GOVERNMENT OF INDIA
MINISTRY OF JAL SHAKTI
DEPARTMENT OF WATER RESOURCES, RIVER DEVELOPMENT & GANGA
REJUVENATION
LOK SABHA
UNSTARRED QUESTION NO. 3090
ANSWERED ON 06.08.2026
STATUS OF CAD&WM PROGRAMME IN ODISHA
3090. Shri PRADEEP PUROHIT:
Will the Minister of JAL SHAKTI be pleased to state:
(a) whether the Government maintains the data on the works being implemented
under the Command Area Development and Water Management (CAD&WM)
Programme in Odisha and if so, the details thereof, district and project-wise;
(b) the total financial assistance released by the Union Government and the State
Government of Odisha under the CAD&WM Programme during the last two
financial years, year and project-wise;
(c) the details and the number of projects completed, under implementation and
yet to be completed under the CAD&WM Programme in Odisha, district-wise;
(d) the details of the works for which tenders have been invited, awarded or are
under process under the CAD&WM Programme in Odisha during the last two
years, project and district-wise; and
(e) the steps taken by the Government to expedite the completion of pending
CAD&WM projects and ensure efficient utilisation of the irrigation potential
created in Odisha?
ANSWER
THE MINISTER OF STATE FOR JAL SHAKTI
(SHRI RAJ BHUSHAN CHOUDHARY)
(a) to (c) Water, being State subject, water resources projects are planned,
funded, executed and maintained by the State Governments themselves as per
their own resources and priority. Role of Government of India is to provide
1technical support, and partial financial assistance for identified projects under
ongoing schemes.
Ninety-Nine (99) ongoing Major/Medium Irrigation projects (and 7 phases)
with pari-passu command area development in 88 projects were identified and
included under Pradhan Mantri Krishi Sinchayee Yojana (PMKSY) during 2016-17.
Eight Command Area Development and Water Management (CADWM)
projects from Odisha were taken up under PMKSY. A total central assistance
(CA) of Rs. 131.964 crore released to these eight CADWM projects of Odishan
since 2016-17. No CA released to any of these projects in the last two years. Out
of the total command area of 236.39 thousand hectares under these projects,
command area of 117.05 thousand hectares has been developed. Project-wise
details are as under:
Sl. No Project Name Districts Command Command Area Status of
Benefitted Area Developed Completion
(Th. Ha) (Th. Ha)
1 Lower Indra Noapada 29.90 29.90 Completed
2 Upper Indravati Kalahandi 23.83 23.83 Completed
3 Rukura Kalahandi 5.75 5.65 Completed
4 RET Irrigation Kalahandi 8.50 10.04 Completed
5 Telengiri Koraput 9.95 9.95 Completed
6 Subernarekha Sundargarh, 68.88 21.57 -
Mayurbhanj
7 Anandpur Barrage Balasore, 60.00 12.80 -
Keonjhar,
Bhadrak
8 Kanupur Kaeonjhar 29.58 3.31 -
Total 236.39 117.05
(d) As per information provided by Government of Odisha, status of tender for
various works under CADWM projects is given at Annexure.
(e) The progress of these projects is reviewed regularly at all levels in the
Department of Water Resources, RD & GR and monitoring is carried out by the
Central Water Commission to track physical and financial targets and expedite
completion.
***
2ANNEXURE
ANNEXURE REFERRED TO IN REPLY TO PART (d) OF UNSTARRED QUESTION NO. 3090 TO
BE ANSWERED IN LOK SABHA ON 06.08.2026 REGARDING “STATUS OF CAD&WM
PROGRAMME IN ODISHA”.
Sl no Name of Work District Agreement Tender
Cost in Crore Status
Anandapur Barrage Project
1 Under Ground Pipeline Irrigation in the Mayurbhanj 56.31 Awarded
command area of Baisinga Branch canal and its
system
2 Distribution system of Salandi Left Main Canal Balasore 764.00 Tendering
(Under Ground Pipe Line-UGPL) from RD Stage
40.927 km to 45.57 km & RD 49.810 km to
73.003 km.
3 Distribution system of Salandi Left Main Canal Balasore 426.50 Awarded
(UGPL) from RD 30.547 km to 40.927 km &
45.570 km to 49.810 km.
4 Distribution System for Baitarani Left Bank Kaeonjhar 120.00 Awarded
Canal (BLBC) (UGPL) from RD 0.00 km to
28.50 km & Baitarani Right Bank Canal (BRBC)
from RD 0.00 Km to 9.00 Km
Kanupur Project
5 CAD & WM works under Jhadaposi Sub -minor Kaeonjhar 4.38 Awarded
6 CAD & WM works of Andharikaman Minor Kaeonjhar 5.73 Awarded
7 CAD & WM works of mahadevpur Minor Kaeonjhar 4.04 Awarded
8 CAD & WM works under Jagannathpur Minor Kaeonjhar 4.37 Awarded
9 CAD & WM works of Ranipur Minor & Ichinda Kaeonjhar 4.93 Awarded
Sub Minor
10 CAD & WM works under Palasa minor Kaeonjhar 3.02 Awarded
11 CAD & WM works of Sananai Minor & Kaeonjhar 2.97 Awarded
Tolaknonda Sub Minor
*****
3