GOVERNMENT OF INDIA
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
LOK SABHA
UNSTARRED QUESTION NO. 824
ANSWERED ON 23RD JULY, 2026
STATUS OF NATIONAL HIGHWAY PROJECT IN VADAKARA
824. SHRI SHAFI PARAMBIL:
Will the Minister of ROAD TRANSPORT AND HIGHWAYS
सड़क परिवहन औि िाजमार् गमंत्री
be pleased to state:
(a) the present status of the National Highway development projects in
Kerala particularly the stretch passing through Vadakara;
(b) whether the Government has taken note of the delay in the
completion of the project, if so, the reasons therefor, including delays
due to land acquisition, environmental clearances, contractual issues
or other factors;
(c) the original and revised timelines for completion of the project
along with its present stage of execution;
(d) the funds sanctioned and utilised for the project so far; and
(e) the steps taken by the Government to expedite the work and the
expected date for completion of the highway project in the Vadakara
section?ANSWER
THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS
(SHRI NITIN JAIRAM GADKARI)
(a) & (c) The details of projects passing through Vadakara
constituency is annexed.
(b) The project progress has been affected due to adverse weather
conditions, numerous public protests, and public representative’s
demands for additional facilities such as underpasses, overpasses,
foot overbridges (FOBs), and viaducts. Further, there have been
instances of failure of Reinforced Soil (RS) Wall in approaches of
Flyovers and Vehicular Underpasses on NH-66. Based on a review of
the design & construction parameters and given the soil conditions in
Kerala along the coastal region, it has been decided to increase the
viaduct portion at identified locations and reduce the height of RS
Wall.
(d) The total sanctioned cost of the project in Rs. 3898 Crore and
expenditure is Rs. 2407 Crore.
(e) Government has established strong framework to review the
progress of all on-going National Highway work. This involves review
at multiple level right from the site to the Highest Authority in the
Government involving all stakeholders including the State
Government.
The Concessionaire has completed 31.2 km out of 40.8 km of project
length. 6 km of the project is affected by the additional structures
sanctioned under Change of Scope (CoS).
The revised date for completion of 6 km of project length in Vadakara
is 31.03.2028.ANNEXURE REFERRED TO IN REPLY TO PART (a) AND (c) OF LOK
SABHA UNSTARRED QUESTION NO. 824 ANSWERED ON 23RD JULY,
2026 ASKED BY SHRI SHAFI PARAMBIL REGARDING ‘STATUS OF
NATIONAL HIGHWAY PROJECT IN VADAKARA’
Sr. Project Stretch Total Scheduled Physical Scheduled /
No length Completion progress Revised
(Km) Date (%) date of
completion
1 6L of Thalapady to 39 15-05-2024 100 PCC issued
Chengala w.e.f.
25.08.2025
2 6L of Chengala- 37.3 11.04.2024 91 31.03.2027
Neeleshwaram
3 6L of Neeleshwaram- 40.1 11.04.2024 87 31.03.2027
Thalipparamba
4 6L of Thaliparamba- 29.9 26.05.2024 84 30.04.2028
Muzhapilangadu
5 6L of Azhiyur-Vengalam 40.8 26.04.2024 68 30.03.2028
6 6L of Kozhikode Bypass 28.4 21-02-2023 99 PCC issued
on
09.10.2025
7 6L of Ramanatukkara 39.7 19-07-2024 100 PCC issued
Junction to start of on
Valanchery bypass 18.07.2025
8 6L of Valanchery bypass 37.4 19-07-2024 100 PCC issued
to Kappirikkad on
17.07.2025
9 6L of Kappirikkad- 33.2 26.02.2025 95 30.06.2027
Thalikkulam
10 6L of Thalikkulam- 28.7 14.03.2025 94 30.06.2027
Kodungallur
11 6L of Kodungallur-Edapally 26 21.04.2025 71 31.05.202712 6-lane Elevated Highway 12.8 31.01.2026 91 06.01.2027
Aroor-Thuravoor
13 6L of Thuravoor-Paravoor 38.4 14.09.2024 81 31.05.2027
14 6L of Paravoor- 37.5 24.02.2025 77 30.11.2027
Kottukulangara
15 6L of Kottukulangara-Start 31.5 08.10.2024 77 31.12.2027
of Kollam Bypass
16 6L of Start of Kollam 31.3 31.03.2025 96 30.06.2027
Bypass-Kadambattukonam
17 6L of Kadambattukonam- 29.8 18.01.2025 77 30.04.2027
Kazhakuttom
18 Rectification of 4 Nos 2.4 21.08.2025 41 31.05.2027
Blackspots/Accident Spots
in Thiruvananthapuram
Bypass section
19 Rectification of 17 Nos 17.3 31.03.2028 2.5 31.03.2028
blackspot from Walayar to
Angamaly
20 Rectification of 11 Nos. 12.1 10.09.2025 63 31.12.2026
black spots/Accident
Spots under Annual Road
Safety Plan for 2023-24 in
the stretch of Walayar-
Angamaly
21 Construction of an 1.1 65 31.05.2027
underpass at km 184.850
and other miscellaneous 20.05.2026
works in Thalassery Mahe
bypass
22 Widening/Development of 124.6 25-06-2025 67 31.03.2027
Existing NH-85
*****