GOVERNMENT OF INDIA
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
RAJYA SABHA
STARRED QUESTION NO - 209
ANSWERED ON - 11/03/2026
SIX LANING OF THE NATIONAL HIGHWAY-48
209. SHRI IRANNA KADADI:
Will the Minister of ROAD TRANSPORT AND HIGHWAYS be pleased to state:
(a) the physical progress of the six-laning of the National Highway-48 (Pune-Bengaluru) stretch
passing through the Belagavi district;
(b) the details of the construction of flyovers and underpasses at the busy junctions like Kittur and
Sankeshwar;
(c) the measures taken to address the traffic congestion at the toll plazas in the district;
(d) the status of the land acquisition and compensation payment for the highway expansion; and
(e) the timeline for the completion of the project to ensure smooth flow of traffic on this critical
corridor?
ANSWER
THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS
(SHRI NITIN JAIRAM GADKARI)
(a) to (e) A Statement is laid on the Table of the House.STATEMENT REFERRED TO IN REPLY TO PARTS (a) to (e) OF RAJYA SABHA STARRED
QUESTION NO. 209 ANSWERED ON 11/03/2026 ASKED BY SHRI IRANNA KADADI
REGARDING ‘SIX LANING OF THE NATIONAL HIGHWAY-48’.
(a) & (e) The details are annexed.
(b) The details regarding construction of Flyover and underpasses at Kittur and Sankeshwar are
annexed.
(c) In Belagavi district, three toll plazas at Hirebagewadi, Hattargi & Kognolli are functioning. The
existing toll plazas at Hattargi & Kognolli have been upgraded with improved toll management
infrastructure to facilitate faster vehicle movement and reduce congestion. Further, Hybrid Electronic
Toll Collection (ETC) system is being upgraded at Hirebagewadi toll plaza for reducing congestion at
the toll plaza.
(d) The status of land acquisition and compensation payment for the highway expansion is annexed.ANNEXURE-I
ANNEXURE REFERRED TO IN REPLY TO PARTS (a) & (e) OF RAJYA SABHA STARRED
QUESTION NO. 209 ANSWERED ON 11/03/2026 ASKED BY SHRI IRANNA KADADI
REGARDING ‘SIX LANING OF THE NATIONAL HIGHWAY-48’.
The details of National Highways passing through the Belagavi District:
Tot
Scheduled
al Start Dat
Date/ sche Physica
Sl. Le Length Co e/
Sanctione duled revi l progre
No Name of the project ngt mpleted (I Appointe
d Cost (In sed date of ss of the
. h (I n Kms) d date
Crs) completio project
n K
n
ms)
Six laning of Belgaum - Project comp
Dharwad section of NH-4 leted and und
1 100%
8 from km 433.00 to km 79.36 79.36 637 er O&M Sta
04.05.2011
515.00 ge
6L from Belgaum to Sank
eshwar Bypass from Km. 23.04.2025/
2 40.01 40.01 1479 25.10.2022 98.10%
515.000 to Km. 555.017 31.03.2026
of NH-48 (Pkg-I)
6L from Sankeshwar Byp
ass to MH-KNT Border fr
37.83 23.04.2025/
3 om Km. 555.017 to Km. 32.48 1388 25.10.2022 78.10%
6 31.10.2026
592.853 of NH-48 (Pkg-I
I)ANNEXURE-II
ANNEXURE REFERRED TO IN REPLY TO PARTS (b) OF RAJYA SABHA STARRED
QUESTION NO. 209 ANSWERED ON 11/03/2026 ASKED BY SHRI IRANNA KADADI
REGARDING ‘SIX LANING OF THE NATIONAL HIGHWAY-48’.
The details of construction of Flyover and underpasses at Kittur on Six laning of Belgaum-
Dharwad section of NH-48:
Sl. No. Location Structure Chainage Status of the work
1 Kittur Pedestrian Underpass Km.456+720 Completed
2 Kittur Vehicular Underpass Km. 458+560 Completed
The details of construction of Flyover and underpasses at Sankeshwar on Six laning of Belgaum-
Sankeshwar section of NH-48:
Sl. Status of the
Location Structure Chainage
No. work
1 Sankeshwar Junction Vehicular Underpass Km.548+809 Completed
2 Gadhinglaz Junction Vehicular Underpass Km.552+904 Completed
3 Solapur Junction Vehicular Underpass Km.554+668 Completed
4 Hosavantamuri Elevated structure Km.525+510 Completed
5 Ghatprabha River Viaduct cum Major Bridge Km.529+662 Completed
6 Near Honaga Village Vehicular Underpass Km.515+580 Completed
7 Bhutramanhatti Village Vehicular Underpass Km.519+604 Completed
Vehicular Underpass & Km.523+702 &
8 Vantamuri Village Completed
Pedestrian Underpass Km.523+965
Km.527+485 &
9 Sutagatti Junction Vehicular Underpass Completed
Km.528+145
10 Near Narasingpur Village Light Vehicular Underpass Km.531.878 Completed
11 Yamakanamardi Junction Vehicle overpass Km.535.891 Completed
12 Near Hattargi Village Vehicular Underpass Km.536+924 Completed
13 Hidkal Junction Interchange Km.538+287 Completed
14 Ullagaddi Khanapur Junction Vehicular Underpass Km.540+670 Completed
15 Chikalgudda Junction Vehicular Underpass Km.544+21 Completed
16 Hebbal Junction Light Vehicular Underpass Km.545+848 Completed
17 Gotur Junction Vehicular Underpass Km.547+409 Completed
Km.566+800 to Under
18 Tavandi Ghat Elevated structure
Km.570+012 progress
19 Hargapur Village Junction Vehicular Underpass Km.556+614 CompletedSl. Status of the
Location Structure Chainage
No. work
20 Honnihalli Village Junction Light Vehicular Underpass Km.558+928 Completed
21 Kanagala Village Junction Vehicular Underpass Km.561+084 Completed
22 Hitani Village Junction Vehicular Underpass Km.563+560
Completed
Completed
Near Shippur Village Vehicular Underpass &
23 Km.566+340
Junction Vehicle overpass
24 Nippani Junction Grade separator Km.572+020
Completed
Completed
25 Nippani Junction Light Vehicular Underpass Km.572+335
Under
26 Nippani Junction Light Vehicular Underpass Km.572+825
progress
Under
27 Shirguppi village Junction Light Vehicular Underpass Km.573+054 progress
Completed
28 Arjun Nagar Junction Grade separator Km.574+685
Completed
29 Nippani Town Junction Grade separator Km.575+993
Completed
Halsidnath Sugar Factory
30 Vehicular Underpass Km.577+740
Junction
31 Yamagarni Village & Kodni Light Vehicular Underpass Km.579+901 Completed
Village Junction
32 Soundalaga Village Junction Vehicular Underpass Km.581+460 Completed
33 Kurli Village Junction Light Vehicular Underpass Km.583+130 Completed
34 Appachiwadi Village Junction Vehicular Underpass Km.586+074 Under
progress
35 Kognoli Village Junction Light Vehicular Underpass Km.589+285 Completed
36 Kognoli Village Junction Trumpet Interchange Km.591+515 Under
progress
37 Kagal Shendur road Light Vehicular Underpass Km.591+670 Yet to startANNEXURE-III
ANNEXURE REFERRED TO IN REPLY TO PARTS (d) OF RAJYA SABHA STARRED
QUESTION NO. 209 ANSWERED ON 11/03/2026 ASKED BY SHRI IRANNA KADADI
REGARDING ‘SIX LANING OF THE NATIONAL HIGHWAY-48’.
The details of Land compensation:
Sl. Project name Total LA Amount Remarks
No. Cost in disbursed in
Cr. Cr.
1 Six laning of Belgaum-Completed
Dharwad section of NH-48
2 6L from Belgaum to 110.08 102.73
Sankeshwar Bypass from Km. The 3G Award approved for the missing
515.000 to Km. 555.017 of additional land in the month of January
NH-48 (Pkg-I) 2026 and compensation disbursement is
3 6L from Sankeshwar Bypass to 212.66 210.79 currently under process.
MH-KNT Border from Km.
555.017 to Km. 592.853 of
NH-48 (Pkg-II)
*****