GOVERNMENT OF INDIA
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
RAJYA SABHA
UNSTARRED QUESTION NO - 3768
ANSWERED ON - 25/03/2026
STATUS OF KEY ROADS, TUNNELS AND HIGHWAYS IN JAMMU AND KASHMIR
3768. SHRI SAJJAD AHMAD KICHLOO:
Will the Minister of ROAD TRANSPORT AND HIGHWAYS be pleased to state:-
(a) the present status, DPR, tendring, land acquisition, environment and security clearances, funds
sanctioned and released, work awarded and timeline fixed for each project with reference to the
Sudhmahdev-Chennai Tunnel, Singhpora-Vailoo Tunnel, Peerki-Gali Tunnel, Chanjer-Bonda tunnel,
Chaidraman-Warwan Tunnel, Padder- Zanskar Road and Doda-Dessa-Kapran road projects; and
(b) the reasons for delay in widening the Batote-Doda-Kishtwar National Highway, including issues of
land acquisition, slope stabilization, retaining walls, contractor performance and weather constraints
and the corrective measures taken along with revised completion schedules?
ANSWER
THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS
(SHRI NITIN JAIRAM GADKARI)
(a) Sudhmahadev - Dranga and Singhpora - Vailoo tunnels fall under National Highway (NH) 244. The
Detailed Project Reports (DPRs) for these tunnels have been completed by National Highways
Infrastructure Development Company Limited (NHIDCL). The Sudhmahadev-Daranga tunnel
including approaches is having a length of 12.85 km and Singhpora- Vailoo tunnel including
approaches is having a length of 38.61 km. The projects for construction of these tunnels are at
appraisal stage.
The Peer-Ki-Gali falls on Shopia-Bafliaz section of NH-701A. The DPR for tunnel on Peer-Ki-Gali
has been taken up through Jammu & Kashmir PWD. At present, alignment is being finalized. Upon
completion of DPR, the tunnel work shall be taken up for consideration in next year’s Annual Plan i.e.
2026-27.
As regards, Chanjer-Bonda tunnel, Chaidraman-Warwan Tunnel, Padder-Zanskar Road and Doda-
Dessa-Kapran road projects, these are not National Highways. Government in Ministry of Road
Transport & Highways is responsible for development, operation and maintenance of National
Highways and National Expressways in the country.
(b) The road stretch of Batote-Doda-Kishtwar is divided into following two stretches:
The Batote-Khellani section of NH-244 is of 2-lane standards. However, due to deficient alignment
having steep curves, this stretch is to be bypassed through development of Chenani-Sudhmahadev-
Goha-Khellani greenfield alignment. Out of total length of 38 km from Chenani to Khellani (excludingSudhmadev -Dranga tunnel portion) the 2-lane has been completed in 34 km and 2 laning is in progress
in remaining 4 km, which is scheduled to be completed by October, 2026.
The Khellani-Doda-Kishtwar section of NH-244 (112.66 km) is being developed to 2 lane with paved
shoulders configuration in 9 civil work contract packages, of which, 47.38 km length has been
completed and remaining length is in progress. Package-wise details are given at Annexure.ANNEXURE REFERRED TO IN REPLY TO PART (b) OF RAJYA SABHA UNSTARRED
QUESTION NO. 3768 ANSWERED ON 25/03/2026 ASKED BY SHRI SAJJAD AHMAD
KICHLOO REGARDING ‘STATUS OF KEY ROADS, TUNNELS AND HIGHWAYS IN JAMMU
AND KASHMIR’
S. Project Name Length Physical Likely Reason for
No. (KM) Progress Completion Delay
date
1 Widening and Up-gradation to 2-Lane with 15.52 94.06% PCC issued (i) Non-
Paved Shoulder of configuration and handing over
geometric improvement from Km 0.000 to Km of hinderance
16.990 on Chenani – Sudhmahadev section of free land.
NH-244 in the UT of Jammu and Kashmir to (ii) Covid-19
be executed on EPC basis Pandemic.
(iii)
Additional
work of COS
(iv) Incessant
rainfall and
snowfall
(v) Slow
progress of the
contractor
2 Up-gradation to Two Lane with Paved 9.46 94% 30.04.2026 (i) Non-
Shoulder from Km 12+850 to Km 20+300 of handing over
7.450 Km length of Goha-Khellani of hinderance
Section and a link road to Goha Village of free land.
2.016 Km on NH-244 in Union Territory of (ii) Covid-19
Jammu and Kashmir on EPC Mode. (Pkg- I) Pandemic.
(iii) Terrorist
attacks and
suspension of
night shifts
(iv) Incessant
rainfall and
snowfall
(v) Slow
progress of the
contractor3 Up-gradation to Two Lane with Paved 8.73 97% 31.03.2026 (i) Non-
Shoulder from Km 20+300 to Km 29+030 of handing over
8.730 Km length of Goha-Khellani Section on of hinderance
NH-244 in Union Territory of Jammu and free land.
Kashmir on EPC Mode (Pkg-II) (ii) Covid-19
Pandemic.
(iii) Terrorist
attacks and
suspension of
night shifts
(iv) Incessant
rainfall and
snowfall
(v) Slow
progress of the
contractor
4 Construction of Uni-Directional Khellani 2.49 100% Completed (i) Covid-19
Tunnel of length 1.574 Km & its approach (CC issued) on Pandemic.
Road from Km 29.030 to Km 31.449 of total 17.03.2025 (ii) Landslide
length of 2.419 Km on NH-244 in Union and poor
Territory of Jammu & Kashmir on EPC Mode. geology
(Pkg-III) (iii) Utility
shifting
(iv)
Additional
time for RE
wall and
terrorist
attacks
5 Construction & Upgradation to 2 lane with 20.25 Work Completed (i) Non-
paved shoulder from Design Km. 31.449 completed on handing over
(Khellani) (Ex. Km 44.946) to Km 51.700 and CC 02.10.2024 of RoW
(Prem Nagar) (Ex. Km 68+617) of 20.251 Km issued, except (ii) Landslide
length on Khellani - Kishtwar - Chattroo de-link and rainfall
section of NH-244 in the UT of J&K on EPC portion of (iii) Covid-19
Mode under NH(O)-Gen (PKG- 1) 1440m Pandemic6 Construction & Upgradation to 2-lane with 14.84 53.33% 31.12.2026 (i) Non-
paved shoulder from Design Ch. Km 51+700 handing over
(at Premnagar km 66+315) to Km 66+535 of hinderance
New Thatri (at Start of Km 83rd, Tunnel Km free land.
82+665) of 14.835 Km design length on (ii) Covid-19
Chenani-Sudhmahadev-Goha Khellani- Pandemic.
Kishtwar-Vailoo Donipawa-Ashajipora section (iii) Incessant
of NH-244 in the UT of J&K on EPC Mode rainfall and
under NH(O)-Gen (Pkg - 2) snowfall
(iv) Slow
progress of the
contractor
7 Construction & Upgradation to 2-lane with 9.12 99% Physically (i) Non-
paved shoulder from Design Km 67.805 (at the completed handing over
end of Km 83rd Tunnel near Dhrabshalla) (Ex. of hinderance
Km 83+905) to Km 80.675 (start of Kishtwar free land.
Bypass - Dulhasti) (Ex. Km 97+0751) of (ii) Covid-19
12.870 Km length on chenani-Sudhmahadev- Pandemic
Goha Khellani-Kishtwar-vailoo-Donipawa- (iii) Flash
Ashajipora seition of NH-244 in the UT of Flood,
J&K on EPC Mode under NH(O)-Gen (Pkg-3) incessant
rainfall and
snowfall
(iv) Heavy
landslide
(v) Local
hindrances
(vi) Slow
progress of the
contractor
8 Construction of Kishtwar bypass with 2 lane 16.75 49.96% 30.06.2027 (i) Non-
with paved shoulder from Design Km. 80.675 handing over
(Dulhasti) to km 95.550 (Bandarkoot ) of of hinderance
14.88 km & a link road to Kishtwar town from free land.
0+000 to 1.871 of length=1.871 Km on (ii) Covid-19
Khellani - Kishtwar - Chattroo section in UT Pandemic.
of Jammu and Kashmir on EPC Mode (Pkg-4) (iii) Flash
Flood,
incessant
rainfall and
snowfall
(iv) Strike of
truck driversand farmers
(v) Closure of
NH-44
(vi) Slow
progress of the
contractor
9 Construction/upgradation to 2-lane with paved 15.50 97.93% 31.03.2026 (i) Non-
shoulder from Design Km 95.55 (Bandarkoot) handing over
to Km. 111.06 (Chattroo) of 15.52 Km length of hinderance
on Khellani-Kishtwar-Chattroo section on NH- free land.
244 in UT of Jammu and Kashmir on EPC (ii) Covid-19
Mode (Pkg-5) Pandemic.
(iii) Flash
Flood,
incessant
rainfall and
snowfall
(iv) Strike of
truck drivers
and farmers
(v) Local
hinderances
(vi) Closure of
NH-44
*****