UNSTARRED QUESTION NO. 2374
TO BE ANSWERED ON THURSDAY, MARCH 12, 2026
SPACEPORT PROJECT AT KULASEKARAPATTINAM
2374. SMT. RAJATHI:
Will the PRIME MINISTER be pleased to state:
(a) the details of funds allocated and actual expenditure incurred on the Spaceport project
at Kulasekarapattinam till date;
(b) whether the target for the first rocket launch by December, 2026 remains on schedule;
(c) whether the Central Government has a specific policy to ensure gender-inclusive
leadership in the management and operations of the second spaceport project there;
and
(d) the number of annual launches envisaged once the facility is fully commissioned?
ANSWER
MINISTER OF STATE IN THE MINISTRY OF PERSONNEL, PUBLIC
GRIEVANCES & PENSIONS AND IN THE PRIME MINISTER’S OFFICE
(DR. JITENDRA SINGH):
****
(a) The overall financial outlay for the Acquisition of land and establishment of new
launch pad for Small Satellite Launch Vehicle is Rs 985.96 Crore. The cumulative
expenditure incurred in the project till end of February 2026 is Rs 511.35 Crore.(b) Currently, the establishment of the second launch pad is in progress at
Kulasekarapattinam which is expected to be completed during FY 2026-27 timeframe.
Once the facility is fully commissioned and made operational, the first rocket launch
will be scheduled.
(c) It may be noted that ISRO’s HR Policies are gender-neutral ensuring equal
participation & opportunity to all employees in various capacities in the organization.
The promotion process in ISRO is gender-neutral and merit based which also ensures
gender-inclusivity in taking up leadership roles in the organization.
(d) Once the facility is fully operational, annually 20-25 launches is expected from the
spaceport.
****