GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 579
TO BE ANSWERED ON 22.07.2026
ROBS AND RUBS IN HAZARIBAGH
579. SHRI MANISH JAISWAL:
Will the Minister of RAILWAYS be pleased to state:
(a) the details of Railway Over Bridges (ROBs) and Railway Under Bridges
(RUBs) sanctioned, under construction and completed in the Hazaribagh
Lok Sabha Constituency during the last five years, year and project-
wise; and
(b) the expected time of completion of the pending projects?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) & (b): Sanctioning of works of Road over Bridge (ROB)/Road under
Bridge (RUB) in lieu of Level crossings (LCs) is a continuous and dynamic
process of Indian Railway. Such works are prioritised and taken up on the
basis of their impact on safety in train operations, mobility of trains &
impact for road users and feasibility etc.
No. of ROBs/ RUBs constructed on Indian Railways during the period
2004-14 viz-a-viz 2014-26 (Upto May’26) is as under:
Period ROBs/ RUBs constructed
2004-14 4,148 Nos.
2014-26 (Upto May’26) 14,451 Nos. (504 Nos. in
the State of Jharkhand)
§ Page 1 of 4As on 01.04.2026, Indian Railways has 15,689 Nos. of Manned Level
Crossings (MLCs) on Broad Gauge (BG). Of these, 298 Nos. MLCs are
situated in the State of Jharkhand, including 17 Nos. MLCs falling within
the Hazaribagh Lok Sabha Constituency.
As on 01.06.2026, 4,993 Nos. ROB/ RUB works are sanctioned on Indian
Railways at an approximate cost of ₹ 1,17,492 Cr. Of these, 147 Nos.
ROB/RUB works at an approximate cost of ₹ 2,964 Cr are in the State of
Jharkhand including 14 Nos. of ROB/RUB works in Hazaribagh Lok Sabha
Constituency which are at various stages of planning and execution. The
details are as below:
S.No. LC Details ROB/RUB Cost of Remarks
work (₹
in Cr
approx.)
1 LC No. 26/Spl/T at ROB 87 Land Acquisition has
km 80/1-2 on been taken up.
Chainpur-
Karmahat
2 LC No 1/C/E at RUB 5 Site feasibility
starting of siding examination taken
on Dugda- up for preparation of
Chandrapura & GAD.
West Bokaro
Siding section
3 LC No. 39/Spl/T at ROB 38 Construction work
km 120/3-4 on has been taken up.
Bhurkunda-Patratu
Page 2 of 44 LC No. 30/C/E at RUB 4 Site feasibility
Km 87/10-11 on examination taken
Gomoh-Barkakana up for preparation of
section GAD.
5 LC No.2/B/T at Km RUB 4 GAD work has been
0/15-1/1 on Patratu- taken up.
Damodar
6 Non LC location at RUB 9 Railway portion has
km 103/7-9 near been completed.
Barkakana yard Approach work has
been taken up.
7 LC No. 38/1/C/E on RUB 4 Site feasibility
Gomoh-Barkakana examination taken
section up for preparation of
GAD.
8 Non LC location at RUB 11 The work of Detailed
km 101/15-15A Estimate has been
near Barkakana taken up.
yard
9 Non LC location at RUB 5 The works of GAD
km 94/9-11 on and Detailed
Ranchi road - Estimate have been
Arigada section taken up.
10 LC No. 1/C/E on RUB 4 Site feasibility
Gomoh-Patratu examination taken
section up for preparation of
GAD.
Page 3 of 411 LC No. 21 at km ROB 35 Combined GAD has
383/16-17 on Muri - been approved.
Barkakana section Tender has been
awarded.
12 LC No.37/1/A/T at RUB 4 Site feasibility
Km 113/9-10 on examination taken
Barkakana-Garhwa up for preparation of
road section GAD.
13 LC No. 31 at Km RUB 15 The works of GAD
396/13-14 on Muri - and Detailed
Barkakana section estimate have been
taken up.
14 Bhurkunda siding RUB 4 Site feasibility
on Gomoh- examination taken
Barkakana section up for preparation of
GAD.
Completion & commissioning of ROB/RUB works depends on various
factors like cooperation of State Governments in giving consent for
closure of LC, fixing of approach alignment, approval of General
Arrangement Drawing (GAD), land acquisition, removal of encroachment,
shifting of infringing utilities, statutory clearances from various
authorities, law and order situation in the area of project / work sites,
duration of working season in a year for the particular project / area due to
climatic conditions etc. All these factors affect the completion time of the
projects / works.
*****