scheme.
Development works at this station have been taken up at a good pace.
At Tiruvallur station, the works for extension and improvement of existing
station building, booking office, parking, improvement of platform surface
of platform no. 1 & 6, platform shelter and the structural works of new
concourse and entrance porch have been completed. The works of 12m
wide foot over bridge, lifts, improvement of circulating area and signages
have been taken up.
At Gummidipundi station, the works of improvement of parking, second
entry booking office, improvement of platform surface of platforms 1 & 2
and 3 & 4 and installation of lifts have been completed. The works of new
station building, improvement of pedestrian plaza, drainage and approach
road at first entry, integrated Passenger Information System and 12 m wide
foot over bridge have been taken up.
Further, development / redevelopment / upgradation / modernisation of
stations on Indian Railways is a continuous and ongoing process and works
in this regard are undertaken as per requirement, subject to inter-se
priority and availability of funds. Development / redevelopment /
upgradation / modernisation of a station is carried out based on category
of station/condition/traffic handled etc.
Ministry of Railways has launched Amrit Bharat Station Scheme for
redevelopment of stations with a long-term approach.
Page 2 of 15The scheme involves preparation of master plans and their implementation
in phases to improve the stations of Indian Railways. The master planning,
keeping in view the necessity of each station, includes:
Improvement of access to station and circulating areas
Integration of station with both sides of city
Improvement of station building
Improvement of waiting halls, toilets, sitting arrangement, water
booths
Provision of wider foot over bridge/subway to commensurate with
passenger traffic
Provision of lifts/escalators/ramps
Improvement of platform surface/ provision of platform shelter
Provision of kiosks for local products through schemes like ‘One
Station One Product’
Parking development
Amenities for Divyangjans
Better passenger information systems
Provision of air concourse, executive lounges, Multimodal integration,
landscaping, etc.
The scheme also envisages sustainable and environment friendly solutions
etc. as per necessity, phasing and feasibility and creation of city centre at
the station in the long term.
So far, 1340 stations have been identified for development under Amrit
Bharat Station Scheme, out of which 77 stations, including Tiruvallur and
Gummidipundi stations, are located in Tamil Nadu. The names of stations
identified for development under Amrit Bharat Station Scheme in Tamil
Nadu are as following:
Page 3 of 15State No. of Names of Stations
Stations
Tamil Nadu 77 Ambasamudram, Ambattur, Arakkonam Jn,
Ariyalur, Avadi, Bommidi, Chengalpattu Jn,
Chennai Beach, Chennai Egmore, Chennai
Park, Chidambaram, Chinna Salem,
Chrompet, Coimbatore Jn, Coimbatore
North, Coonoor, Dharmapuri, Dindigul,
Erode Jn., Guduvancheri, Guindy,
Gummidipundi, Hosur, Jolarpettai Jn,
Kanniyakumari Terminus, Karaikkudi Jn,
Karur Jn, Katpadi Jn, Kovilpatti, Kulitturai,
Kumbakonam, Lalgudi, Madurai Jn,
Mambalam, Manaparai, Mannargudi,
Mayiladuturai Jn, Mettupalayam, Morappur,
Nagercoil Jn, Namakkal, Palani,
Paramakkudi, Perambur, Podanur Jn.,
Pollachi Jn, Polur, Pudukkottai, Puratchi
Thalaivar Dr. M.G. Ramachandran Central,
Rajapalayam, Ramanathapuram,
Rameswaram, Salem, Samalpatti,
Sholavandan, Srirangam, Srivilliputtur,
St.Thomas Mount, Tambaram, Tenkasi,
Thanjavur Jn, Thiruvarur Jn., Tiruchendur,
Tirunelveli Jn, Tirupadripulyur, Tirupattur,
Tiruppur, Tirusulam, Tiruttani, Tiruvallur,
Tiruvannamalai, Tuticorin,
Udagamandalam, Vellore Cantt.,
Page 4 of 15State No. of Names of Stations
Stations
Villupuram Jn., Virudhunagar,
Vriddhachalam Jn.
Completed Stations:
Development works at railway stations under Amrit Bharat Station Scheme
in Tamil Nadu have been taken up at a good pace. Details of stations
completed in Tamil Nadu are as under:
No. of
State Name of Stations
Stations
Tamil Nadu 26 Ambasamudram, Bommidi, Chennai Park,
Chidambaram, Chinna Salem, Coonoor,
Karaikkudi Junction, Kulitturai,
Mambalam, Manaparai, Mannargudi,
Morappur, Namakkal, Palani, Paramakkudi,
Pollachi Junction, Polur, Samalpatti,
Sholavandan, Srirangam, Srivilliputtur,
St.Thomas Mount, Thiruvarur Junction,
Tiruvannamalai, Udagamandalam,
Vriddhachalam Junction
The activities for development at other stations have also been taken up at
good pace and progress of some of the stations is as given below:
Virudhunagar station: The works of improvement of circulating area,
parking, entry/exit gate, installation of Coach Indication Boards and
Train Indication Boards have been completed. The works of
Page 5 of 15improvement of station building including entrance porch and 6 m
wide foot over bridge have been taken up.
Karur Junction station: The works of improvement of station building,
12 m wide foot over bridge, improvement of circulating area, parking,
main entrance gate, waiting hall, toilets, parcel office building,
improvement of platform resurface and platform widening of platform
no.1 have been completed. The works of lifts and escalators have
been taken up.
Thanjavur Junction station: The works of entrance porch,
improvement of circulating area including landscaping, concourse &
subway, platform shelter, arrival lobby, exit gate, booking office,
installation of Coach Indication Board, Train Indication Board and
signages have been completed. The works of parking, lift and
escalator have been takenup.
Villupuram Junction station: The works of new arrival building,
Government Railway Police (GRP) building, platform shelter,
improvement of platform surface, booking office, improvement of
parking, parcel office and signages have been completed. The works
of 6 m wide foot over bridge, improvements of circulating area,
parking, concourse, departure building, entrance gate, installation of
Coach Indication Board, Train Indication Board and escalator have
been taken up.
Rameswaram station: The works of revamping of Multi Functional
Complex (MFC) building into retiring rooms, structural works of East
and North terminal building, parcel office, residential tower,
departure forecourt, arrival forecourt, substation building and sewage
treatment plant have been completed. The finishing works of East
Page 6 of 15terminal building, North terminal building, departure forecourt,
sewage treatment plant, arrival forecourt, platform shelter and
improvement of waiting hall have been taken up.
Development / Upgradation of railway stations is a complex in nature
involving safety of passengers & trains and requires various statutory
clearances such as tree cutting, heritage, fire clearance, airport clearance
etc. These stations are in operation since long, so brownfield work
challenges are being faced, such as shifting of utilities (involving
water/sewage lines, optical fibre cables, gas pipelines, power/signal
cables, etc.), infringements, operation of trains without hindering
passenger movement, speed restrictions due to works carried out in close
proximity of the tracks and near to high voltage power lines, etc. and these
factors affect the progress of work and completion time.
Development / upgradation / modernisation of stations including under
Amrit Bharat Station Scheme is generally funded under Plan Head-53
‘Customer Amenities’. The details of allocation and expenditure under Plan
Head-53 are maintained Zonal Railway-wise and not station-wise or state-
wise. Tamil Nadu is covered under the jurisdiction of three railway zones,
namely, Southern Railway, South Western Railway and South Coast
Railway. For these zones, an allocation of ₹ 1,298 crore has been made for
the financial year 2026-27, out of which an expenditure (up to June, 2026)
of ₹ 582 crore has been incurred so far.
ROBs/RUBs
Sanctioning of works of Road over Bridge (ROB)/Road under Bridge (RUB) in
lieu of Level Crossings (LCs) is a continuous and dynamic process of Indian
Railway. Such works are prioritised and taken up on the basis of their
Page 7 of 15impact on safety in train operations, mobility of trains & impact for road
users and feasibility etc.
No. of ROBs/ RUBs constructed on Indian Railways during the period 2004-
14 viz-a-viz 2014-26 (Upto May’26) is as under:
Period ROBs/ RUBs constructed
2004-14 4,148 Nos.
2014-26 (Upto May’26) 14,451 Nos. (814 Nos. in the State of Tamil
Nadu)
As on 01.06.2026, 4,993 Nos. ROBs/ RUBs works are sanctioned at a cost of
approx. ₹1,17,492 Cr on Indian Railways including 248 Nos. ROBs/ RUBs
works at a cost of approx. ₹ 4,952 Cr in the State of Tamil Nadu which are
at various stages of planning and execution.
As on 01.04.2026, Indian Railways has 15,689 Nos. of Manned Level
Crossings (MLCs) on Broad Gauge (BG). Of these, 1,211 Nos. MLCs are
situated in the State of Tamil Nadu, including 26 Nos. MLCs falling within
the Tiruvallur district. 16 Nos. ROB/RUB works (excluding the non-feasible
works) are sanctioned for elimination of LCs in the Tiruvallur district. The
details are as under:
S.No LC No. ROB/ Total Current Status
RUB cost (₹
in
crore)
1 LC No. 13 at 36 Railway Portion has been
km 31/12 - 14 ROB completed.
on Tiruninravur Approach Portion work has
- Tiruvallur been taken up.
section
Page 8 of 152 LC No. 20 at RUB 9 GAD preparation work has been
km 44/30-45/2 taken up.
on Tiruvallur –
Kadambattur
section
3 LC No. 22 at RUB 5 The work of DPR preparation
km 50/8-10 on has been taken up.
Tiruvallur –
Kadambattur
section
4 LC No. 25 at ROB 37 GAD preparation work has been
km 57/32-58/2 cum taken up.
on RUB
Kadambattur –
Tiruvalangadu
section
5 LC No. 42 at RUB 35 The work of DPR preparation
km 83/10-12 on has been taken up.
Tiruttani -
Ponpadi
section
6 LC No. 45 at ROB 43 The work of DPR preparation
km 88/21-25 on has been taken up.
Tiruttani -
Ponpadi
section
7 LC No. 2 at km ROB 37 GAD has been approved.
2A/40-42 on
Basin Bridge
Junction –
Korukkupet
section
8 LC No. 14 at ROB 41 Construction work has been
km 22/14-16 on taken up.
Attippattu -
Minjur section
9 LC No. 16 at ROB 39 Construction work has been
km 24/16-18 on taken up.
Attippattu -
Minjur section
10 LC No. 20 at ROB 39 Land acquisition has been taken
km 28/22-24 on up.
Minjur –
Ponneri section
Page 9 of 1511 LC No. 23 at ROB 41 Land acquisition has been taken
km 32/02-04 on up.
Minjur –
Ponneri section
12 LC No. 25 at ROB 41 Land acquisition has been taken
km 33/42-34/2 up.
on Ponneri –
Kavaraippettai
section
13 LC No. 26 at ROB 40 Railway Portion is Completed
km 35/06-08 on and Work for Approach Portion
Ponneri – has been taken up.
Kavaraippettai
section
14 LC No. 30 at ROB 41 Land acquisition has been taken
km 40/22-24 on up.
Kavaraippettai
– Gummidipundi
section
15 LC No. 31 at ROB 34 Alignment yet to be finalized.
km 41/36-38 on cum
Kavaraippettai– RUB
Gummidipundi
section
16 LC No. 35 at ROB 35 Land acquisition has been taken
km 48/10-12 on up.
Gummidipundi –
Elavur section
Completion & commissioning of ROB/RUB works depends on various
factors like cooperation of State Governments in giving consent for
closure of LC, fixing of approach alignment, approval of General
Arrangement Drawing (GAD), land acquisition, removal of encroachment,
shifting of infringing utilities, statutory clearances from various
authorities, law and order situation in the area of project / work sites,
duration of working season in a year for the particular project / area due to
climatic conditions etc. All these factors affect the completion time of the
projects / works.
Page 10 of 15TAMIL NADU:
Railway Budget:
Budget allocation in recent years has increased significantly. Budget
allocation for infrastructure projects and safety works, falling fully/partly in
the State of Tamil Nadu is as under:
Period Outlay
2009-14 ₹ 879 crore/year
₹ 7,611 crore (more than 8 times)
2026-27
Track Construction:
The details of constructing new track falling fully/partly in the State of
Tamil Nadu are as under:
Period New track Commissioned
2009-14 923 km
2014-26 1,356 km
Projects sanctioned:
As on 01.04.2026, 19 projects (08 new line, 03 gauge conversion and 08
doubling) of total length of 1,874 km, costing ₹27,282 Crore, falling
fully/partly in the State of Tamil Nadu have been sanctioned. The summary
is as under:
Page 11 of 15Category No. of Total Length Total Exp.
projects Length Commissioned till upto March,
(in km) March, 2026 (in km) 2026
(₹ in Cr.)
New Line 8 811 24 1,514
Gauge
3 748 631 3,605
Conversion
Doubling /Multi-
8 314 54 3,693
tracking
Total 19 1,874 709 8,811
Recently Completed Projects:
Details of some of the recently completed projects falling fully/partly in the
State of Tamil Nadu are as under:
S.N. Project Cost
(₹ in
Crores)
1 Dindigul - Pollachi gauge conversion (121 km) 610
2 Pollachi - Palghat gauge conversion (56 km) 350
3 Pollachi - Podhanur gauge conversion (40 km) 400
4 Quilon - Tiruchendur gauge conversion (357 km) 1,122
5 Mayiladuturai - Karaikkudi gauge conversion (187 km) 1,338
6 Madurai - Bodiyakannur gauge conversion (90 km) 593
7 Chengalpattu - Villupuram doubling (102 km) 670
8 Tiruvallur - Arakkonam 4th line (27 km) 83
9 Thanjavur - Ponmalai doubling (48 km) 370
10 Villupuram - Dindigul doubling (273 km) 2,000
Page 12 of 15S.N. Project Cost
(₹ in
Crores)
11 Chennai Beach - Attipattu 4th line (22 km) 293
12 Omalur - Metturdam Patch doubling (29 km) 327
13 Chengalpattu - Villupuram and Tambaram - 1,122
Chengalpattu - 3rd line (133 km)
14 Salem - Omalur doubling (11 km) 115
15 Madurai - Tuticorin doubling (160 km) 1,891
16 Maniyachi - Nagercoil doubling (102 km) 1,752
17 Chennai Beach - Chennai Egmore doubling (4 km) 272
Ongoing Projects:
Some of the projects falling fully/partly in the State of Tamil Nadu which
have been taken up are as under:
Cost
S.N. Project
(₹ in Crores)
1 Tindivanam - Nagari new line (184 km) 3,631
2 Morappur - Dharmapuri new line (36 km) 359
3 Trivandrum - Kanyakumari doubling (87 km) 4,494
4 Irugur - Podanur doubling (11 km) 277
5 Tambaram - Chengalpattu 4th Line (30 km) 757
6 Attipattu - Gummidipundi 3rd & 4th line (23 km) 365
7 Tirupati - Katpadi doubling (105 km) 1,216
8 Tindivanam - Tiruvannamalai New Line (71 km) 1,400
9 Attipattu – Puttur New Line (88 km) 1,700
Page 13 of 15Cost
S.N. Project
(₹ in Crores)
10 Chennai – Cuddulore New Line (179 km) 2,670
11 Baiyapannahalli - Hosur doubling (48 km) 1,160
12 Arakkonam - Chengalpattu doubling (68 km) 993
13 Erode - Karur doubling (67 km) 986
Details of some major projects which are delayed due to land acquisition
are as under:
SN Name of the project Total Land Balance
land acquired Land to be
required (in ha) acquired
(in ha) (in ha)
1. Tindivanam - Tiruvannamalai 276 33 243
new line (71 km)
2. Attiputtu - Puttur new line 189 0 189
(88 km)
3. Morappur - Dharmapuri new line 93 47 46
(36 km)
4. Mannargudi - Pattukkottai new 204 0 204
line (41 km)
5. Thanjavur - Pattukottai new line 152 0 152
(52 km)
Summary of the status of land acquisition in Tamil Nadu is as under:
Total Land required for Projects in Tamil Nadu 4,612 ha
Land Acquired 1,178 ha (26%)
Balance Land to be acquired 3,434 ha (74%)
Page 14 of 15Sanction of any railway project depends upon many parameters/factors
which include the following:
Anticipated traffic projections and remunerativeness of the
proposed route
First and last mile connectivity provided by the project
Connection of missing links and providing additional route
Augmentation of congested/saturated lines
Demands raised by State Governments/Central Ministries/Public
representatives
Railway’s own operational requirements
Socio-economic considerations
Overall availability of funds
Completion of Railway project/s depends on various factors which include
the following:
Land acquisition by State Government
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
*****