Official TranscriptGOVERNMENT OF INDIA MINISTRY OF ROAD TRANSPORT AND HIGHWAYS RAJYA SABHA UNSTARRED QUESTION NO. 3782 ANSWERED ON 25.03.2026 ROAD INFRASTRUCTURE DEVELOPMENT AND CONNECTIVITY ENHANCEMENT IN GOA 3782. SHRI SADANAND MHALU SHET TANAVADE: Will the Minister of ROAD TRANSPORT AND HIGHWAYS be pleased to state: (a) the details of all National Highway and major road infrastructure-projects sanctioned,...
GOVERNMENT OF INDIA MINISTRY OF ROAD TRANSPORT AND HIGHWAYS RAJYA SABHA UNSTARRED QUESTION NO. 3782 ANSWERED ON 25.03.2026 ROAD INFRASTRUCTURE DEVELOPMENT AND CONNECTIVITY ENHANCEMENT IN GOA
3782. SHRI SADANAND MHALU SHET TANAVADE:
Will the Minister of ROAD TRANSPORT AND HIGHWAYS be pleased to state:
(a) the details of all National Highway and major road infrastructure-projects sanctioned, underway or completed by the Ministry in Goa during last five years, including total project lengths, objectives and year-wise commencement and completionอพ
(b) the budgetary allocation and actual expenditure for each of these projects during the above period, with a head-wise breakup of funds released under successive Union Budgets and Centrally Sponsored Schemesอพ and
(c) whether the Ministry has considered innovative interventions such as ring roads, bypasses, grade-separated interchanges or eco-sensitive alignments to further enhance connectivity, reduce travel time and minimize environmental impact in sensitive-areas of the State, if so, the details thereof? ANSWER THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS (SHRI NITIN JAIRAM GADKARI)
(a) to (c) The development of National Highways (NHs) including the State of Goa is a continuous process and the requirement of construction of widening of roads, ring roads, bypasses, flyovers and grade-separated interchanges is assessed on case to case basis as per traffic requirements, available Right of Way (RoW), congestion in urban/built-up sections, road safety considerations, etc. at the time preparation of Detailed Project Reports (DPRs) and provisioned in the approved DPRs of NH works either as part of the NH Corridor or on standalone basis. The details of all NH development projects sanctioned, underway or completed in Goa during the last five years including current year is annexed.
The details of the funds allocated and expenditure incurred on the development of NHs in the state of
Goa are as under:
Year Allocation (Rs. in Crores) Expenditure (Rs. in Crores) 2020-21 734 734 2021-22 615 615 2022-23 673 673 2023-24 620 620 2024-25 851 651 2025-26 (till 28.02.2026) 730 612In addition to above, 7 works have also been approved at an estimated of Rs. 172.50 cr. for development of State roads under Central Road and Infrastructure Fund (CRIF) Scheme in Goa during the last five years including current year. Against this, year-wise allocation and release of funds to the
State Government is as under:
Year Allocation (Rs. in Crores) Release (Rs. in Crores) 2020-21 14.43 0 2021-22 13.41 0 2022-23 14.74 0 2023-24 15.61 48.16 2024-25 15.03 29.70 2025-26 (till 28.02.2026) 16.41 9.29ANNEXURE ANNEXURE REFERRED TO IN REPLY TO PART (a) to (c) OF RAJYA SABHA UNSTARRED QUESTION NO. 3782 ANSWERED ON 25.03.2026 ASKED BY SHRI SADANAND MHALU SHET TANAVADE REGARDING ROAD INFRASTRUCTURE DEVELOPMENT AND CONNECTIVITY ENHANCEMENT IN GOA.
Details of all NH development projects sanctioned, underway or completed in Goa during the last five years including current year S. Project Name NH Length Total Appointed Actual / Current status No. No. (km) Project Date Scheduled Cost (Rs. Completion Cr) Date FY 2020-21 1 Replacement 66 0 0 27-05-2022 03-02-2023 Completed existing elastomeric bearing of the New Mandovi bridge on NH-66 [Old NH- 17] 2 Urgent replacement 66 0 6.27 06-12-2021 31-03-2023 Completed of existing elastomeric expansion joints and bearings of the Old Mandovi Bridge on NH-17
(66) 3 Rehabilitation of 66 0 1.92 11-06-2021 31-03-2022 Completed Bhatpal Bridge at Km. 592.400 on NH-66 (old NH-17) 4 Repair of 66 0 8.58 26-07-2021 30-09-2022 Completed Orthophond bridge, Margao over bridge and Mashem bridge on NH-66 5 Strengthening from 66 2.5 10.47 02-08-2021 30-04-2023 Completed km 30/00 to 31/600, 33/400, to km 35/00 and km 37/500 to km 38/500 of NH- 66 6 Improvement of 66 0 47.85 14-06-2017 31-08-2020 Completed Old Goa โ Karmali junction at Ch.S. Project Name NH Length Total Appointed Actual / Current status No. No. (km) Project Date Scheduled Cost (Rs. Completion Cr) Date 144/080 along Ribandar bypass on NH4A (New 748) by providing vehicular underpass and appartunances 7 Construction of 566 0 13.29 28-09-2017 30-03-2021 Completed VUP at Km 3/500 on NH-17B.
8 Paved shoulders for 748 7.5 63.87 24-10-2017 12-03-2021 Completed Ribander bypass for NH-4A, Construction of Vehicular over pass
(VOP) & road safety measures Total 10 152.25 FY 2021-22 9 Construction of Six 166s 6.6 1183.16 11-04-2022 21-06-2024 Completed Lane link road (NH-166s) with Paved shoulder configuration to Mopa Airport on EPC Mode 10 Improvement of 748 0 1.93 31-08-2022 28-08-2023 Completed cross drainage and construction of protection wall for flood prone stretch from Km.98/00 to Km.99/00 on NH- 748 11 Construction of 748 0.84 58.25 31-10-2022 31-01-2026 Completed Bridge over Chimbel creek at Km 150/600 in a length of 200 mts and approaches in 100 mts length along Ribander bypass on NH-748S. Project Name NH Length Total Appointed Actual / Current status No. No. (km) Project Date Scheduled Cost (Rs. Completion Cr) Date 12 Rehabilitation of 66 0 2.01 17-01-2023 31-03-2024 Completed existing Zuari Bridge between chainage km.
531/00 to km.
532/00 along NH- 66 13 Providing utility 566 0 30.99 15-03-2023 14-02-2025 Completed corridor between Km.15/500 to Km.19/00 on NH- 566 14 Margao Western 66 11.9 354.43 29-12-2015 01-08-2021 Completed Bypass (Km 26/200 to km 38/100 NH-
17) 15 Construction of 66 3.85 229.09 16-11-2015 02-11-2021 Completed Verna Missing link between km Km 11/680 to Km 14/020 & widening of existing 2 lane road to 4 lane road between km 14/020 to km 15/520 on NH-17B 16 Widening to 4/6/8 66 8.23 819.95 08-06-2016 23-03-2022 Completed lanes of existing NH-17 (new NH-
66) from km 522/615 (near GMC) to km 530/850 joining new Zuari bridge (Package โ I) on EPC mode 17 Widening to 4/6 66 3.67 773.98 08-06-2016 31-03-2022 Completed lanes of existing NH-17 (new NH-
66) from km 531/934 (after Zuari bridge) to km 536/250 (Jn. With Verna IndustrialS. Project Name NH Length Total Appointed Actual / Current status No. No. (km) Project Date Scheduled Cost (Rs. Completion Cr) Date Zone) (Package โ III) on EPC mode 18 4-laning of NH-17 66 17.44 769.2 08-12-2017 31-03-2022 Completed from existing km
502.500 to km
514.830 and km
517.880 to km
522.790 19 Providing VUP at 748 0 32.37 13-12-2017 31-03-2022 Completed km. 146/00 of Ribander bypass on NH-4A 20 Construction of 748 0 13.45 01-12-2023 30-05-2025 Completed service road on the existing Ribander bypass from km
143.120 to km
152.800 km on NH- 748 21 Replacement of 748 0 1.83 14-01-2021 02-08-2021 Completed Bearing and strip seals of expansion joints of Banastarim Bridge at Km.139.200 on NH-748 Total 52.53 4270.64 FY 2022-23 22 Balance Work of 4- 748 0.75 126.64 21-08-2023 30-05-2025 Completed laning of NH-748 between km.118/00 to km.125/00 including construction of new Khandepar Bridge at Km.118/800 23 Construction of 66 0 1.71 31-08-2023 08-06-2024 Completed culvert on NH-66 Karaswada Bambolim section at Ch. 507.459 24 Rehabilitation of 66 0 0.54 21-08-2023 06-12-2023 CompletedS. Project Name NH Length Total Appointed Actual / Current status No. No. (km) Project Date Scheduled Cost (Rs. Completion Cr) Date Culvert at Km.
571/000 on NH-66 25 Slope stabilization 748 0 2.84 07-08-2023 31-03-2024 Completed work of slope and construction of breast wall/ toe wall in various stretches between Km. 84.00 to km. 97.00 on NH-748 26 Widening of NH- 366 1.1 18.06 17-09-2023 30-06-2026 Under 366(old NH-17A) implementation from Sada junction (Km. 14/90) to Gate No. 1 of MPT (Km.
16/00).
27 lmprovement to 66 0 1.78 11-07-2023 20-01-2024 Completed accident prone stretch from Km.
549/650 (Collectorate Building) to Km.
550/00 (KTC Bus Stand Margao) on NH-66 28 Urgent restoration 66 0 4.89 19-06-2023 31-03-2024 Completed to existing road formation of NH-66 between km 572/500 to Km595/200 29 Consultancy for 566 0 0.51 16-01-2023 12-03-2023 Completed structural health study of new Borim Bridge across Zuari river 30 4L from existing 66 25.5 769.52 08-05-2018 31-01-2023 Completed km 475.000 to
502.500 of NH-17 [Patradevi to Karaswada section] 31 Widening of narrow 66 0 5.98 15-06-2018 30-10-2022 Completed culverts at km 53/600, 58/800 &S. Project Name NH Length Total Appointed Actual / Current status No. No. (km) Project Date Scheduled Cost (Rs. Completion Cr) Date 60/00 of NH-17 32 Strengtheningkm.84 66 34 39.69 14-08-2020 31-10-2022 Completed /00 to km. 118/00 on NH-66 33 Strengthening 748 9.62 26.16 14-08-2020 30-06-2022 Completed Ribender bypass Km.143/200- 152/820 on NH-748 34 Road safety 748 0 2.43 14-10-2022 28-08-2023 Completed
Measures:
Improvement and providing crash barriers and other safety devices in isolated stretches on NH-748 Km.84/00 to Km.97/00 Total 70.97 1000.75 FY 2023-24 35 Construction of Six 66 5.15 641.46 15-04-2024 15-10-2026 Under lane Elevated implementation Corridor from Km.
508.000 to Km.
513.150 including approaches on NH- 66 36 Strengthening of 366 10 19.42 15-02-2024 25-03-2025 Completed NH-366 from Km.
0.00 (Cortalim Junction) to Km.
10.00 (Chicalim Circle) on EPC Mode 37 Rahabilitation of 6 66 0 2.95 19-02-2024 13-01-2025 Completed Nos. of culverts between Km.
570.000 to Km.584.715 on NH-66 38 Improvement to 66 0 1.3 19-02-2024 16-08-2024 Completed Accident Spot of Colva Circle Junction at KmS. Project Name NH Length Total Appointed Actual / Current status No. No. (km) Project Date Scheduled Cost (Rs. Completion Cr) Date 550/700 on NH-56 39 Strengthening 748 7 37.69 07-03-2024 03-03-2025 Completed between Km 118/00 to Km 125/00 (Khandeapar to Safa Masjid Ponda) of NH-748 40 Strengthening of 566 4 22.22 26-02-2024 14-10-2024 Completed NH-566 from Km
0.00 to Km 4.00 (Dhavali bypass) 41 Replacement of 748 0 2.87 16-03-2024 30-11-2024 Completed wearing coat and painting to the Banastari Bridge at Km. 139/200 on NH-748 42 Restoration of 3 748 0 2.96 16-03-2024 12-03-2025 Completed Nos. of minor bridges between Km 93/650 to Km 94/500 on NH-748 43 Dismantaling of 66 0 3.82 16-02-2024 30-05-2025 Completed pipe culverts and construction of box culverts at ch.
518/800 kms. & 519/650 km on NH- 66 44 Reconstruction and 748A 0 8.76 20-02-2024 01-03-2025 Completed repairs of existing A Old Masonry Culverts between Km 0/00 to Km 27/00 on NH- 748AA on EPC mode 45 Rectification of 66 3.8 41.15 11-03-2024 06-03-2026 Completed blackspot lD No.
018 and 019 (Verna to Nuvem Section) on NH-66S. Project Name NH Length Total Appointed Actual / Current status No. No. (km) Project Date Scheduled Cost (Rs. Completion Cr) Date 46 Rectification of 566 0 2.1 07-03-2024 30-04-2025 Completed blackspot ID No.
025 from km 7/250 (Borim Sakhav) to Km 7/750 (Saibaba Temple) on NH- 566 47 Strengthening and 566 0 20.67 17-03-2024 28-02-2026 Completed rehabilitation of Borim Bridge across river Zuari on NH-S66 48 Rectification of 66 0 3.87 06-03-2024 31-01-2025 Completed Blackspot ID No.
026 at Km 583/600 (Bhumipurush Temple), accident spot at Km 585/400 (Palolem Junction) and road safety measures between Km 576/500 to Km 578/00 on NH-66 49 Rectification of 748 0 37.12 14-03-2024 30-05-2025 Completed Blackspots and Accident Spots on NH- 748 between Km 84.00 to Km
143.200 50 Improvement of 566 1.16 12.53 03-09-2024 31-03-2026 Under existing โSโ curves implementation between Km 13/570 to Km 14/500 on NH-566 51 One time 66 2.39 6.51 19-09-2024 15-03-2025 Completed improvement of bypassed sections between Km
485.300 to Km
485.800 and Km
486.600 to Km
487.950 on NH-66 52 Overlaying of 66 0 7.18 19-09-2024 08-04-2025 Completed carpet along withS. Project Name NH Length Total Appointed Actual / Current status No. No. (km) Project Date Scheduled Cost (Rs. Completion Cr) Date safety measures and painting for New and Old Mandovi bridge on NH-66 53 Construction of 66 0 6.7 05-12-2025 05-06-2026 Under Foot Over Bridge implementation
(FOB) near Holy Shrine, Bambolim at Km 524.330 on NH-66 54 Construction of 4 566 4.17 471.98 01-08-2024 31-05-2027 Under Lane Flyover from implementation MES College Junction to Bogmalo Junction on NH-566 from km 7.106 to km
10.460 and 4 lane VUP at Queeny Nagar Junction from km 3.330 to km 4.550 on EPC Mode 55 Construction of 66 1.08 936.41 11-04-2016 30-08-2023 Completed bridge including approaches across river Zuari on NH- 17 (New NH-66) (Pkg. II Km 530/850 to km 531/934 on EPC mode) Total 38.75 2289.67 FY 2024-25 56 4-Laning from End 66 6.65 398.25 Yet to start 15-02-2028 Yet to start of Zuari approaches to Start of Margao Bypass section of NH-66 from Km
536.800 to Km
543.450 57 Construction of 66 0 18.65 21-01-2025 31-05-2026 Under temporary and implementationS. Project Name NH Length Total Appointed Actual / Current status No. No. (km) Project Date Scheduled Cost (Rs. Completion Cr) Date permanent Toll Plaza at Km
476.500 of NH-66 58 Rectification of 66 0 16.64 21-01-2025 31-05-2026 Under blackspot No. GA- implementation
(03)-006 at Balli and No. GA-(06)- 005 at Cuncolim Bus Stand including Road Safety measures from Km
562.00 to Km
570.00 on NH-66 59 4-laning of Ponda 748 9.61 557.14 Yet to start 31-12-2028 Yet to start to Bhoma Section of NH-748 from km
125.440 to Km
135.050 on EPC Mode 60 Improvement of St. 366 0 3.49 17-02-2025 31-05-2026 Under Andrewโs junction, implementation Vasco at Km
11.350 on NH-366 61 4-laning of Navelim 66 7.23 746.75 Yet to start 31-12-2028 Yet to start to Cuncolim
Section of NH-66 from Km 554.245 to Km 561.480 on HAM Mode 62 Construction of 66 1 45.31 23-05-2025 23-11-2026 Under Flyover at Dhargal implementation from Km 494.418 to Km 494.548 on NH-66 63 Construction of 66 0.74 44.17 13-10-2025 13-04-2027 Under Vehicular implementation Underpass (VUP) including approaches near Peddem junction at Km. 502.327 of NH-66S. Project Name NH Length Total Appointed Actual / Current status No. No. (km) Project Date Scheduled Cost (Rs. Completion Cr) Date 64 Construction of 66 0.75 50 28-11-2025 28-05-2027 Under VUP including implementation approaches near Naibag at Km
485.345 on NH-66 65 Urgent protection to 66 0 31.77 14-01-2026 14-12-2026 Under Hill side slope implementation between Km 532/300 to Km 535/600 on NH- 66 66 Four Laning of 66 22.1 1376.12 Yet to start 31-12-2028 Yet to start Benordem โ Start of Canacona Bypass (km 570.190 to km584.880) and End of Canacona Bypass to Pollem (km 602.890 to km
610.300) section of NH-66 on Hybrid Annuity Mode 67 4-laning of Boma to 748 7 1060.21 Yet to start 31-12-2028 Yet to start Old Goa Section of NH-748 from Km
135.050 to Km.
142.050 on HAM.
68 Construction, 566 7.52 397 14-10-2015 27-01-2025 Completed Operation and maintenance of Balance Works for 4 laning of the stretch of NH-17B from Varunapuri to Sada Junction from km 13.100 to km
18.300 and elevated road cum flyover cum ROB from Ravindra Bhavan Junction to gate no.09 of the MPT including its loop connectivity ramps Total 62.6 4745.5S. Project Name NH Length Total Appointed Actual / Current status No. No. (km) Project Date Scheduled Cost (Rs. Completion Cr) Date FY 2025-26 69 One time 66 1.5 1.75 31-10-2025 30-04-2026 Under improvement to implementation bypassed section of NH-66 at Siridao from Km 524.700 to Km 526.200 70 Rectification of 566 1.61 24.5 Yet to start 30-06-2027 Yet to start Black spot along NH-566 from Baithakhol circle to Sakav (5/00 to 7/00) at Borim.
And Km. 0/00 to 12/200 71 Permanent slope 66 0 14.11 Yet to start 30-06-2027 Yet to start protection measures at landslide prone location from Km
486.825 to Km
487.095 at Malpem on NH-66 72 Road Safety 566 13.1 2.8 01-04-2023 30-11-2024 Completed Measures and Operation and Maintenance of NH-17B from Km.0.000 (Verna Junction) to Km.13.100 (Varunapuri Junction) 73 Road Safety 566 13.1 2.82 01-12-2024 31-03-2026 Under Measures and implementation Operation and Maintenance of NH-17B from Km.0.000 (Verna Junction) to Km.13.100 (Varunapuri Junction) Total 29.31 45.98S. Project Name NH Length Total Appointed Actual / Current status No. No. (km) Project Date Scheduled Cost (Rs. Completion Cr) Date Gross Total 264.16 12,504.79 *****