GOVERNMENT OF INDIA
MINISTRY OF HOUSING AND URBAN AFFAIRS
LOK SABHA
UNSTARRED QUESTION NO. 755
TO BE ANSWERED ON JULY 23, 2026
STATUS OF PROJECTS UNDER AMRUT 2.0 IN RAJASTHAN
NO. 755 SHRI HANUMAN BENIWAL:
Will the Minister of HOUSING AND URBAN AFFAIRS be pleased to state:
(a) whether it has come to the notice of the Government that several
projects relating to drinking water supply, sewerage, rejuvenation of
water bodies and green space development sanctioned under AMRUT
2.0 in various Urban Local Bodies (ULBs) of Rajasthan have not been
completed within the stipulated time and if so, the reasons therefor;
(b) the details of the Central assistance sanctioned, released, utilised
and currently pending for Rajasthan under the said mission, year and
ULB-wise; and
(c) whether the Government is aware that citizens are facing severe
inconvenience due to excessive delay in works related to drinking
water pipelines, sewerage networks and road excavations in many
cities of Rajasthan and if so, the details thereof along with the action
taken to investigate the causes of these delays and fix the
accountability of the concerned agencies?
ANSWER
THE MINISTER OF STATE IN THE
MINISTRY OF HOUSING AND URBAN AFFAIRS
(SHRI TOKHAN SAHU)
(a) to (c): Under Atal Mission for Rejuvenation and Urban Transformation
(AMRUT) 2.0, States/ Union Territories are empowered to select,
appraise, prioritise and implement the projects. Under AMRUT 2.0, the
State of Rajasthan has taken up 363 projects worth ₹11,560.07 crore
(including operation and maintenance cost), which includes Central
Assistance (CA) of ₹3,552 crore. The approved projects include 178
water supply projects worth ₹5099.47 crore, 48 sewerage and septage
management projects worth ₹5950.85 crore, 134 water body
rejuvenation projects worth ₹505.41 crore and 3 parks and green space
projects worth ₹4.33 crore.
…2/--2-
Central share of funds under AMRUT 2.0 are released to the States/ UTs
and not Urban Local Body (ULB)-wise. The State further distribute the
funds to the ULBs as per progress of the projects. Up to the Financial
Year (FY) 2025–26, CA amounting to ₹745.12 crore was released for
AMRUT 2.0 projects to the State of Rajasthan. During the current year
(FY 2026-27), Mother Sanction for ₹250 crore has been released for
projects of which ₹104.44 crore has been utilised as on 20.07.2026.
The projects under AMRUT 2.0 are implemented by the States/ UTs. The
State has informed that 109 water supply projects of ₹1428.90 crore, 42
sewerage and septage management projects of ₹4656.80 crore and 129
water body rejuvenation projects of ₹443.86 crore have been awarded.
As informed by the State, there have been some issues faced during the
execution of projects such as delay in allotment of land/ area due to
Court Cases/ local public hinderances; delay in receiving permission from
various departments as Forest/ National Highway Authority of India
(NHAI)/ Railway/ Public Works Department (PWD) etc.; delay in execution
due to imposition of Graded Response Action Plan (GRAP) in National
Capital Region (NCR) cities; ban on construction work by the High Court,
etc.
The State Government has also informed that it is aware of the
temporary inconvenience during the execution of works, including road
excavation. The progress of these works is regularly reviewed, and
necessary efforts have been made to remove the hindrances affecting
their execution. The concerned agencies have been directed to expedite
the works and restore the roads after completion.
*****