GOVERNMENT OF INDIA
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
LOK SABHA
UNSTARRED QUESTION NO. 2058
ANSWERED ON 30TH JULY, 2026
STATUS OF NATIONAL HIGHWAY PROJECTS IN NASHIK
2058. SHRI RAJABHAU PARAG PRAKASH WAJE:
Will the MINISTER OF ROAD TRANSPORT AND HIGHWAYS
सड़क परिवहन औि िाजमार्ग मंत्री
be pleased to state:
(a) the details and present status of all National Highway projects
sanctioned in Nashik district during the last five years, indicating
project-wise length, cost, physical progress and target completion dates;
(b) the current status of the proposed Nashik Outer Ring Road,
including DPR, land acquisition, financial approval and reasons for the
delay in commencement;
(c) the details and present status of all Greenfield Highway projects
proposed or approved in Nashik district including alignment, land
acquisition and timelines;
(d) whether cost escalation and execution delays have adversely
affected these projects and if so, the reasons and responsibility fixed;
(e) the status of land acquisition and fund release, project-wise; and
(f) the time-bound action plan to complete all pending National
Highway, Outer Ring Road and Greenfield Highway projects before
further cost escalation and inconvenience to the public?
ANSWER
THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS
(SHRI NITIN JAIRAM GADKARI)
(a) The status of all National Highways (NHs) projects sanctioned in
Nashik district during the last five years including current year is
annexed.
(b) The Government in the Ministry of Road Transport and Highways is
primarily responsible for development and maintenance of NHs. Nashik
Outer Ring Road is not a NH and the same is being developed by the
State Government of Maharashtra through its own funds.(c) to (e) The Government has sanctioned construction of 6-lane
access control Greenfield Expressway project from Nashik-Adgoan-
Niphad-Sinnar-Ahilyanagar having total length of 152 km at an estimated
cost of Rs. 9494 Crores. At present, compensation awards for land
acquisition have been declared for 90% area and compensation
disbursed for 25% area. The bids for award of civil construction work are
invited with Bid Due Date on 20.08.2026. The civil construction works
are targeted for completion in Financial Year (FY) 2030-31.
(f) The Government has taken number of steps to ensure timely
completion of NH projects. These include streamlining and expediting
land acquisition using “Bhoomirashi” portal and GIS-based Land
Acquisition Plan, revamping “Parivesh” Portal through Ministry of
Environment, Forest and Climate Change, to facilitate faster forest and
environmental clearances, enabling online approval of General
Arrangement of Drawings (GAD) of Road Over Bridge / Road Under Bridge
(ROB/RUB) from the Railways, and leveraging the mechanism of review
and resolution of bottlenecks / hindrances in ongoing projects, in active
collaboration with the State Governments and other stakeholders.
Government has also launched a web portal for Railway related
clearances with defined timelines for various approvals.
Government has put in place a strong framework using multiple
mechanisms for monitoring project progress and contractor
inefficiencies. Regular review meetings are conducted at various levels
with stakeholders to assess project progress, and critical projects such
as those delayed by more than three years or pending for award /
appointment.
Many State Governments conduct coordination meetings led by the
Chief Secretary to resolve issues affecting project execution. Projects
where issues remain unresolved are escalated for further review through
the Project Monitoring Group and also through “PRAGATI”.ANNEXURE
ANNEXURE REFERRED TO IN REPLY TO PART (a) OF LOK SABHA
UNSTARRED QUESTION NO. 2058 ANSWERED ON 30TH JULY, 2026
ASKED BY SHRI RAJABHAU PARAG PRAKASH WAJE REGARDING
STATUS OF NATIONAL HIGHWAY PROJECTS IN NASHIK.
S. Project Name NH Date of Length Total Scheduled Physical
No No. sanction (km) Project Completion Progress
. Cost date %
(Rs. in
Crores)
1 Rehabilitation and Up- 752G 22.03.2022 37.14 428.80 14.05.2025 Completed
gradation of Satana to
Mangrul (Chandwad)
section of NH-752G
Design Km.64.000 to Km.
101.140 to two / four lane
with paved shoulders in
the state of Maharashtra
on Engineering
procurement &
Construction (EPC) mode
2 Strengthening from 160A 23.02.2022 30.00 37.83 05.10.2023 Completed
Khambale to Pahine
Section (Km. 58.300 to
71.800, 72.800 to 79.100
& 81.800 to 88.600) and
Satgaon to Amboli
Section (Km. 98.200 to
101.600) including
reconstruction of Minor
Bridge & Culverts (5-
Nos) on NH-160 A Sinner -
Ghoti - Trimbakshwer -
Jawahar Road in the
State of Maharashtra
3 Strengthening of existing 60 23.02.2022 8.64 14.11 07.10.2023 Completed
road from Km 177.000
to 185.500 (Section in
Sinnar Town) of Pune -
Nashik Road NH 60 (old
NH50) in the State of
Maharashtra. (Length-
8.636 Km)
4 PQC of existing 848 31.03.2022 0.28 1.57 01.12.2022 Completed
carriageway from Km.
57/00 to 57/284 L=0.284
km Peth to Hattipada
Section of Thane-Nashik-S. Project Name NH Date of Length Total Scheduled Physical
No No. sanction (km) Project Completion Progress
. Cost date %
(Rs. in
Crores)
Peth-Kaparda-Pardi Road
of NH-848 in the State of
Maharashtra.
5 Construction of water 60 24.03.2023 0.39 4.06 22.04.2024 Completed
channel in Shinde village
at Slab culvert
Km.194.200 of Pune
Nashik Road NH-60
6 Construction of Service 60 21.03.2023 1.09 5.67 22.09.2024 Completed
road at Saradwadi village
along Sinnar bypass road
(Pune Nashik road) NH-60
at Km.187.910 to 189.000
7 Rehabilitation & 953 22.02.2024 17.57 125.45 06.04.2027 15%
Upgradation of NH 953
from Km.104.000 to Km.
121.570 section from
Saputara to
Chausale(Gujarat/Mahara
shlra State border) to
2L+PS configuration,
Dist. Nashik in the state
of Maharashtra
8 Strengthening of existing 60 09.11.2023 6.30 19.42 04.02.2025 Completed
6 lane of NH 60 from
km.201.350 to 202.080 &
203.080 to 208.649
section from Nashik road
to Dwarka, Dist. Nashik
in the state of
Maharashtra
9 Construction of 2L 160H 04.03.2024 7.45 73.21 17.03.2027 Recently
Malegaon Bypass to NH started
160H from Km 0.000 to
7.450 in Dist. Nashik in
the State of Maharashtra.
10 Construction of R.O.B at 753J 11.10.2023 1.05 116.62 15.12.2027 2%
LC 115B (Near
Nastanpur) at
Km.126+150 of Nandgaon
Chalisgaon section of NH-
753J in the state of
Maharashtra on EPC
mode
11 Construction of 12 No of 3 01.03.2024 17.35 850.62 31.03.2027 40%
Standalone SafetyS. Project Name NH Date of Length Total Scheduled Physical
No No. sanction (km) Project Completion Progress
. Cost date %
(Rs. in
Crores)
Structures (Package–I) at
different locations on
NH–3 – in the state of
Maharashtra on EPC
mode
12 Six laning of existing 4 3 01.02.2024 19.71 880.99 14.04.2027 35%
lane section from Gonde
(Km. 439.038) to Pimpri-
Sado (Km. 459.905)
section of NH-848 (Old
NH-3) (Design
Length=19.712Km) under
NH(O) in the state of
Maharashtra on Hybrid
Annuity Mode
13 Periodic Renewal of Six 3 17.05.2023 46.00 250.00 13.03.2025 Completed
laned Pimpalgaon-Nashik-
Gonde (Ch. 380.00 to Ch.
439.038) section of NH-03
in the State of
Maharashtra using Thin
White Topping (TWT)
(Excluding EPC-II works
& proposed EPC
structures) on EPC mode
14 Design and Construction 3 15.09.2024 1.22 47.84 31.12.2026 75%
of Vehicular Underpass
as Long-term
rectification work at
MoRTH Blackspot i.e.
Dongarbaba Temple (MH-
04-192) at Ch. 425.510 on
Pimpalgaon-Nashik-
Gonde Section of NH-3 in
the State of Maharashtra
on EPC Mode
15 Upgradation to two lanes 848 02.01.2025 4.53 69.09 27.10.2026 10%
with paved shoulder
configuration from km
38.970 to km 41.816
(Sawal ghat) and km
49.730 to km 51.413
(Kotambi Ghat) of NH-848
in Nashik District in the
State of Maharashtra on
EPC modeS. Project Name NH Date of Length Total Scheduled Physical
No No. sanction (km) Project Completion Progress
. Cost date %
(Rs. in
Crores)
16 Design & Construction of 3 19.06.2024 1.20 48.09 31.12.2026 75%
Vehicular Underpass
(VUP) at Khadakjambat
Ch. 373+430 & Light
Vehicular Underpass
(LVUP) at Ch. 373+650 in
the State of Maharashtra
on EPC Mode
17 Improvement and 160A 21.03.2025 53.10 264.35 30.09.2026 77%
strengthening of existing
2 lane stretch to 2-Lane
with PS (1.5m on both
sides) on Ghoti-Sinnar
section of NH-160A using
Thin White Topping
(200mm thick) in the
State of Maharashtra on
EPC mode
18 Upgradation to Four lane 953 22.09.2025 22.77 107.88 11.06.2027 Recently
with Paved Shoulder started
configuration of the Vani
to Pimpalgaon section of
NH953 from km 136.500
to km 160.500 in the
state of Maharashtra on
EPC mode
19 Upgradation to four lane 848 15.10.2025 36.37 264.47 Bids under -
with paved shoulder evaluation
configuration of the
Nashik to Peth section of
NH-848 from design km
11.600 to km 25.600, km
26.100 to km 38.970, km
41.816 to km 43.600, km
44.200 to km 49.730, km
51.413 to km 53.600
(Length – 36.371 km) in
the state of Maharashtra
on EPC mode.
20 Rehabilitation and 160A 11.03.2026 47.60 1353.50 Bids under -
Upgradation of Ghoti to evaluation
Trimbak section of NH-
160A from km 53.500 to
km 101.100 to four lane
with shoulder
configuration in the StateS. Project Name NH Date of Length Total Scheduled Physical
No No. sanction (km) Project Completion Progress
. Cost date %
(Rs. in
Crores)
of Maharashtra on EPC
Mode
21 Construction of service 60 15.09.2025 12.78 65.72 04.05.2027 2%
road in the intermittent
stretches from Km
180/470 to Km 205/780 on
the Sinnar to Nashik
section of NH-60 in the
State of Maharashtra on
EPC mode
22 Performance Based 753J 30.07.2025 25.99 13.43 08.03.2031 10%
Maintenance Contract
(PBMC) for maintanance
of Chalisgaon to
Nandgaon section of NH-
753J from km 103.000 to
km 104.300 and km
122.250 to km 147.425
[project length = 25.985
km] in the State of
Maharashtra for 5 years
Maintenance Period.
23 Construction of an 60 & 12.01.2026 1.73 213.86 17.02.2027 50%
Interchange at the 848
Dwarka Circle, Nashik in
the State of Maharashtra
on EPC mode.
24 Construction of new 60 14.11.2025 30.28 347.82 17.10.2026 2%
Slip/Service Road on
either side at various
location (total length
30.30 km (LHS+RHS) and
Flyover(2x30m) at
Sawadgaon Phata (Km.
310+415) on Dhule-
Pimpalgaon section of
NH-60 from Km. 261.720
to Km. 380+000 in the
state of Maharashtra on
EPC mode under NH(O)
25 Construction of 6 lane Greenfi30.06.2025 152.00 9494.00 Bids invited -
access controlled eld
Greenfield highway
starting from junction
with NH-60 at Adgaon
(Km.138.160) toS. Project Name NH Date of Length Total Scheduled Physical
No No. sanction (km) Project Completion Progress
. Cost date %
(Rs. in
Crores)
Ahilyanagar (Km.290.000)
in the State of
Maharashtra
26 Construction of 848 14.11.2025 25.14 372.03 26.10.2027 2%
Slip/Service Road on
either side at various
locations total length
25.140 Km (LHS+RHS),
Flyover (2 x 25m) at
Borivali Junction (Km.
528+550) & LVUP (1 X
15M) at Sherekarpada
(Km. 528+800) on EPC
mode under NH (O) in the
state of Maharashtra
27 Widening to 6 lanes of 60 03.06.2026 6.435 221.52 Bids invited -
the Dwarka Circle -
Upanagar Naka - Datta
Mandir Chowk from km
0/260 to km 5/910,
including construction of
2 lane service roads on
both sides of NH-60 in
Nashik city in the State
of Maharashtra on EPC
Mode.
0 605.94 15256.56
*****