GOVERNMENT OF INDIA
DEPARTMENT OF ATOMIC ENERGY
RAJYA SABHA
UNSTARRED QUESTION NO-2242
ANSWERED ON 12/03/2026
STATUS OF POWER PLANTS
2242. SHRI C. VE. SHANMUGAM
Will the PRIME MINISTER be pleased to state:-
(a) the number of nuclear power plants operational in the country and total capacity thereof;
(b) the details of projects which are under various stages of construction;
(c) whether it is a fact that the Kudankulam Nuclear Power Plant has not been made fully
operational;
(d) if so, the details thereof;
(e) the likely date by which all the six units/reactors of the plant would become operational;
and
(f) the action taken by Government to complete the project early?
ANSWER
THE MINISTER OF STATE FOR PERSONNEL, PUBLIC GRIEVANCES & PENSIONS
AND PRIME MINISTER’S OFFICE (DR. JITENDRA SINGH)
(a) At present there are 24 nuclear power plants (excluding RAPS-1 – 100 MW, which is
under prolonged shutdown) operational in the country with total installed capacity of
8,780 MW.
(b) At present, there are 18 nuclear power reactors with a total capacity of 13600 MW under
implementation, comprising of 10 nuclear reactors under construction and 8 reactors
under pre-project activities.
Location Project Capacity (MW)
Projects Under Construction / Commissioning
Rajasthan RAPP-8 700
KKNPP-3&4 2 X 1000
Kudankulam, Tamilnadu
KKNPP-5&6 2 X 1000
Gorakhpur, Haryana GHAVP-1&2 2 X 700
Kaiga, Karnataka Kaiga-5&6 2 X 700
PFBR, Kalpakkam PFBR 1 X 500
Projects Under Pre-project Activities
Gorakhpur, Haryana GHAVP-3&4 2 X 700
Chutka, Madhya Pradesh Chutka-1&2 2 X 700
Mahi Banswara, Mahi Banswara-1&2 2 X 700
Rajasthan Mahi Banswara-3&4 2 X 700BHAVINI is currently commissioning a 500 MWe Prototype Fast Breeder Reactor
(PFBR) project at Kalpakkam, Tamil Nadu. Government has accorded approval to carry
out pre-project activities for 2 x 500 MWe twin unit of FBR 1&2 project at Kalpakkam,
Tamil Nadu. On attaining first criticality of PFBR, Government will be approached for
financial sanction of FBR 1&2 projects.
(c) to (e) The Kudankulam project comprises of six units of 1000 MW LWRs each, being set up
in technical cooperation with the Russian Federation. At present, Units 1&2 (KKNPP
1&2 - 2 X 1000 MW) are already in operation, having been commissioned in the years
2014 & 2017 respectively. The remaining four units of 1000 MW each – KKNPP 3&4
(2X1000 MW) and KKNPP 5&6(2X1000 MW) are under various stages of construction.
(f) The measures taken include, constant monitoring of progress of project activities at
multiple levels, timely identification of constraints & making necessary mid-course
corrections, frequent meetings with vendors/ contractors, re-sequencing of construction
activities to the extent possible etc. to ensure completion of activities expeditiously and
complete the project at the earliest.
*****