GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
RAJYA SABHA
UNSTARRED QUESTION NO. 3314
ANSWERED ON 20.03.2026
SAFETY, CAPACITY AND PASSENGER WELFARE
3314 SHRI VIVEK K. TANKHA:
Will the Minister of RAILWAYS be pleased to state:
(a) the reasons as to why do safety lapses, overcrowding and service disruptions continue to affect
Indian Railways, despite record capital expenditure and infrastructure expansion;
(b) number of independent safety audits that have been conducted in the last three years;
(c) the status of track renewal and signalling upgrades; and
(d) manner in which passenger safety, affordability and service quality will be safeguarded amid
increasing private participation?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (d) : Safety is accorded the highest priority on Indian Railways. Regular Safety Inspections of
Track, OHE, Signalling assets, Rolling stock, etc are carried out by designated officials and necessary
action is taken accordingly. As a consequence of various safety measures taken over the years, there has
been a steep decline in the number of accidents.
Number of Consequential Train Accidents has reduced as shown in the table below:-
Year Consequential Accidents
2014-15 135
2025-26 (upto 28.02.2026) 14 (90% lesser)
Another important index showing improvement in safety in train operations is Consequential Accident
Index, the details of which are as under:-
Consequential Accident Index:-
Year Accident Index
2014-15 0.11
2024-25 0.03 (73% lesser)
§This index measures number of consequential accidents as a ratio of total running kilometers of all trains.
Accident Index =
234
165
135
55
31
14
2005-06 2009-10 2014-15 2019-20 2024-25 2025-26
(Feb 2026)
The various safety measures taken to enhance safety in train operations are as under:-
1. On Indian Railways, the expenditure on Safety related activities has increased over the years as
under:-
Expenditure/Budget on Safety related activities (Rs. in Cr.)
2013-14 2022-23 2023-24 2024-25 2025-26 2026-27
39,200 87,336 1,01,662 1,14,022 1,17,693 1,20,389
2. Electrical/Electronic Interlocking Systems with centralized operation of points and signals have
been provided at 6,665 stations up to 28.02.2026 to reduce accidents due to human failure.
3. Interlocking of Level Crossing (LC) Gates has been provided at 10,153 Level Crossing Gates up to
28.02.2026 for enhancing safety at LC Gates.
4. Complete Track Circuiting of stations to enhance safety by verification of track occupancy by
electrical means has been provided at 6,669 stations up to 28.02.2026.
stnediccA
niarT
laitneuqesnoC
fo
.oN
No. of consequential accidents
No. of trains X million kilometers run5. Indian Railways has gone for implementation of indigenously developed Automatic Train
Protection (ATP) system, which required safety certification of highest order (SIL 4). Kavach has
been adopted as a National ATP system in July 2020. Based on deployment of Kavach version 3.2
on 1465 RKm on South Central Railway and experience gained, further improvements were made.
Finally, Kavach specification version 4.0 was approved by RDSO on 16.07.2024. After extensive
and elaborate trials, Kavach Version 4.0 has been successfully commissioned on 1,452 Route
Kilometres, covering the high density Delhi - Mumbai and Delhi - Howrah routes as below:
S.N. Section Progress Route (Km)
(1) Delhi-Mumbai route:
i Junction cabin – Palwal – Mathura –Nagda section 667
ii Vadodara - Ahmedabad section 96
iii Vadodara - Virar section 336
(2) Delhi – Howrah route:
i Gaya Sarmatanr section 93
ii Chota Ambana - Bardhaman – Howrah section 260
Further, track side Kavach implementation work has been taken up on 24,427 RKM covering all
GQ, GD, HDN and identified sections of Indian Railways.
6. Detailed instructions on issues related with safety of Signalling, e.g. mandatory correspondence
check, alteration work protocol, preparation of completion drawing, etc. have been issued.
7. System of disconnection and reconnection for S&T equipment as per protocol has been re-
emphasized.
8. All locomotives are equipped with Vigilance Control Devices (VCD) to improve alertness of Loco
Pilots.
9. Retro-reflective sigma boards are provided on the mast which is located two OHE masts prior to
the signals in electrified territories to alert the crew about the signal ahead when visibility is low
due to foggy weather.
10. A GPS based Fog Safety Device (FSD) is provided to loco pilots in fog affected areas which
enables loco pilots to know the distance of the approaching landmarks like signals, level crossing
gates, etc.
11. Modern track structure consisting of 60kg, 90 Ultimate Tensile Strength (UTS) rails, Prestressed
Concrete Sleeper (PSC) Normal/Wide base sleepers with elastic fastening, fan shaped layout
turnout on PSC sleepers, Steel Channel/H-beam Sleepers on girder bridges is used while carrying
out primary track renewals.
§12. Mechanisation of track laying activity through use of track machines like PQRS, TRT, T-28 etc. to
reduce human errors.
13. Maximizing supply of 130m/260m long rail panels for increasing progress of rail renewal and
avoiding welding of joints, thereby improving safety.
14. Ultrasonic Flaw Detection (USFD) testing of rails to detect flaws and timely removal of defective
rails.
15. Laying of longer rails, minimizing the use of Alumino Thermic Welding and adoption of better
welding technology for rails i.e., Flash Butt Welding.
16. Monitoring of track geometry by OMS (Oscillation Monitoring System) and TRC (Track
Recording Cars).
17. Patrolling of railway tracks to look out for weld/rail fractures.
18. The use of Thick Web Switches and Weldable CMS Crossing in turnout renewal works.
19. Inspections at regular intervals are carried out to monitor and educate staff for observance of safe
practices.
20. Web based online monitoring system of track assets viz. Track database and decision support
system has been adopted to decide rationalized maintenance requirement and optimize inputs.
21. Detailed instructions on issues related with safety of Track, e.g. integrated block, corridor block,
worksite safety, monsoon precautions, etc. have been issued.
22. Preventive maintenance of railway assets (Coaches & Wagons) is undertaken to ensure safe train
operations.
23. Replacement of conventional ICF design coaches with LHB design coaches is being done.
24. All unmanned level crossings (UMLCs) on Broad Gauge (BG) route have been eliminated by
January 2019.
25. Safety of Railway Bridges is ensured through regular inspection of Bridges. The requirement of
repair/rehabilitation of Bridges is taken up based upon the conditions assessed during these
inspections.
26. Indian Railways has displayed Statutory “Fire Notices” for widespread passenger information in
all coaches. Fire posters are provided in every coach so as to educate and alert passengers
regarding various Do’s and Don’ts to prevent fire. These include messages regarding not carrying
any inflammable material, explosives, prohibition of smoking inside the coaches, penalties etc.
27. Production Units are providing Fire detection and suppression system in newly manufactured
Power Cars and Pantry Cars, Fire and Smoke detection system in newly manufactured coaches.
Progressive fitment of the same in existing coaches is also underway by Zonal Railways in a
phased manner.
28. Regular counselling and training of staff is undertaken.
§29. Concept of Rolling Block introduced in Indian Railways (Open Lines) GeneralRules vide Gazette
notification dated 30.11.2023, wherein work of integrated maintenance/repair/replacement of
assets is planned up to 52 weeks in advance on rolling basis and executed as per plan.
The details of the Safety related works related to better maintenance practices, Technological
improvements, better infrastructure and rolling stock etc. undertaken by Railways are tabulated below:-
2004-05 to 2014-15 to 2014-25 Vs.
S.N. Item
2013-14 2024-25 2004-14
Technological Improvements
1. Use of high-quality rails 57,450 Km 1.43 Lakh Km More than
(60 Kg) (Km) 2 times
2. Longer Rail Panels 9,917 Km 77,522 Km Nearly 8 times
(260m) (Km)
3. Electronic Interlocking 837 Stations 3,691 Stations More than
(Stations) 4 times
4. Fog Pass Safety Devices As on 31.03.14: As on 31.03.25: 288 times
(Nos.) 90 Nos. 25,939 Nos.
5. Thick Web Switches (Nos.) Nil 28,301 Nos.
Better Maintenance Practices
1. Primary Rail Renewal 32,260 Km 49,941 Km 1.5 times
(Track Km)
2. USFD (Ultra Sonic Flaw 79.43 Lakh 2 Crore More than
detection) Testing of Welds 2 times
(Nos.)
3. Weld failures (Nos.) In 2013-14: 3699 In 2024-25: 90% reduction
Nos. 370 Nos.
4. Rail fractures (Nos.) In 2013-14: 2548 In 2024-25: More than
Nos. 289 Nos. 88% reduction
Better Infrastructure and Rolling Stock
1. New Track KM added 14,985 Km 34,428 Km More than
(Track Km) 2 times
2. Flyovers 4,148 Nos. 13,808 Nos. More than
(RoBs)/Underpasses 3 times
(RUBs) (Nos.)
3. Unmanned Level crossings As on 31.03.14: As on 31.03.24:Nil Removed
(Nos.) on BG 8,948 (All eliminated by
31.01.19)
4. Manufacture of LHB 2,337 Nos. 42,677 More than
Coaches (Nos.) 18 times
NON-AC COACHES (GENERAL AND SLEEPER COACH)
With a view to meet the demand of passengers travelling in unreserved coaches, Railways have
significantly increased the facilities for passengers demanding general class travel. During the last
financial year 2024-25 alone, 1250 general coaches have been utilised in various long-distance trains.In
§the current financial year (upto February, 2026), 860 Coaches have been utilised for permanent
augmentation.
To cater to the travel demand of the low and middle income families, Indian Railways have taken up
manufacturing of 17,000 non-AC coaches (general/sleeper).
On IR, the percentage of non-AC coaches, is about 70% as indicated below:
Table 1: Distribution of coaches:
Non-AC coaches (general and sleeper) ~62,000 ~70%
AC coaches ~27,000 ~30%
Total coaches ~89,000 100%
Due to higher availability of general coaches, the number of passengers travelling in general/
unreserved coaches has shown an increasing trend as shown below:
Table 2: Passengers in general/unreserved coaches:
Year No. of Passengers
2020-21 99 Cr (Covid year)
2021-22 275 Cr (Covid year)
2022-23 553 Cr
2023-24 609 Cr
2024-25 651 Cr
The number of seats available for non-AC passengers has also increased. The current composition is
as follows:
Table 3: Distribution of seats:
Non-AC seats ~ 54 lakhs ~ 78%
AC seats ~ 15 lakhs ~ 22%
Total ~ 69 lakhs 100%
Moreover, to provide greater accommodation for the passengers using General and non-AC Sleeper
Coaches, the extant policy regarding composition of Mail/Express trains provides for 12 (Twelve)
General class& Sleeper class non- AC coaches and 08 (eight) AC-Coaches, in a train of 22 coaches,
§thereby providing greater accommodation for the passengers using General and non-AC Sleeper
Coaches.
AMRIT BHARAT SERVICE:
To provide affordable means of transportation to the low and middle income families, Indian
Railways have introduced Amrit Bharat services that are fully non-AC modern trains. As on
15.03.2026, 60 services are already in operation. The present composition of Amrit Bharat consists of
11 General Class coaches, 8 Sleeper Class coaches, 01 Pantry Car and 02 Luggage cum Divyangjan
coaches.
High Speed and enhanced Safety standards are the hallmarks of these trains with following enhanced
features and amenities:
● Better aesthetics of seat and berths with enhanced look & feel on the lines of Vande Bharat
Sleeper.
● Jerk Free Semi-Automatic Couplers.
● Improved Crashworthiness in coaches by provision of crash tube.
● Provision of CCTV system in all coaches.
● Improved designs of toilets.
● Improved design of Ladder for ease of climbing on to the berth.
● Improved LED Light fitting & Charging Sockets.
● Provision of EP assisted braking system.
● Aerosol based fire suppression system in toilets and electrical cubicles.
● USB Type-A and Type-C mobile charging sockets.
● Emergency Talk Back system for two-way communication between Passenger and Guard/Train
Manager.
● Non-AC pantry with enhanced heating capacity.
● Fully sealed gangways with quick release mechanism for easy attachment and detachment.
Further, to cater to the needs of passengers desirous of availing unreserved accommodation,
Indian Railways (IR) operate unreserved non-AC passenger trains/ MEMU / EMU etc. for affordable
travel, which are in addition to the unreserved accommodation (coaches) available in Mail/Express
services.
Presently, the following 60 Amrit Bharat Express services are being operated on the Indian Railways
network:
SN Train No. and Name
1 11015/11016 Lokmanya Tilak (T) - Saharsa Amrit Bharat Express
§2 13697/13698 Gaya - Delhi Amrit Bharat Express
3 15293/15294 Muzaffarpur - Charlapalli Amrit Bharat Express
4 15557/15558 Darbhanga - Anand Vihar (T) Amrit Bharat Express
5 15561/15562 Darbhanga - Gomtinagar Amrit Bharat Express
6 15567/15568 Bapudham Motihari - Anand Vihar (T) Amrit Bharat Express
7 22361/22362 Rajendranagar (T) - New Delhi Amrit Bharat Express
8 13433/13434 SMVT Bengaluru - Malda Town Amrit Bharat Express
9 13435/13436 Malda Town - Gomtinagar Amrit Bharat Express
10 15133/15134 Chhapra - Anand Vihar (T) Amrit Bharat Express
11 14047/14048 Sitamarhi - Delhi Amrit Bharat Express
12 14627/14628 Saharsa - Chheharta Amrit Bharat Express
13 19623/19624 Madar - Darbhanga Amrit Bharat Express
14 16601/16602 Erode - Jogbani Amrit Bharat Express
15 19021/19022 Udhna - Brahmapur Amrit Bharat Express
16 15671/15672 Kamakhya - Rohtak Amrit Bharat Express
17 20609/20610 New Jalpaiguri - Tiruchchirappalli Amrit Bharat Express
18 16597/16598 SMVT Bengaluru - Alipurduar Amrit Bharat Express
19 11031/11032 Panvel - Alipurduar Amrit Bharat Express
20 16107/16108 Tambaram - Santragachi Amrit Bharat Express
21 13065/13066 Howrah - Anand Vihar (T) Amrit Bharat Express
22 22587/22588 Sealdah - Banaras Amrit Bharat Express
23 20603/20604 New Jalpaiguri - Nagercoil Amrit Bharat Express
24 15949/15950 Dibrugarh - Gomti Nagar Amrit Bharat Express
25 16121/16122 Tambaram - Thiruvananthapuram Central Amrit Bharat Express
26 16329/16330 Nagercoil - Mangaluru Amrit Bharat Express
27 17041/17042 Charlapalli - Thiruvananthapuram North Amrit Bharat Express
28 16619/16620 Podanur-Dhanbad Amrit Bharat Express
29 16357/16358 Nagercoil-Charlapalli Amrit Bharat Express
30 15673/15674 Charlapalli - Kamakhya Amrit Bharat Express
§SPECIAL TRAINS
IR also operates Special train services during festivals, holidays, etc. to cater to the extra needs of
passengers and supplement the accommodation available by regular services.
Accordingly, the number of Special trains operated across the Indian Railways network, to facilitate the
passengers during Summer/winter vacations, festivals, etc. are as below:
Year No. of trips
2023-24 ~40,500
2024-25 ~85,400
2025-26(upto Jan, 2026) ~70,350
PUNCTUALITY
Indian Railways makes all possible efforts to run trains on time. However, several factors affect
punctual running of trains which include path constraints, asset maintenance, alarm chain pulling,
agitations, cattle run over, bad/foggy weather and other unforeseen circumstances. Based on
assessments of factors impeding the punctual running of trains, remedial measures, both short term
and long term, are initiated. High priority is accorded to making resources available for speedy
execution of critical capacity augmentation as these on completion inter-alia facilitate improved
efficiency and reliability in train operations.
Due to these initiatives, Indian Railways, during 2025-26 (up to February’2026) recorded an overall
punctuality of more than 77%
No. of Divisions Punctuality Percentage
24 Punctuality of more than 90%
19 Punctuality between 80% and 90%
All Divisions of Indian Railways 77%
*****
§