See Full Document Text
GOVERNMENT OF INDIA
MINISTRY OF ENVIRONMENT, FOREST AND CLIMATE CHANGE
RAJYA SABHA
UNSTARRED QUESTION NO. 695
TO BE ANSWERED ON 05.02.2026
Retrospective environmental clearances
695. SHRI MUKUL BALKRISHNA WASNIK:
SMT. RANJEET RANJAN:
SHRI HARIS BEERAN:
SMT. PHULO DEVI NETAM:
Will the Minister of ENVIRONMENT, FOREST AND CLIMATE CHANGE be pleased to
state:
(a) the number of postfacto or retrospective environmental clearances granted since 2021,
year-wise and State/UT-wise;
(b) the details of penalties collected from such cases, if any;
(c) the year-wise and State/UT-wise details of projects granted clearance despite being
flagged by the Ministry’s own Expert Appraisal Committees;
(d) whether Government has conducted any assessment of ecological and economic
consequences of regularising such projects; and
(e) if so, the findings thereof and if not, the reasons therefor?
ANSWER
MINISTER OF STATE IN THE MINISTRY OF ENVIRONMENT, FOREST AND
CLIMATE CHANGE
(SHRI KIRTI VARDHAN SINGH)
(a) to (e) The Government of India has issued Environment Impact Assessment (EIA)
Notification, 2006 under the powers conferred by sub-section (1) and clause (v) of sub-section
(2) of section 3 of the Environment (Protection) Act, 1986. As per the provision of EIA
Notification, 2006, construction of new projects or activities or the expansion or
modernization of existing projects or activities listed in the Schedule to this notification
entailing capacity addition with change in process and or technology shall be undertaken in
any part of India only after the prior environmental clearance from the Central Government or
as the case may be, by the State Level Environment Impact Assessment Authority, duly
constituted by the Central Government under sub-section (3) of section 3 of the said Act, in
accordance with the procedure specified in the EIA Notification.
As per the provisions laid down in the Environment Impact Assessment (EIA) Notification,
2006, as amended, the proposals are appraised by the Expert Appraisal Committee (EAC) or
State Level Expert Appraisal Committee (SEAC) considering all the environmental
implications involved in the project including the issues raised in Public Consultation. Based
on the recommendation of the EAC/SEAC, projects are further considered by the Ministry or
State Environmental Impact Assessment Authority (SEIAA) for approval for grant of
Environmental Clearance (EC) or otherwise.Projects or activities that have started the construction work on site or have expanded the
production capacity and /or project area beyond the limit specified in the environmental
clearance or change of scope without obtaining prior-EC under the EIA Notification, 2006 are
considered as Violation proposals. To bring such projects and activities in compliance with the
environmental laws at the earliest point of time, rather than leaving them unregulated and
unchecked, which will be more damaging to the environment, the Ministry issued Notification
No. S.O. 804(E) dated 14th March, 2017, providing a one-time opportunity for such proposals
for regularization. Subsequently, in compliance with a direction of the National Green
Tribunal, the Ministry issued a Standard Operating Procedure (SOP) by Office Memorandum
dated 7th July, 2021, setting out the process for identification and handling of violation cases.
Both the 2017 Notification (S.O. 804(E) dated 14th March 2017) and the 2021 Standard
Operating Procedure (OM dated 7th July 2021) provide for action against project proponents
under Section 15 of the Environment (Protection) Act, 1986, in cases where prior
environmental clearance was permissible but the same had not been obtained and also require
appraisal of the Environmental Impact Assessment (EIA) report and Environmental
Management Plan (EMP) by the Expert Appraisal Committee. This appraisal includes
assessment of ecological damage and corresponding remediation plan and natural &
community resource augmentation plan as part of the EIA/EMP review process. If, on
examination of the EIA/EMP report, the project is considered permissible for operation as per
extant regulations, the requisite EC is accorded by the Regulatory Authority concerned. Such
clearance becomes effective from the date of its issue and is subject to the implementation of
both standard and specific environmental conditions, including the implementation of the
remediation plan and community& natural resource augmentation plan for past violations, as
safeguards to mitigate and manage environmental impacts. In addition, as per the Standard
Operating Procedure (SoP) dated 7th July 2021, penalty is also imposed on violation cases, to
the extent of 1% of the total project cost. Further, in case, such a project/activity has
commenced operations, an additional penalty of 0.25 % of the total turnover during the period
of violation is provided for.
The Hon’ble Supreme Court vide judgement dated 16.05.2025 in W.P. (C) 1394 of 2023 titled
Vanashakti vs. Union of India struck down the above mentioned Notification and OM.
However, the Hon’ble Supreme Court vide judgement dated 18.11.2025 has recalled the
judgement dated 16.05.2025 and has directed that the writ petitions and the appeal are restored
to file with the directions to the Registry to place the matter before the Chief Justice of India
on the administrative side for obtaining the necessary orders.
The Year-wise and State-wise details of the projects that have been accorded EC by the
Ministry at the central level under the Notification no. S.O. 804(E) dated 14th March 2017 and
SoP dated 07th July 2021 and amount recommended by the EAC for implementation of
remediation plan and natural & community resource augmentation plan is annexed.
*****Annexure
Year-wise and State-wise details of the projects that have been accorded EC by the Ministry at the central level under the violation category since
2021 under notification no 804 (E) dated 14.03.2017 and SoP dated 07.07.2021 and amount recommended by EAC for implementation of
Remediation Plan (R.P) & Natural & Community Resource Augmentation Plan (NCRAP)
2021 2022 2023 2024 2025
Cost for Cost for Cost for Cost for
No. of No. of No. of Cost for R.P No. of
R.P & No. of ECs R.P & R.P & R.P &
States/UTs ECs ECs ECs & NCRAP ECs
NCRAP granted NCRAP NCRAP NCRAP
granted granted granted In (Lakhs)* granted
In (Lakhs)* In (Lakhs)* In (Lakhs)* In (Lakhs)*
Chhattisgarh 1
23.16
Daman and
2
Diu 69.38
Goa 1
60.00
Gujarat 2 1 13.28
119.62
Haryana 2 63.07 2
71.72
Himachal
2 1 8.13
Pradesh 26.00
Jharkhand 2 4 4,289.43 1 1 318.08
1,688.68 56.44
Karnataka 2
184.16
Maharashtra 5 3
869.07 2699.99Orissa 1 1 1,480.83 2
4,921.00 176.22
Rajasthan 1
19.00
Tamil Nadu 1 1 355.9 1 606.94
61.40
Telangana 4 1 464.50 2 1 127.00
3,397.72 373.54
West Bengal 1 1 5,183.97
5,375.00
Total 23 16,731.03 12 11,859.11 12 3,461.07 2 733.94 1 318.08
*Cost for implementation of Remediation Plan (R.P) & Natural & Community Resource Augmentation Plan (NCRAP)