GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 1632
TO BE ANSWERED ON 29.07.2026
SAFETY OF ROBS, RUBS AND LEVEL-CROSSINGS IN THE COUNTRY
1632. SHRI CAPTAIN BRIJESH CHOWTA:
Will the Minister of RAILWAYS be pleased to state:
(a) whether the Government has reviewed ROB, RUB and level-crossings
safety and the present project or operational status in the country and
if so, the details thereof, section and station-wise;
(b) the details of sanctioned cost, physical and financial progress,
traffic/passenger data and target dates of above said projects;
(c) the details of capacity, safety, staffing, land/inter-zonal bottlenecks and
the authority holding each action; and
(d) the details of the approval and completion of roadmap with firm
milestones?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (d): As on 01.06.2026, there are 15,689 Nos. of Manned Level
Crossings (MLCs) on Indian Railways. Further, all Unmanned level crossings
(UMLCs) on Broad Gauge (BG) network of Indian Railways have been
eliminated in 2019.
Level Crossings (LCs) are eliminated either by providing Road over
Bridges/ Road under Bridges (ROBs/ RUBs) in lieu of LCs or through direct
closure (for low traffic LCs) or by diversion of road traffic to nearby
ROB/RUB/LC depending upon the site conditions.
§ Page 1 of 3Sanctioning of works of Road over Bridge (ROB)/Road under Bridge
(RUB) in lieu of Level crossings (LCs) is a continuous and dynamic process
of Indian Railway. Such works are prioritised and taken up on the basis of
their impact on safety in train operations, mobility of trains & impact for
road users and feasibility etc.
No. of ROBs/ RUBs constructed on Indian Railways during the period
2004-14 vis a vis 2014-26 (Upto May’26) is as under:
Period ROBs/ RUBs constructed
2004-14 4,148 Nos.
2014-26 (Upto May’26) 14,451 Nos.
As on 01.06.2026, 4,993 Nos. ROBs/ RUBs works are sanctioned at a
cost of approx. ₹ 1,17,492 Cr on Indian Railways which are at various
stages of planning and execution.
Completion & commissioning of ROB/RUB works depends on various
factors like cooperation of State Governments in giving consent for
closure of LC, fixing of approach alignment, approval of General
Arrangement Drawing (GAD), land acquisition, removal of encroachment,
shifting of infringing utilities, statutory clearances from various
authorities, law and order situation in the area of project / work
sites, duration of working season in a year for the particular project /
area due to climatic conditions etc. All these factors affect the
completion time of the projects / works.
Railways have taken following measures to expedite the progress of
work:
Page 2 of 3i. Joint survey with concerned State Govt./Road Owning Authority is
done before finalizing the General Arrangement Drawing (GAD) to
ensure smooth execution.
ii. Periodic meetings of Railway & State Government officials are done
to resolve various issues related to ROB/RUB works.
iii. Standardization of superstructure and substructure drawings for
various combinations of span, skewness and width of road on the
Railway portion has been done to avoid delays during the design
approval. This has been issued in the form of a compendium, which
can be directly adopted for Road Over Bridge across Railway lines for
expeditious planning.
*****