GOVERNMENT OF INDIA
MINISTRY OF TOURISM
LOK SABHA
STARRED QUESTION NO.*230
ANSWERED ON 09.03.2026
REDEVELOPMENT OF TEMPLE CORRIDORS AND PILGRIMAGE SITES
*230. SMT. ANITA SUBHADARSHINI:
Will the Minister of TOURISM be pleased to state:
(a) the details of the major temple corridor and pilgrimage sites
redevelopment projects undertaken or completed during the last two
years and the current year in the country, State/UT-wise;
(b) the details of the funds sanctioned, released and utilized for these
projects during the said period along with its current status;
(c) the details of the steps taken by the Government to balance heritage
conservation with proper pilgrim amenities, crowd management and
environmental sustainability;
(d) the extent to which the said redevelopment initiatives have increased
local employment and regional connectivity; and
(e) the details of the new temple corridor from the State of Odisha to be
taken up for development during the year 2026?
ANSWER
THE MINISTER OF TOURISM (SHRI GAJENDRA SINGH SHEKHAWAT)
(a) to (e): A Statement is laid on the Table of the House.
******STATEMENT IN REPLY TO PARTS (a) TO (e) OF LOK SABHA STARRED
QUESTION NO.*230 ANSWERED ON 09.03.2026 REGARDING
REDEVELOPMENT OF TEMPLE CORRIDORS AND PILGRIMAGE SITES RAISED
BY SMT. ANITA SUBHADARSHINI
(a) to (b): The Ministry of Tourism, through its ongoing Central Sector
Schemes of ‘Pilgrimage Rejuvenation and Spiritual, Heritage Augmentation
Drive (PRASHAD)’, ‘Swadesh Darshan (SD)’, ‘Swadesh Darshan (SD2.0)’,
‘Challenge Based Destination Development (CBDD)’, a sub-scheme of
Swadesh Darshan 2.0 scheme, ‘Special Assistance to States for Capital
Investment (SASCI)’ and Assistance to Central Agencies for Tourism
Infrastructure Development supplements the efforts of the State
Government(SG)/ Union Territory (UT) Administration/ Central Agencies by
providing financial assistance for the development of tourism related
infrastructure in the country including major pilgrimage sites and temple
corridors.
The State/UT-wise list of projects sanctioned under the above-
mentioned schemes during the last two years and the current year along with
funds sanctioned, released, utilized and their present status are given in the
Annexure-I.
(c): Under the above mentioned schemes various interventions have been
sanctioned such as queue management complex, waiting halls, cloak room,
widening of approach roads, CCTVs for pilgrim safety, foot-over bridges,
parking, tourist information centre, basic amenities such as toilets, dustbins,
drinking water facilities and other site development works for improving and
upgrading overall pilgrim/tourist experience.To ensure balance between heritage conservation with proper pilgrim
amenities, crowd management and environmental sustainability, the
projects under the above mentioned schemes are prepared in consultations
with the respective State Governments, UT Administrations, local bodies,
and other stake holders. In addition, factors such as carrying capacity,
footfall, cultural, historical & heritage importance of the places, resident
population are taken into consideration so as to ensure sustainable and
responsible tourism.
(d): The above mentioned Schemes of the Ministry of Tourism aims to
rejuvenate pilgrimage and spiritual experience of the tourists through
availability of well-planned tourism infrastructure enabling tourist
convenience, accessibility, cleanliness, last-mile connectivity among
others. The development of tourism infrastructure is ensured in a holistic
manner with the objective of boosting tourism, generating employment and
strengthening the local economy.
(e): No proposal relating to a new temple corridor in the State of Odisha is
under consideration of the Ministry of Tourism. However, the Ministry of
Tourism has sanctioned various tourism development projects in Odisha
amounting to Rs.326.86 Crore, details of which are given in the Annexure-II.
Receiving proposals from the State Governments/UT Administrations
for financial assistance for tourism projects is a continuous process. The
proposals received are examined with reference to the prescribed guidelines
and financial assistance is extended for such projects subject to fulfilment
of the stipulated conditions and availability of funds.
*****ANNEXURE -I
STATEMENT IN REPLY TO PARTS (a) TO (b) OF LOK SABHA STARRED QUESTION NO.*230 ANSWERED ON
09.03.2026 REGARDING REDEVELOPMENT OF TEMPLE CORRIDORS AND PILGRIMAGE SITES BY SMT.
ANITA SUBHADARSHINI
i. List of Projects sanctioned in last two years and current year under PRASHAD Scheme:
S. State/UT Name of the Sanction Sanctioned Amount Amount Physical Current
No. Project Year Cost Authorized Utilized Progress Status
(₹ in Crore) (₹ in Crore) (₹ in Crore) (%)
as per UC
received
1. Karnataka Development of 2023-24 45.38 13.33 0 3.63% Ongoing
Pilgrimage
Amenities at
Sri
Chamundeshw
ari Devi
Temple,
Mysuru
2. Andhra Development of 2024-25 25.33 6.74 0 30.06% Ongoing
Pradesh Pilgrimage
Tourism
Infrastructure
in Annavaram
Temple Town3. Bihar Development of 2024-25 13.29 0.00 0 0% Ongoing
Ambika
Bhawani
Temple, Saran
4. Goa Development of 2024-25 16.46 4.68 0 24.78% Ongoing
Bom Jesus
Basilica
5. Karnataka Development of 2024-25 18.37 0.00 0 0% Ongoing
RenukaYallama
Devi temple
6. Karnataka Development of 2024-25 22.25 6.30 0 0% Ongoing
Basic
Amenities at
Papnash
Temple, Bidar
dist.
7. Mizoram Development of 2024-25 5.47 1.56 0 24.53% Ongoing
Basic
Amenities
under
PRASHAD
scheme in
Vangchhia,
Champhai
District
8. Puducherry Development of 2024-25 25.94 0.00 0 0% Ongoing
Pilgrim
Facilites&
Touristattractions for
Sri
Dharbaranyes
wara Temple
9. Tamil Nadu Development of 2024-25 40.94 0.00 0 3.19% Ongoing
8 Navagraha
Temples
10. Telangana Development of 2024-25 4.22 0.00 0 27.50% Ongoin
Basic g
Amenities at
goddess
RenukaYellam
aDevasthanam
Total 217.65 32.61 0
ii. List of Projects completed in last two years and current year under PRASHAD Scheme
S. State/UT Name of the Sancti Completion Sanction Amount Amount Physical Current
No Project on Year ed Cost Authorized Utilized Progress Status
Year (₹ in (₹ in Crore) (₹ Crore) (%)
Crore) as per
UC
received
1 Bihar Development 2015- 2023-24 29.62 29.62 29.62 100% Completed
at Patna 16
Sahib
2 Meghalaya Development 2020- 2023-24 29.29 27.78 27.78 100% Completed
of Pilgrimage 21Facilitation in
Meghalaya
3 Nagaland Development 2018- 2023-24 25.2 23.56 23.56 100% Completed
of Pilgrimage 19
Infrastructure
in Nagaland
4 Jammu & Development 2016- 2024-25 40.46 34.30 34.30 100% Completed
Kashmir at Hazratbal 17
Shrine,
Srinagar
5 Chhattisgar Development 2020- 2024-25 48.44 40.19 31.94 100% Completed
h of 21
MaaBamlesh
wari Devi
Temple,
Dongargarh,
Rajnandgaon
District,
Chhattisgarh
6 Rajasthan Integrated 2015- 2024-25 32.64 26.11 26.11 100% Completed
Development 16
of Pushkar/
Ajmer
7 Uttar Development 2018- 2024-25 37.59 34.64 30.97 100% Completed
Pradesh of 19
Infrastructure
facilities at
Govardhan8 Uttarakhan Augmentation 2021- 2024-25 54.36 10.22 10.22 Foreclosed Foreclosed
d of Pilgrimage 22
Infrastructure
Facilities and
Gangotri and
YamunotriDh
am
9 West Development 2016- 2024-25 30.03 23.39 23.39 100% Completed
Bengal of Belur Math 17
10 Madhya Development 2020- 2025-26 49.99 42.55 34.63 100% Completed
Pradesh of 21
Amarkantak
11 Maharasht Development 2017- 2025-26 45.41 38.44 38.44 100% Completed
ra of 18
Trimbakeshw
ar, Nashik
12 Nagaland Development 2022- 2025-26 18.18 15.45 15.45 100% Completed
of Pilgrimage 23
Tourism
Infrastructure
at Zunheboto
13 Sikkim Development 2020- 2025-26 33.32 28.31 28.31 100% Completed
of Pilgrimage 21
Facilitation at
Four Patron
Saints,
Yuksom
14 Telangana Development 2020- 2025-26 38.9 33.07 33.07 100% Completed
of Jogulamba 21Devi Temple,
Alampur
Total 513.43 407.63 387.79
iii. List of Projects completed in last two years and current year under Swadesh Darshan 1.0 Scheme
S. State/ Name of the Sancti Completi Sanction Amount Amont Physical Current
N UT Project on on Year ed Cost Authoriz Utilized Progress Status
o. Year (₹ Cr.) ed (₹ Cr.) (%)
(₹ Cr.) as per
UC
receive
d
1 Andhra Development of 2017- 2023-24 35.24 30.02 30.02 100% Completed
Pradesh Buddhist 18
Circuit:
Shalihundam-
Bavikonda-
Bojjanakonda -
Amravati-
Anupu
(Buddhist
Circuit)
2 Kerala Development of 2016- 2023-24 46.54 33.39 33.39 100% Completed
Sabarimala - 17Erumeli-Pampa-
Sannidhanam
(Spiritual
Circuit)
3 Maharash Development of 2018- 2023-24 45.47 43.19 38.84 100% Completed
tra Waki- Adasa- 19
Dhapewada-
Paradsingha-
Telankhandi-
Girad
(Spiritual
Circuit)
4 Punjab Development of 2018- 2023-24 85.32 81.05 81.05 100% Completed
Anandpur Sahib 19
- Fatehgarh
Sahib -
ChamkaurSahib
- Ferozpur -
Khatkar Kalan –
Kalanour –
Patiala
(Heritage
Circuit)
5 Rajasthan Development of 2016- 2023-24 75.80 73.85 73.85 100% Completed
Govind Dev ji 17
temple (Jaipur),
Khatu Shyam Ji
(Sikar) andNathdwara
(Rajsamand)
(Krishna
Circuit)
6 Telangana Development of 2017- 2023-24 96.90 70.61 70.61 100% Completed
QutubShahiHerit 18
age Park-
Paigah Tombs-
Hayat Bakshi
Mosque-
Raymond's
Tomb
(Heritage
Circuit)
7 Uttar Development of 2018- 2023-24 18.30 18.12 18.12 100% Completed
Pradesh Gorakhnath 19
Temple
(Gorakhpur),
Devipattan
Temple
(Balrampur) and
Vatvashni
Temple
(Domariyagunj)
(Spiritual
Circuit)
Total 403.57 350.23 345.88iv. List of Projects sanctioned in last two years and current year under Swadesh Darshan 2.0 Scheme
S. State/ Destination Name of the Sancti Sanctio Amount Amont Physical Current
No Experience on ned Authoris Utilized Progress Status
UT
. Year Cost ed (₹ Cr.) as (%)
(₹ per UC
(₹ Crore)
Crore) received
1 Madhya Chitrakoot Spiritual 2023- 27.22 2.72 0 2.65% Ongoing
Pradesh experience at 24
Chitrakoot
2 Rajasthan Bundi Spiritual 2023- 21.65 2.17 0 5.23% Ongoing
Experience, 24
Keshavraipatan
3 Chhattisg Kawardha BhoramdeoCorr 2024- 145.99 14.60 0 0% Ongoing
arh idor 25
Development,
Kawardha
4 Rajasthan Sikar Development 2024- 87.87 8.79 0 9.65% Ongoing
works at Shri 25
Khatu Shyam Ji
Temple (Sikar)
5 Himachal Chintpurni Development of 2025- 56.26 5.63 0 0% Ongoing
Pradesh MaaChintpurni 26
Devi Temple,
Una6 Madhya Datia Development of 2025- 44.24 4.42 0 3.59% Ongoing
Pradesh PitambaraPeeth 26
Datia
7 Rajasthan Bikaner Development 2025- 22.58 2.26 0 31.19% Ongoing
dist. Works at Shri 26
Karnimatamand
ir, Bikaner
8 Rajasthan MalaseriDun Development of 2025- 48.73 4.87 0 3.66% Ongoing
gari (District MalaseriDungri, 26
Bhilwara) Bhilwara
District
Total 454.54 45.46 0
v. List of Projects sanctioned in last two years and current year under CBDD Scheme
S. State/ Destination Name of the Sancti Sanctioned Amount Amont Physical Current
No. UT Experience on Cost Authori Utilized Progress Status
Year (₹ Crore) zed (₹ Cr.) as (%)
(₹ per UC
Crore) received
1 Andhra Ahobilam Ahobilam-A 2024- 24.99 2.50 0 28.58% Ongoing
Pradesh Temple spiritual 25
Odyssey
2 Jharkhand RamrekhaD Tourism 2024- 18.87 1.87 0 0% Ongoing
ham Infrastructure 25
Development
at RamrekhaDham,
Simdega
3 Kerala Varkala Varkala- 2024- 25.00 2.50 0 2.29% Ongoing
Dakshin 25
Kashi
4 Punjab Anandpur Heritage 2024- 24.90 2.49 0 1.31% Ongoing
Sahib, street -A 25
Rupnagar symbol of
peace and
Harmony at
Sri Anandpur
Sahib,
Rupnagar
5 Uttarakh Kainchidham Developmen 2024- 17.60 1.76 0 19.96% Ongoing
and t of 25
Kainchidha
m campus,
Kainchidha
m
Total 111.36 11.12 0
vi. List of Projects sanctioned in last two years and current year under SASCI Scheme
S. State Name of the Project Sanction Sanctioned Amount Amont Physical Current
No. Year Cost Released Utilized Progress Status
(₹ Crore) (₹ Crore) (₹ Crore) (%)
as per As per
MPRUC
received
1 Karnataka Development of 2024-25 100.00 66.00 _ 0% Ongoing
SavadattiYallammag
udda in Belgavi
2 Uttar Development of 2024-25 74.05 48.87 _ 26.03% Ongoing
Pradesh Bateshwar in
District-Agra
3 Uttar Integrated Buddhist 2024-25 80.24 52.96 40.71 44.61% Ongoing
Pradesh Tourism
Development in
Shrawasti
Total 254.29 167.83 40.71
vii. List of Projects sanctioned in last two years and current year under ACA Scheme
Sn State/ Implement Name of the Sanction Sanctioned Amount Amont Physical Current
ing Experience Year Cost Authorised Utilized Progress Status
UT
Agency (₹ Crore) (₹ Cr.) as (%)
(₹ Crore)
per UC
received
1. T amil ITDC Illumination 2024-25 11.47 0 0 0% Ongoing
Nadu and allied
works at
Gangaikonda
Cholapuram
Temple,District -
Ariyalur
Total 11.47 0 0
******ANNEXURE-II
STATEMENT IN REPLY TO PART (e) OF LOK SABHA STARRED QUESTION
NO.*230 ANSWERED ON 09.03.2026 REGARDING REDEVELOPMENT OF
TEMPLE CORRIDORS AND PILGRIMAGE SITES RAISED BY SMT. ANITA
SUBHADARSHINI
i. List of Project sanctioned in Odisha under PRASHAD Scheme
Name of the Project Sanction Year Sanction Cost Status
(Rs. In Crore)
Infrastructure (2014-15) 50.00 Foreclosed
Development at Puri
ii. List of Project sanctioned in Odisha under Swadesh Darshan Scheme
Name of the Project Sanction Year Sanction Cost Status
(Rs. In Crore)
Development of Gopalpur, (2016-17) 70.82 Complete
Barkul, Satapada and
Tampara
iii. List of Projects sanctioned in Odisha under Special Assistance to States
for Capital Investment (SASCI)
Name of the Project Sanction Year Sanction Cost Status
(Rs. In Crore)
Development of Hirakud (2024-25) 99.90 Ongoing
Development of Satkosia (2024-25) 99.99 Ongoing
iv. List of Project sanctioned in Odisha under Assistance to Central Agencies
for Tourism Infrastructure Development (ACA)
Name of the Project Sanction Cost (Rs. In Crore) Status
Puri Railway Station 6.15 Complete
******