GOVERNMENT OF INDIA
MINISTRY OF JAL SHAKTI
DEPARTMENT OF WATER RESOURCES, RIVER DEVELOPMENT & GANGA REJUVENATION
LOK SABHA
UNSTARRED QUESTION NO. 3419
ANSWERED ON 12.03.2026
STATUS OF INTER-LINKING OF RIVER BASINS RELATED TO KRISHNA RIVER
3419. Dr. K SUDHAKAR:
Will the Minister of JAL SHAKTI be pleased to state:
(a) the current status of the proposed inter-linking of river basins related to the Krishna river for
providing water to Kolar and Chikkaballapur districts of Karnataka;
(b) whether the Government has taken any concrete steps or approved any projects to ensure transfer or
sharing of water under river-linking initiatives and if so, the details thereof; and
(c) the expected time-frame for completion of such inter-linking or related works to provide irrigation
and drinking water benefits to Kolar and Chikkaballapur districts?
ANSWER
THE MINISTER OF STATE FOR JAL SHAKTI
(SHRI RAJ BHUSHAN CHOUDHARY)
(a) to (c) The Government of India has formulated the National Perspective Plan (NPP) for interlinking
of rivers, under which 30 Interlinking of Rivers (ILR) projects—comprising 16 Peninsular and 14
Himalayan links—have been identified to address water scarcity and augment irrigation and other
water-related benefits across the country. The National Water Development Agency (NWDA) is the
nodal agency entrusted with carrying out studies and preparing project reports for these ILR links.
NWDA has completed Pre-Feasibility Reports (PFRs) for all 30 links, Feasibility Reports (FRs) for
26 links, and Detailed Project Reports (DPRs) for 11 links. The status of these 30 link projects under the
NPP is enclosed at Annexure.
Several of the identified links involve the Krishna basin, including the Krishna (Almatti)–Pennar
link, Krishna (Srisailam)–Pennar link, and others. However, none of these links is designed to transfer
water to Kolar or Chikkaballapur districts of Karnataka.
Since no ILR project under the NPP is presently envisaged for providing Krishna river water to
Kolar and Chikkaballapur districts, no time-frame can be indicated for completion of such works for
these districts.
***
1ANNEXURE
ANNEXURE REFERRED TO IN REPLY TO PART (a) to (c) OF UNSTARRED QUESTION NO.
3419 TO BE ANSWERED IN LOK SABHA ON 12.03.2026 REGARDING “STATUS OF INTER-
LINKING OF RIVER BASINS RELATED TO KRISHNA RIVER”.
Details and current status of ILR projects under the NPP
Peninsular Component
Sl. Name States benefited Status
No
1 Mahanadi (Manibhadra) - Godavari Andhra Pradesh (AP) FR completed
(Dowlaiswaram) link and Odisha
Alternate Mahanadi (Barmul)- AP and Odisha FR completed
Rushikulya–Godavari Dowlaiswaram) link
2 Godavari (Polavaram) - Krishna AP, Karnataka, FR Completed
(Vijayawada) link @ Maharashtra and
Telangana
3 a.) Godavari (Inchampalli) - Krishna Telangana FR completed
(Nagarjunasagar) link
b.) Alternate Godavari (Inchampalli) - DPR completed
Telangana
Krishna (Nagarjunasagar) link *
4 Godavari (Inchampalli/ SSMPP) - Krishna Telangana and AP DPR completed
(Pulichintala) link
5 a.) Krishna (Nagarjunasagar) - Pennar AP FR completed
(Somasila ) link
b.)Alternate Krishna (Nagarjunasagar) - DPR completed
AP
Pennar (Somasila ) link *
6 Krishna (Srisailam) – Pennar link AP DPR Completed
7 Krishna (Almatti) – Pennar link Karnataka &AP DPR completed
8 a.) Pennar (Somasila) - Cauvery (Grand AP, Tamil Nadu and FR completed
Anicut) link Puducherry
b.) Alternate Pennar (Somasila) - Cauvery AP, Tamil Nadu and
(Grand Anicut) link * Puducherry DPR completed
9 Cauvery (Kattalai) - Vaigai -Gundar link Tamil Nadu DPR completed
10 Parbati –Kalisindh - Chambal link Madhya Pradesh FR completed
(MP) and Rajasthan
b) Modified Parbati – Kalisindh-Chambal MP and Rajasthan MoA for implementation
link has been signed by both the
States
11 Damanganga - Pinjal link Maharashtra (only DPR completed and
water supply to dropped from status of
Mumbai) “priority links”
12 Par-Tapi-Narmada link Gujarat and DPR completed and
Maharashtra dropped from status of
“priority links”
13 Ken-Betwa link Uttar Pradesh (UP) DPR completed and project
and MP is under implementation
14 Pamba - Achankovil - Vaippar link Tamil Nadu and FR completed
Kerala
15 Bedti - Varda link @@ Karnataka DPR completed
16 Netravati – Hemavati link*** Karnataka PFR completed
2* Due to pending consensus on Manibhadra and Inchampalli dams, Phase-I of Project to divert unutilized
waters of Godavari river, Study was carried out and DPR of Godavari (Inchampalli) – Krishna
(Nagarjunasagar) - Pennar (Somasila) – Cauvery (Grand Anicut) link projects (combined) called as
Godavari-Cauvery link was completed. The report has further been updated terminating the link canal at
Manimukhtanadi, a Tributary of Vellar river flowing adjacent to Cauvery basin.
@@ Bedti – Varda Link - DPR was prepared directly after preparation of its PFR, no FR was prepared.
@ Godavari (Polavaram) - Krishna (Vijayawada) Link- the project has been taken up by Govt. of Andhra
Pradesh and is under execution by Polavaram Project Authority.
*** Netravati – Hemavati link: Further studies not taken up after PFR preparation since after
implementation of Yettinahole project by Govt. of Karnataka, no surplus water is available in Netravati
basin for diversion through this link.
Himalayan Component
Sl. Name States / Countries Status
No benefited
1. Kosi-Mechi link** Bihar and Nepal PFR completed
2. Kosi-Ghaghra link Bihar, Uttar Pradesh (UP) FR completed
and Nepal
3. Gandak - Ganga link UP and Nepal FR completed
4. Ghaghra - Yamuna link UP and Nepal FR completed
5. Sarda - Yamuna link UP and Uttarakhand FR completed
6. Yamuna-Rajasthan link Haryana and Rajasthan FR completed
7. Rajasthan-Sabarmati link Rajasthan and Gujarat FR completed
8. Chunar - Sone Barrage link Bihar and UP FR completed
9. Sone Dam - Southern Tributaries of Ganga Bihar and Jharkhand Draft FR
link completed
10. Manas-Sankosh-Tista-Ganga (M-S-T-G) Assam, West Bengal and FR completed
link Bihar
11. Jogighopa-Tista-Farakka link (Alternative to Assam, WB and Bihar PFR completed
M-S-T-G) (The proposal
has been
dropped)
12. Farakka-Sundarbans link WB FR completed
13. Ganga (Farakka) - Damodar-Subarnarekha WB, Odisha and Jharkhand FR completed
link
14. Subarnarekha-Mahanadi link WB and Odisha FR completed
**Kosi-Mechi Inter State link - PFR prepared and proposal was dropped due to international issues,
subsequently, on request of Govt. of Bihar, NWDA has taken up Kosi-Mechi Intra State link project.
*****