GOVERNMENT OF INDIA
MINISTRY OF POWER
RAJYA SABHA
UNSTARRED QUESTION NO.1910
ANSWERED ON 09.03.2026
STATUS OF REVENUE AND PROGRESS OF DUL HASTI HYDROELECTRIC PROJECT
1910. SHRI SAJJAD AHMAD KICHLOO:
Will the Minister of POWER be pleased to state:
(a) the total revenue earned to date from the operational Dul Hasti Hydroelectric power project,
Kishtwar, J and K;
(b) the current status of Dul Hasti Stage II project in term of approval, construction timeline and
financial outlay;
(c) whether Government is proceeding with the original commitment for phase II to be executed
as a joint venture between NHPC Ltd. and CVPPL or has that arrangement been changed; and
(d) the locals who gave land for Phase I and were promised jobs against that, not yet have been
employed, whether they will be considered for jobs in Phase II as part of project benefits?
A N S W E R
THE MINISTER OF STATE IN THE MINISTRY OF POWER
(SHRI SHRIPAD NAIK)
(a): Dulhasti Power Station (390 MW) has been developed by NHPC Limited with financing
through equity and loans / market borrowings. Revenue from the project is being realised since its
commissioning in April, 2007 from sale of power at the tariff determined by the Central Electricity
Regulatory Commission (CERC) in accordance with applicable CERC tariff regulations. A significant
portion of the revenue generated is utilised towards meeting Operation & Maintenance (O&M)
expenses, debt servicing and other obligations. The earning of NHPC Limited from the project is
limited only to the Return on Equity (RoE).
(b): Central Electricity Authority (CEA) has concurred the Detailed Project Report (DPR) of
Dulhasti Stage-II Hydro Electric Project (HEP) (260 MW) on 26.05.2025. Environmental Clearance
has been accorded on 07.01.2026, while Forest Clearance is not required as no forest land is involved.
Further, the Board of Directors of NHPC Limited, on 20.02.2026, has accorded investment approval
of the project. The construction timeline of the project is 44 months.
(c): Based on Memorandum of Understanding (MoU) signed between NHPC Limited & JKSPDCL
on 03.01.2021 wherein considering operational aspects, cost efficiency, construction & operational
ease, economies of scale and to ensure synergy with Dulhasti Phase-I of the project, it has been agreed
for execution of Dulhasti Stage-II HEP by NHPC Limited on BOOT (Build-Own-Operate-Transfer)
basis.
(d): The acquisition of private land for the Dulhasti Stage-II HEP is being done in accordance with
the provisions of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation
and Resettlement Act, 2013 (RFCTLARR Act, 2013). All admissible benefits to the Project Affected
Families (PAFs) are envisaged as per the applicable provisions of the R&R Scheme.
In case of Dulhasti Power Station, jobs have been provided to the PAFs and, at present, there
are no pending cases related to providing jobs to PAFs.
*******