GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
RAJYA SABHA
STARRED QUESTION NO. 163
ANSWERED ON 13.02.2026
ROADMAP TO IMPROVE AVERAGE SPEED OF TRAINS
*163 SHRI VIVEK K. TANKHA:
Will the Minister of RAILWAYS be pleased to state:
(a) despite network expansion, electrification and substantial capital investment, the reasons for most
Indian passenger and express trains continue to operate at low average speeds, often well below
global and even regional benchmarks;
(b) the key constraints—track quality, signalling systems, congestion or mixed freight- passenger
traffic—that prevent achieving an average speed of at least 120 km/h on major routes;
(c) the number of routes that currently meet the technical standards required for such speeds; and
(d) the time-bound roadmap prepared by Government to upgrade infrastructure, rationalise timetables
and decongest corridors to significantly improve average train speeds across the network?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (d): A Statement is laid on the Table of the House.
*****
§STATEMENT REFERRED TO IN REPLY TO PARTS (a) TO (d) OF STARRED QUESTION
NO.163 BY SHRI VIVEK K. TANKHA ANSWERED IN RAJYA SABHA ON 13.02.2026
REGARDING ROADMAP TO IMPROVE AVERAGE SPEED OF TRAINS
(a) to (d) Upgradation and improvement of railway tracks and signalling on Indian Railways to increase
the speed potential have been carried out in a big way during last 11 years. Improvement of track
infrastructure is a continuous and ongoing process over Indian Railways. The following measures are
being taken by Indian Railways to upgrade railway tracks, signalling etc.:
i. Modern track structure consisting of 60kg, 90 Ultimate Tensile Strength (UTS) rails, Wider and
heavier Pre-stressed Concrete Sleepers (PSC) with elastic fastening, fan-shaped layout turnout on
PSC sleepers and H-beam Sleepers on girder bridges are being used while carrying out primary
track renewals.
ii. The Thick Web Switches and Weldable CMS Crossings are being used in turnout renewal works.
iii. Supply of 260m long rail panels have been increased to avoid welding of joints, thereby
improving safety and riding quality.
iv. Thick Web Switch Expansion Joints are being used in place of earlier Conventional/Improved
SEJs.
v. Adoption of better welding technology for rails i.e. Flash Butt Welding.
vi. Adoption of mechanized system for track maintenance using high output plain tampers and
points & crossing tampers for improved maintainability & reliability of track.
vii. Deployment of state-of-the-art modern machines including Rail Grinding Machines to further
improve asset reliability.
viii. Mechanisation of track laying activities through use of track machines like PQRS, TRT, T-28 etc.
ix. Use of advanced Phased Array technology of testing of rail and welds.
x. Deployment of Integrated Track Monitoring Systems (ITMS) and Oscillation Monitoring System
(OMS) for comprehensive health assessment to ascertain optimal maintenance requirements.
xi. Using web enabled Track Management System (TMS) for integration and data analytics of the
track inspection records received through various sources to enable precise maintenance inputs.
xii. Electrical/Electronic Interlocking Systems with centralized operation of points and signals in
place of old mechanical signalling have been provided at 6660 stations as on 31.12.2025.
xiii. Interlocking of Level Crossing Gates (LC) has been provided at 10097 Level Crossing Gates upto
31.12.2025 for enhancing safety at LC Gate.
xiv. Axle counters for automatic clearance of Block Section, BPAC (Block Proving Axle Counter) are
provided to ensure complete arrival of train without manual intervention before granting line
clear to receive next train and to reduce human element. These systems have been provided on
6142 Block Sections up to 31.12.2025.
§xv. Automatic Block Signalling (ABS) that enhances line capacity within existing track infrastructure
has been provided at 6625 Route km upto 31.12.2025.
xvi. Indian Railways has also gone for implementation of indigenously developed Automatic Train
Protection (ATP) system which required safety certification of highest order. Kavach has also
been adopted as a National AT system in July 2020. After extensive and elaborate trials, Kavach
version 4.0 has been successfully commissioned on 1297 Route Kilometres, covering the high
density Delhi - Mumbai and Delhi - Howrah routes. On the Delhi - Mumbai route Kavach ver 4.0
has been commissioned on Junction cabin - Palwal - Mathura - Nagda section (667 Rkm) &
Ahmedabad - Vadodara - Virar section (432 Rkm) and on the Delhi - Howrah route on Gaya -
Saramatan (93 Rkm) and Bardhaman - Howrah section (105 Rkm).
xvii. Complete Track Circuiting of stations to enhance safety by verification of track occupancy by
electrical means has been provided at 6,665 stations up to 31.12.2025.
xviii. All unmanned level crossings (UMLCs) on Broad Gauge (BG) route have been eliminated by
January 2019.
As a result of above measures, there has been significant increase in speed potential of the tracks. The
details of speed potential of railway tracks during 2013-14 vis-a-vis 2025-26 are as under:
2013-14 2025-26 (up to Jan’26)
Sectional Speed
(kmph)
Track Km % Track Km %
130 & above 5,036 6.3 23,477 22.2
110 - 130 26,409 33.3 61,711 58.4
< 110 47,897 60.4 20,484 19.4
Total 79,342 100 1,05,672 100
On Indian Railways, the average speed of the train services is dependent inter alia on the Maximum
Permissible Speed (MPS) of the sections, track structure, geometry along the route including gradients
and curves, topographical conditions, number of stoppages enroute, line capacity utilisation of
sections, maintenance works in the section etc. Accordingly, the train services have been charted at the
Maximum Permissible Speed of the respective sections over which the trains are being operated.
Further, speeding-up of train services is an on-going process on Indian Railways.
§The details of the works related to better maintenance practices, Technological improvements, better
infrastructure and rolling stock etc. undertaken by Railways are tabulated below:-
S.N. Item 2004-05 to 2014-15 to 2014-25 Vs.
2013-14 2024-25 2004-14
Technological Improvements
1. Use of high-quality 57,450 Km 1.43 Lakh More than 2
rails (60 Kg) (Km) Km times
2. Longer Rail Panels 9,917 Km 77,522 Km Nearly 8
(260m) (Km) times
3. Electronic 837 Stations 3,691 More than 4
Interlocking Stations times
(Stations)
4. Fog Pass Safety As on As on 288 times
Devices (Nos.) 31.03.14: 31.03.25:
90 Nos. 25,939 Nos.
5. Thick Web Nil 28,301 Nos.
Switches (Nos.)
Better Maintenance Practices
1. Primary Rail 32,260 Km 49,941 Km 1.5 times
Renewal(Track Km)
2. USFD (Ultra Sonic 79.43 Lakh 2 Crore More than 2
Flaw detection) times
Testing of Welds
(Nos.)
3. Weld failures (Nos.) In 2013-14: In 2024-25: 90 %
3699 Nos. 370 Nos. reduction
4. Rail fractures In 2013-14: In 2024-25: More than
(Nos.) 2548 Nos. 289 Nos. 88%
reduction
Better Infrastructure and Rolling Stock
1. New Track KM 14,985 Km 34,428 Km More than 2
added (Track Km) times
2. Flyovers (RoBs)/ 4,148 Nos. 13,808 Nos. More than 3
Underpasses times
(RUBs) (Nos.)
3. Unmanned Level As on As on Removed
crossings 31.03.14: 31.03.24: Nil
(Nos.) on BG 8,948 (All
eliminated by
31.01.19)
4. Manufacture of 2,337 Nos. 42,677 More than 18
LHB Coaches (Nos.) times
§To improve capacity of existing network, several capacity enhancement/ augmentation survey/ works
have been sanctioned by railways. These works include multi-tracking, rail flyovers, by pass lines,
yard remodelling works etc
As on 01.04.2025, across Indian Railways, 431 Railway infrastructure projects (154 New line, 33
Gauge Conversion and 244 Doubling) of total length 35,966 Km, costing approx. 6.75 lakh crore are
sanctioned.
Zone-wise/year-wise details of all Railway projects are made available in public domain on Indian
Railway’s website.
The details of commissioning/laying of new track across Indian Railways is given below:-
Period New track commissioned Average commissioning of new tracks
2009-14 7,599 Km 4.2 Km/day
2014-25 34,428 Km 8.6 Km/day (more than 2 times)
During last 3 years (2022-23, 2023-24, 2024-25) and current Financial Year 2025-26, 973 no. Surveys
(291 New line, 13 Gauge Conversion and 669 Doubling) of total length 66,639 Km have been
sanctioned across Indian Railways.
Sanction of any railway project depends upon many parameters/ factors which include the following:
• Anticipated traffic projections and remunerativeness of the proposed route
• First and last mile connectivity provided by the project
• Connection of missing links and providing additional route
• Augmentation of congested/saturated lines
• Demands raised by State Governments/Central Ministries/Public representatives,
• Railway’s operational requirements
• Socio-economic considerations
• Overall availability of funds
*****
§