**Executive Summary**
This document presents the Ministry of Railways' response to Unstarred Question No. 654 regarding the Amrit Bharat Station Scheme (ABSS), which aims to redevelop railway stations with a long-term approach. The answer details the scheme's components, the number of stations identified for development, and progress updates on several stations. No specific deadline or action item is mentioned.
**Key Points / Main Content**
* **Amrit Bharat Station Scheme (ABSS):**
* Launched by the Ministry of Railways to redevelop railway stations.
* Involves phased implementation and preparation of master plans for station improvement.
* **Master Planning Components:**
* Improvement of access to stations and circulating areas.
* Integration of stations with both sides of cities.
* Improvement of station buildings, waiting halls, toilets, and water booths.
* Provision of wider foot over bridges/air concourses.
* Provision of lifts/escalators/ramps.
* Improvement/Provision of platform surfaces and covers.
* Provision of kiosks for local products (e.g., 'One Station One Product').
* Parking areas and multimodal integration.
* Amenities for Divyangjans (disabled individuals).
* Better passenger information systems.
* Executive lounges, spaces for business meetings, landscaping.
* Sustainable and environment-friendly solutions.
* Provision of ballastless tracks.
* Creation of city centers at stations.
* **Implementation Status:**
* 1337 stations identified for development.
* Works completed at 105 stations (names listed in document).
* Work is progressing at other stations, with examples given for Tirupati, Nellore, Yesvantpur, Bangalore Cantt., and Rameswaram stations (details of specific works underway provided).
* **Funding:**
* Funded under Plan Head-53 "Customer Amenities."
* Fund allocation for FY 2025-26 is ₹ 12,118 crore.
* Expenditure up to October 2025 is ₹ 7,253 crore.
* Fund details are maintained at Zonal Railway-wise, not station-wise or state-wise.
**Impact Analysis**
**Stakeholder: Passengers**
* **Impact:** Passengers will experience improved amenities, better access, and modernized facilities at redeveloped railway stations.
* **Action Required:** None.
**Stakeholder: Railway Authorities**
* **Impact:** Required to implement the Amrit Bharat Station Scheme and oversee station redevelopment projects.
* **Action Required:** Continue implementing the ABSS, monitor progress, and ensure effective fund utilization.
**Stakeholder: Local Businesses/Vendors**
* **Impact:** Opportunity to participate through kiosks at stations, offering local products under the "One Station One Product" scheme.
* **Action Required:** Explore opportunities to establish kiosks at redeveloped stations.
Key Entities Referenced
Amrit Bharat Station Scheme (ABSS): A scheme launched by the Ministry of Railways for the redevelopment of railway stations, focusing on modernization, infrastructure improvement, and sustainable solutions.
Ministry of Railways: The primary ministry responsible for the Amrit Bharat Station Scheme.
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 654
TO BE ANSWERED ON 03.12.2025
SELECTED RAILWAY STATIONS UNDER ABSS
654. SMT. JUNE MALIAH:
Will the Minister of RAILWAYS be pleased to state:
(a) the name of stations selected under the Amrit Bharat Station Scheme
(ABSS), State-wise;
(b) the number of stations where work has been sanctioned, State-wise;
(c) the number of stations where work has been completed, State-wise;
and
(d) the amount of funds allocated, released and utilised under the said
scheme since its inception, year-wise?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (d) Ministry of Railways has launched Amrit Bharat Station
Scheme for redevelopment of stations with a long-term approach.
The scheme involves preparation of master plans and their
implementation in phases to improve the stations. The masterplanning includes:
Improvement of access to station and circulating areas
Integration of station with both sides of city
Improvement of station building
Improvement of waiting halls, toilets, sitting arrangement,
water booths
Provision of wider foot over bridge/air concourse
commensurate with passenger traffic
Provision of lift/escalators/ramp
Improvement /Provision of platform surface and cover over
platforms
Provision of kiosks for local products through schemes like
‘One Station One Product’
Parking areas, Multimodal integration
Amenities for Divyangjans
Better passenger information systems
Provision of executive lounges, nominated spaces for business
meetings, landscaping, etc. keeping in view the necessity at
each station
The scheme also envisages sustainable and environment friendly
solutions, provision of ballastless tracks etc. as per necessity,
phasing and feasibility and creation of city centre at the station in
the long term.
So far, 1337 stations have been identified for development under this
scheme. Development works at railway stations under Amrit Bharat
Station Scheme have been taken up at a good pace. Till now, worksof 105 stations has been completed. Names of these stations are as
following:
Ambikapur, Amgaon, Ayodhya Dham, Bagalkot, Baijnath Paprola,
Balrampur, Bareilly City, Begumpet, Bhanupratappur, Bhilai, Bijnor,
Bundi, Chanda Fort, Chidambaram, Chinchpokli, Chirayinkeezh,
Cuttack, Dakor, Derol, Deshnoke, Devlali, Dharwad, Dhule,
Dongargarh, Fatehabad, Fatehpur Shekhawati, Gadag, Gogameri,
Gokak Road, Gola Gokarnath, Gomti Nagar, Govardhan, Govind Garh,
Govindpuri, Govindpur Road, Haibargaon, Hathras City, Hapa, Idgah
Agra Jn., Izzatnagar, Jam Jodhpur, Jam Wanthali, Joychandi Pahar,
Kalyani Ghoshpara, Kanalus Jn., Karamsad, Karimnagar, Katni South,
Kedgaon, Kosamba Jn., Kulitturai, Lasalgaon, Limbdi, Lonand Jn.,
Mahe, Mahuva, Mailani, Mandal Garh, MandawarMahwa Road, Mandi
Dabwali, Mannargudi, Matunga, Mithapur, Morbi, Munirabad,
Murtizapur Jn., Narmadapuram (Hoshangabad), Netaji Subhash
Chandra Bose Itwari Junction, Okha, Orchha, Palitana, Panagarh,
Parel, Pirpainti, Pokhrayan, Polur, Rajgarh, Rajmahal, Rajula Jn.,
Ramghat Halt, Saharanpur Jn., Samakhiyali, Samalpatti, Sankarpur,
Savda, Seoni, Shahad, Shajapur, Shridham, Siddharth Nagar, Sihor
Jn., Srirangam, St.Thomas Mount, Sullurpeta, Suraimanpur,
Swaminarayan Chappia, Thawe, Tiruvannamalai, Ujhani, Urkura,
Utran, Vadakara, Vadala Road, Vriddhachalam Jn., Warangal.
The works at other stations have also been taken up at good pace and
progress of some of the stations is as given below:
Tirupati station: The structural framework of new main entry station
building on South side and 2 nos. air concourses have beencompleted. The finishing works of new main entry station building on
South side and air concourses, structural work of station building on
North side, platform shelter works, lift, escalators etc. have been
taken up.
Nellore station: The structural frameworks, brickwork and plastering
of station buildings on both East and West sides and structural work
of air concourse have been completed. The finishing works of station
building on both East and West side and air concourse, extension
work of subway, water tanks, sewage treatment plant have been
taken up.
Yesvantpur station: The structural works of East side station
building, civil works of East side sub-station, East side elevated road
and Multi Level Car parking have been completed. The finishing
works of East side station building, East side elevated road and Multi
Level Car parking, sewage treatment plant, structural work of West
side station building and air concourse have been taken up.
Bangalore Cantt. station: The works of 24m wide diversion road
on the South side, training centre, hostel on North side, structural
work of South side station building have been completed. The
finishing work South side station building, structural work of
North side station building, Foot Over Bridge have been taken up.
Rameswaram station: The structural works of East/North terminal
building, departure forecourt, arrival forecourt, residential tower,
sub-station building, desalination plant and sewage treatment
plant have been completed. The masonry works of East terminal
building, finishing works of North terminal building, departure
forecourt, arrival forecourt, residential tower, platformupgradation including platform shelter and revamping of existing
waiting hall have been taken up.
Safdarjung station: The work of signal building, station building,
plumbing and firefighting, structural work of operational building up
to terrace floor slab, air concourse foundation and pedestals have
been completed. The station building electrical and low voltage work,
platform refurbishing work, finishing work of operational building,
overhead tank, air concourse have been taken up.
Further, development / redevelopment / upgradation / modernisation
of stations on Indian Railways is a continuous and ongoing process
and works in this regard are undertaken as per requirement, subject
to inter-se priority and availability of funds. The priority for
development / redevelopment / upgradation / modernisation of
stations is accorded to higher category of station over lower
category of station while sanctioning and executing the works.
Development / Upgradation of railway stations is complex in nature
involving safety of passengers & trains and requires various statutory
clearances such as fire clearance, heritage, tree cutting, airport
clearance etc. The progress also gets affected due to brownfield related
challenges such as shifting of utilities (involving water/sewage lines,
optical fibre cables, gas pipe lines, power/signal cables, etc.),
infringements, operation of trains without hindering passenger
movement, speed restrictions due to works carried out in close
proximity of tracks and high voltage power lines, etc. and these factors
affect the completion time. Therefore, no time frame can be indicated at
this stage.Development / Upgradation / Modernisation of stations including
under Amrit Bharat Station Scheme is generally funded under Plan
Head-53 ‘Customer Amenities’. The details of allocation and
expenditure under Plan Head-53 are maintained Zonal Railway-wise
and not work-wise or station wise or state-wise. The fund allocation
of ₹ 12,118 crore has been made for the financial year 2025-26 under
Plan Head–53 and expenditure (up to October, 2025) of ₹ 7,253 crore
has been incurred so far.
*****