GOVERNMENT OF INDIA
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
LOK SABHA
UNSTARRED QUESTION NO. 889
ANSWERED ON 23RD JULY, 2026
ROAD PROJECTS IN MAHARASHTRA
889. DR. AMOL RAMSING KOLHE:
Will the MINISTER OF ROAD TRANSPORT AND HIGHWAYS
सड़क परिवहन औि िाजमार्ग मंत्री
be pleased to state:
(a) whether the Government has reviewed the proposed High-Speed
and High-Density Corridors and Build-Operate-Transfer (BOT) National
Highway projects in Maharashtra;
(b) the details of such projects proposed, approved and under
implementation in the State, including district-wise alignment and
estimated cost;
(c) whether these projects are expected to improve connectivity to
industrial clusters, ports, agricultural markets and backward regions of
Maharashtra, if so, the details thereof;
(d) the timeline fixed for land acquisition, award of contracts and
completion of the projects; and
(e) the measures taken by the Government to ensure timely execution,
adequate financing and resolution of bottlenecks so as to accelerate
economic growth and reduce logistics costs in Maharashtra?
ANSWER
THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS
(SHRI NITIN JAIRAM GADKARI)
(a) The Government has established a framework for regular review of
the progress of all on-going National Highways (NHs) works including
High-Speed and High-Density Corridors and Build-Operate-Transfer (BOT)
projects. This involves review at site, State and Central Government
level involving all stakeholders including the State Government.
(b) to (d) The status of High-Speed and High-Density Corridors and
Build-Operate-Transfer (BOT) National Highway projects sanctioned by
the Central Government for improving the connectivity to industrialclusters, ports, agricultural markets and backward regions of
Maharashtra is as under:
S. Details Length Sanctione Districts Present status
No (km) d cost covered
. (Rs. in
crores)
1 Vadodara- 149.60 10,556.02 Palghar, Thane Under
Mumbai implementation
Expressway with target for
completion on
31.08.2026
2 Akkalkot – 36.40 872.17 Solapur Under
Maharashtra- implementation
Karnataka with target for
Border completion on
31.08.2026
3 6-laning of 140.35 1724.55 Pune, Satara Under
Pune-Satara implementation
section of with target for
NH-48 on completion on
BOT 31.12.2026
4 4-laning of 100.06 923.04 Solapur, Under
Solapur- Dharashiv implementation
Maharashtra- with target for
Karnataka completion on
Border of NH- 31.12.2026
65 on BOT
5 6-laning of 67.00 1749.86 Satara, Kolhapur Under
Satara-Kagal implementation
section of with target for
NH-48, Pkg-II completion on
on BOT 31.12.2026
6 Development 20.00 7801.00 Pune Under bidding.
of Nashik Target for
Phata-Alandi completion in FY
Phata-Khed 2030-31
(NH-60) on
BOT
7 Development 29.00 4377.00 Raigad Under bidding.
of Pagote
Chowk (NH-348B) on
BOT
8 Connectivity 32.00 4384.00 Palghar Work awarded.
to Vadhawan Target for
Port section completion in FY
of NH-248S 2029-30
9 Nashik- 374.00 19,142.00 Nashik, Under bidding.
Ahmednagar- Ahilyanagar,
Solapur- Beed, Dharashiv,
Akkalkot on Solapur
BOT
(e) The Government has taken number of steps to ensure timely
completion of NH projects. These include streamlining and expediting
land acquisition using “Bhoomirashi” portal and GIS-based Land
Acquisition Plan, revamping “Parivesh” Portal through Ministry of
Environment, Forest and Climate Change, to facilitate faster forest and
environmental clearances, enabling online approval of General
Arrangement of Drawings (GAD) of Road Over Bridge / Road Under Bridge
(ROB/RUB) from the Railways, and leveraging the mechanism of review
and resolution of bottlenecks / hindrances in active collaboration with
the State Governments and other stakeholders. The support of State
Government of Maharashtra has been specifically sought to expedite
land acquisition and other statutory clearances. Government has also
launched a web portal for Railway related clearances with defined
timelines for various approvals.
Government has put in place a strong framework using multiple
mechanisms for monitoring project progress and contractor
inefficiencies. Regular review meetings are conducted at various levels
with stakeholders to assess project progress, and critical projects such
as those delayed by more than three years or pending for award /
appointment.
Many State Governments conduct coordination meetings led by the
Chief Secretary to resolve issues affecting project execution. Projects
where issues remain unresolved are escalated for further review through
the Project Monitoring Group.
*****