GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 681
TO BE ANSWERED ON 22.07.2026
STATUS OF THE ANGAMALY SABARI RAILWAY LINE
681. ADV DEAN KURIAKOSE:
Will the Minister of RAILWAYS be pleased to state:
(a) the current status of the Angamaly Sabari railway line;
(b) the details of the estimated updated cost of the project as on date;
(c) whether the Kerala State Government of Kerala has to enter into a
tripartite agreement with the Railway Ministry as well as the RBI for
the implementation of the project; and
(d) if so, the details thereof?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (d): Angamali - Sabarimala via Erumeli new line project was
sanctioned in 1997-98. Work on Angamali-Kaladi (7 Km) and long lead
works on Kaladi-Perumbavoor (10 Km) was taken up. However, further
works on this project could not be taken forward due to protests by people
against land acquisition and fixing of alignment of the line, court cases
filed against the project and inadequate support from the Government of
Keralam. Therefore, the project could not proceed ahead.
§ Page 1 of 5The estimated cost of the Angamali - Sabarimala via Erumeli new line
project was updated at ₹3,801 crore and submitted to Government of
Keralam for the acceptance of the estimate and willingness to share cost
of the project.
In August 2024, the Government of Keralam communicated their
conditional consent. Government of Keralam was requested by Railway to
submit unconditional consent for sharing the cost.
Then the Minister of Railways requested the Chief Minister of Keralam to
acquire land using their share of 50% of the cost of the project.
Now, on the request of Govt. of India, the Govt. of Keralam has initiated
land acquisition proceedings and the Angamali – Sabarimala new line
project has moved forward. Ministry of Railways is following up the land
acquisition process with Govt. of Keralam. During 2026-27, an outlay of
₹505 crore has been provided for this project by Ministry of Railways.
Keralam:-
Railway Budget:-
Budget allocation in the recent years has increased significantly. Budget
allocation for infrastructure projects and safety works, falling
fully/partly in the State of Keralam is as under:-
Period Outlay
2009-14 ₹ 372 crore/year
2026-27 ₹3,795 crore (more than 10 times)
Page 2 of 5Projects Sanctioned:-
As on 01.04.2026, 09 projects (03 new line and 06 doubling) of 302 km
length, costing ₹11,650 crore falling fully/partly in Keralam are sanctioned.
The summary is as under:-
Category No. of Total Length Total Expenditure
projects Length Commissioned upto March, 2026
(in Km) upto March, 2026 (₹ in Cr.)
(in Km)
New line 03 148 0 317
Doubling 06 154 40 3,550
/multitracking
Total 09 302 40 3,867
Recently Completed Projects:-
Details of some of the recently completed projects falling fully/partly in the
State of Keralam are as under:
S. Project Cost
No. (₹ in Crores)
1 Dindigul - Palghat & Pollachi - Coimbatore gauge 1,360
conversion (217 km)
2 Quilon- Tiruchendur gauge conversion (357 km) 1,122
3 Mulanturutti-Kuruppantara doubling (24 km) 303
4 Chenganur-Chingavanam doubling (27 km) 436
5 Ambalapuzha-Haripad doubling (18 km) 346
6 Kurruppanthara-Chingavanam doubling (27 km) 749
Ongoing Projects:-
Some of the projects falling fully/partly in the State of Keralam which have
been taken up are as under:
Page 3 of 5S No. Project Cost
(₹ in Crores)
1 Tirunnavaya –Guruvayur new line (35 km) 144
2 Angamali-Sabarimala new line (111 km) 3,801
3 Ernakulam-Kumbalam doubling (8 km) 808
4 Kumbalam - Thuravur doubling (16 km) 1,172
5 Trivandrum- Kanyakumari doubling (87 km) 4,494
6 Alappuzha-Ambalapuzha doubling (13 km) 324
7 Turavur - Mararikulam doubling (21 km) 451
8 Mararikulam-Alappuzha doubling (11 km) 221
Execution of important infrastructure projects falling fully/partly in the
State of Keralam are held up due to delay in land acquisition. Status of land
acquisition in the State of Keralam is as under:
Total Land required for Projects in Keralam 618 ha
Land Acquired 78 ha (13%)
Balance Land to be acquired 540 ha (87%)
Railway had deposited ₹1,976 crore for land acquisition to Government of
Keralam. Support of the Government of Keralam is needed to expedite the
land acquisition. For instance, details of some major projects which are
delayed due to land acquisition are as under:-
SN Name of the project Total Land Balance
land acquired Land to be
required (in Ha) acquired
(in Ha) (in Ha)
1. Angamali - Sabarimala new line 304 25 279
(111 km)
2. Ernakulam – Kumbalam Patch 4 3 1
doubling (8 km)
Page 4 of 53. Kumbalam – Turavur Patch doubling 10 9 1
(16 km)
4. Shoranur-Vallathol doubling (10 Km) 5 0 5
Government of India is geared up to execute projects, however success
depends upon the support of Government of Keralam.
Sanction of any railway project depends upon many parameters/factors
which include the following:
Anticipated traffic projections and remunerativeness of the
proposed route
First and last mile connectivity provided by the project
Connection of missing links and providing additional route
Augmentation of congested/saturated lines
Demands raised by State Governments/Central Ministries/Public
representatives
Railway’s own operational requirements
Socio-economic considerations
Overall availability of funds
Completion of Railway project/s depends on various factors which include
the following:
Land acquisition by State Government
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
*****