GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 638
TO BE ANSWERED ON 22.07.2026
RESUMPTION OF PENDING RAILWAY PROJECTS
638. SHRI ISHA KHAN CHOUDHURY:
Will the Minister of RAILWAYS be pleased to state:
(a) whether the Government earlier reply confirming financial sanction of
hundred crore under hundred percent Railway funding for the Railway
Overbridge (ROB) at Khalitpur in lieu of LC Gate No. 49/SPL at Kaliachak
to Mothabari block road, Malda, construction has not yet commenced
and if so, the details thereof including the timeline; and
(b) whether the “Special Class” ROB (TVU more than 4 Lakhs) at Samsi,
Ratua 1 Block Level Crossing No. 101, sanctioned in the Railway Budget
2011-12 and the foundation stone was laid in 2013 is still pending and if
so, the details thereof including the reasons therefor and the timeline
fixed for commencement and completion of Railway Overbridge?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) & (b): Sanctioning of works of Road over Bridge (ROB)/Road under
Bridge (RUB) in lieu of Level crossings (LCs) is a continuous and dynamic
process of Indian Railway. Such works are prioritised and taken up on the
basis of their impact on safety in train operations, mobility of trains &
impact for road users and feasibility etc.
No. of ROBs/ RUBs constructed on Indian Railways during the period
2004-14 viz-a-viz 2014-26 (Upto May’26) is as under:
§ Page 1 of 3Period ROBs/ RUBs constructed
2004-14 4,148 Nos.
2014-26 (Upto May’26) 14,451 Nos. (547 Nos. in
the State of West Bengal)
As on 01.06.2026, 4,993 Nos. ROBs/RUBs works are sanctioned at a
cost of approx.₹ 1,17,492 Cr on Indian Railways including 363 Nos. ROBs/
RUBs works at a cost of approx. ₹ 8,060 Cr in the state of West Bengal
which are at various stages of planning and execution.
The work for construction of ROB in lieu of LC No. 49/Spl between
Khaltipur and Chamagram stations in Malda Division has been sanctioned
on railway cost at a cost of ₹ 40 Cr approx. The work for Preparation of
General Arrangement Drawing (GAD) has been taken up.
The work for construction of a Road Over Bridge (ROB) in lieu of Level
Crossing (LC) No. NC-101 at Km 198/8-9 on the New Jalpaigudi–Malda Town
section of Katihar Division was sanctioned during 2012-13 on a cost-
sharing basis. The work was held up due to non-completion of land
acquisition by State Govt. Subsequently, looking at the public interest, the
work has been taken up at Railway cost. The work of General Arrangement
Drawing (GAD) has been taken up.
Completion & commissioning of ROB/RUB works depends on various
factors like cooperation of State Governments in giving consent for
closure of LC, fixing of approach alignment, approval of General
Arrangement Drawing (GAD), land acquisition, removal of encroachment,
shifting of infringing utilities, statutory clearances from various
authorities, law and order situation in the area of project / work sites,
Page 2 of 3duration of working season in a year for the particular project / area due to
climatic conditions etc. All these factors affect the completion time of the
projects / works.
*****